Runwal One-Tower D1
by Runwal Developers Limited · Sandozbaugh, Thane
Possession date of Runwal One-Tower D1: 30 January 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1330002502798, and currently active. Its completion date is now January 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Runwal One-Tower D1?
How the possession date of Runwal One-Tower D1 has moved
30 September 2030
Completion date given when the project was registered
30 January 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Runwal One-Tower D1’s extension records on MahaRERA (PR1330002502798), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Runwal One-Tower D1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 6 court cases, and how it ended
- Construction pace against the January 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Runwal One- Tower D2PR1330002502886 · possession 30 Nov 2031
- Runwal One-Tower EPR1330002503071 · possession 31 May 2031
- MahaRERA registration
- PR1330002502798
- Status
- Registered and active
- Builder
- Runwal Developers Limited
- Location
- Sandozbaugh, Thane · 400607
- Project type
- Residential / Group Housing
- Registered on
- 16 Mar 2026
- Completion date at registration
- September 2030
- Latest completion date
- January 2031
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 282
- Sold or booked
- 19%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 6
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of Runwal One-Tower D1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG. TYPE- D1 | 100% | 23% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLDG. TYPE- D1: covers 59 floors
Latest CC order on MahaRERA: dated 05/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Runwal One-Tower D1 every month.
Runwal One-Tower D1: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG. TYPE- D1 (59 floors, 282 units)
- Car parking: 187 covered
- Land: 58,730 sq m (about 14.5 acres) · sanctioned built-up 32,653 sq m · recreational space 5,974 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Runwal One-Tower D1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Runwal One-Tower D1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Runwal One-Tower D1
What is the possession date of Runwal One-Tower D1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Runwal One-Tower D1 in Sandozbaugh, Thane is 30 January 2031, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Runwal One-Tower D1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Runwal One-Tower D1's builder has filed on MahaRERA, the official one, is 30 January 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Runwal One-Tower D1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Runwal One-Tower D1 in Sandozbaugh, Thane is PR1330002502798.
Is Runwal One-Tower D1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1 is registered as PR1330002502798 and its status is "Registered and active".
What is the construction status of Runwal One-Tower D1?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLDG. TYPE- D1 is 23% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Runwal One-Tower D1 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Runwal One-Tower D1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1 is registered on MahaRERA as PR1330002502798, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Runwal One-Tower D1 have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Runwal One- Tower D2 (PR1330002502886, possession 30 Nov 2031); Runwal One-Tower E (PR1330002503071, possession 31 May 2031). Check that your agreement names the registration of your own wing.
How can I get updates if Runwal One-Tower D1's possession date changes?
The latest dates are on Runwal One-Tower D1's MahaRERA page (PR1330002502798). GharKundli's Kundli Watch sends a free WhatsApp update on Runwal One-Tower D1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Runwal One-Tower D1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1 has one building filed: BLDG. TYPE- D1 with 59 floors and 282 units.
How much parking does Runwal One-Tower D1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 187 covered car parking spaces for Runwal One-Tower D1.
How big is the land of Runwal One-Tower D1?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1 stands on 58,730 sq m of land (about 14.5 acres), with 32,653 sq m of sanctioned built-up area and 5,974 sq m of recreational open space.
Where can I read reviews of Runwal One-Tower D1?
Google Maps has reviews of Runwal One-Tower D1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Runwal One-Tower D1?
Runwal One-Tower D1 by Runwal Developers Limited is in Sandozbaugh, Thane (pincode 400607), Maharashtra, and is registered on MahaRERA as PR1330002502798, per GharKundli's check of MahaRERA records.
How many homes are in Runwal One-Tower D1?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1 has 282 homes in 1 tower registered on MahaRERA, and 19% of them are sold or booked.
When was Runwal One-Tower D1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Runwal One-Tower D1 was registered on MahaRERA on 16 March 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on Runwal One-Tower D1?
6 court cases are listed for Runwal One-Tower D1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Runwal One-Tower D1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Runwal Developers Limited, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Runwal One-Tower D1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Thane →
Other projects in pincode 400607
- UNIQUE VISTAS-BLDG. NO. 3
- UNIQUE VISTAS-BLDG. NO. 5
- Godrej Exquisite
- Elanor - Tower 1
- Elanor - Tower 2
- Lodha Kolshet A2 - Tower 3
- Sector B- Tower A and B
- Hiranandani Westgate - Hampstead
Other projects by Runwal Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.