ALTUS 24
by JINDAL TODAY INFRA LLP (Micron) · Trans-Thana Creek Industrial Area, ThaneAlso near Airoli
Possession date of ALTUS 24: 30 January 2033. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1330002600534, and currently active. Its completion date is now January 2033, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ALTUS 24?
How the possession date of ALTUS 24 has moved
30 September 2032
Completion date given when the project was registered
30 January 2033
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ALTUS 24’s extension records on MahaRERA (PR1330002600534), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ALTUS 24
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2033 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1330002600534
- Status
- Registered and active
- Builder
- JINDAL TODAY INFRA LLP
- Location
- Trans-Thana Creek Industrial Area, Thane · 400708
- Project type
- Residential / Group Housing
- Registered on
- 25 May 2026
- Completion date at registration
- September 2032
- Latest completion date
- January 2033
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 154
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of ALTUS 24, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RESIDENTIAL (A) | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RESIDENTIAL (A): covers 2 BASEMENTS+ GROUND FLOOR+ 27 FLOORS
Latest CC order on MahaRERA: dated 04/04/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ALTUS 24 every month.
ALTUS 24: buildings, flats and land, as filed on MahaRERA
- Buildings: RESIDENTIAL (A) (30 floors, 154 units)
- Car parking: 239 covered
- Land: 8,100 sq m (about 2.0 acres) · sanctioned built-up 18,365 sq m
- Boundaries filed include: MIDC Road, Thana Belapur Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Today Global Homes (a group of 18 linked companies) has 40 projects on MahaRERA since 2017, this one included. Of the 40 GharKundli has checked: 18 finished, 13 within the promised date and 5 needed more time (typically 6 months); 20 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 50 complaints on MahaRERA across 10 projects.
Read Google reviews of ALTUS 24 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ALTUS 24: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ALTUS 24
What is the possession date of ALTUS 24?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ALTUS 24 in Trans-Thana Creek Industrial Area, Thane is 30 January 2033, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ALTUS 24?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ALTUS 24's builder has filed on MahaRERA, the official one, is 30 January 2033, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ALTUS 24?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ALTUS 24 in Trans-Thana Creek Industrial Area, Thane is PR1330002600534.
Is ALTUS 24 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24 is registered as PR1330002600534 and its status is "Registered and active".
What is the construction status of ALTUS 24?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RESIDENTIAL (A) is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does ALTUS 24 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is ALTUS 24 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24 is registered on MahaRERA as PR1330002600534, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ALTUS 24's possession date changes?
The latest dates are on ALTUS 24's MahaRERA page (PR1330002600534). GharKundli's Kundli Watch sends a free WhatsApp update on ALTUS 24 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ALTUS 24 have?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24 has one building filed: RESIDENTIAL (A) with 30 floors and 154 units.
How much parking does ALTUS 24 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 239 covered car parking spaces for ALTUS 24.
How big is the land of ALTUS 24?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24 stands on 8,100 sq m of land (about 2.0 acres), with 18,365 sq m of sanctioned built-up area.
What is the track record of ALTUS 24's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Today Global Homes (a group of 18 linked companies) has 40 projects on MahaRERA since 2017, this one included. Of the 40 GharKundli has checked: 18 finished, 13 within the promised date and 5 needed more time (typically 6 months); 20 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 50 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ALTUS 24?
Google Maps has reviews of ALTUS 24 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ALTUS 24?
ALTUS 24 by JINDAL TODAY INFRA LLP (Micron) is in Trans-Thana Creek Industrial Area, Thane (pincode 400708), near Airoli, Maharashtra, and is registered on MahaRERA as PR1330002600534, per GharKundli's check of MahaRERA records. Its boundaries filed there include MIDC Road, Thana Belapur Road.
How many homes are in ALTUS 24?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24 has 154 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was ALTUS 24 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ALTUS 24 was registered on MahaRERA on 25 May 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on ALTUS 24?
No court cases are listed for ALTUS 24 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ALTUS 24?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JINDAL TODAY INFRA LLP, the company Micron files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ALTUS 24
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- LOTUS
- Panache
- Mahavir Breeze Phase 1
Other projects by JINDAL TODAY INFRA LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.