KANAKIA PARIS
by KANAKIA SPACES REALTY PRIVATE LIMITED · Andheri East, MumbaiAlso near Khar West, Santacruz West, Bandra West
Possession: KANAKIA PARIS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800000122. Status: Completed. 11 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KANAKIA PARIS?
How the possession date of KANAKIA PARIS has moved
30 September 2019
Completion date given when the project was registered
28 June 2021
Extended at the builder's request (MahaRERA application EXT51800002488)
Reason the builder gave MahaRERA:
“The Real Estate Project namely “Kanakia Paris” was assigned Registration No. P51800000122 and Authority has issued Certificate of Registration dated 05.07.2017. The Registration is valid for a period commencing from 05/07/2017 and ending wi…” Read the full reason
“The Real Estate Project namely “Kanakia Paris” was assigned Registration No. P51800000122 and Authority has issued Certificate of Registration dated 05.07.2017. The Registration is valid for a period commencing from 05/07/2017 and ending with 30/09/2019. The Construction of the Project is duly completed and we have started handing over possession of the flats to the Allottees. We have received Occupation Certificate for the Real Estate Project save and except 4 (Four) flats in Tower G on 3.04.2019. Copy of the Occupation Certificate is already uploaded on the MahaRera website. The occupatio…”28 December 2021
Revised completion date on MahaRERA
Source: KANAKIA PARIS’s extension records on MahaRERA (P51800000122), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KANAKIA PARIS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 11 complaints, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800000122
- Status
- Completed
- Builder
- KANAKIA SPACES REALTY PRIVATE LIMITED
- Location
- Andheri East, Mumbai · 400052
- Project type
- Residential / Group Housing
- Registered on
- 5 Jul 2017
- Completion date at registration
- September 2019
- Latest completion date
- December 2021
- Delay so far
- 27 months
- Homes
- 470
- Towers
- 1
- Complaints on MahaRERA
- 11
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of KANAKIA PARIS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KANAKIA PARIS | 100% | 100% | 97% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KANAKIA PARIS every month.
KANAKIA PARIS: buildings, flats and land, as filed on MahaRERA
- Buildings: KANAKIA PARIS (25 floors)
- Land: 7,359 sq m (about 1.8 acres) · sanctioned built-up 47,747 sq m · recreational space 537 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Kanakia Future Realty (a group of 4 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 15 finished, 13 within the promised date and 2 needed more time (typically 23 months); 4 still being built, none past the promised date yet. 80 complaints on MahaRERA across 13 projects.
Read Google reviews of KANAKIA PARIS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KANAKIA PARIS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KANAKIA PARIS
What is the possession date of KANAKIA PARIS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KANAKIA PARIS in Andheri East, Mumbai is 28 December 2021 — 27 months later than 30 September 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KANAKIA PARIS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KANAKIA PARIS's builder has filed on MahaRERA, the official one, is 28 December 2021, already 27 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KANAKIA PARIS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS's builder applied to MahaRERA to extend the completion date once: to 28 June 2021, giving the reason "The Real Estate Project namely “Kanakia Paris” was assigned Registration No. P51800000122 and Authority has issued Certificate of Registration dated 05.07.2017. The Registration is valid for a period commencing from 05/07/2017 and ending with 30/09/2019. The Construction of the Project is duly completed and we have started handing over possession of the flats to the Allottees. We have received Occupation Certificate for the Real Estate Project save and except 4 (Four) flats in Tower G on 3.04.2019. Copy of the Occupation Certificate is already uploaded on the MahaRera website. The occupatio…".
What is the RERA number of KANAKIA PARIS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KANAKIA PARIS in Andheri East, Mumbai is P51800000122.
Is KANAKIA PARIS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS is registered as P51800000122 and its status is "Completed".
What is the construction status of KANAKIA PARIS?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS's status on MahaRERA is "Completed". As filed by the builder, slab work on KANAKIA PARIS is 100% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.
Does KANAKIA PARIS have complaints on MahaRERA?
11 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KANAKIA PARIS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS is registered on MahaRERA as P51800000122, its MahaRERA status is "Completed", its completion date has moved 27 months since registration and 11 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KANAKIA PARIS's possession date changes?
The latest dates are on KANAKIA PARIS's MahaRERA page (P51800000122). GharKundli's Kundli Watch sends a free WhatsApp update on KANAKIA PARIS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KANAKIA PARIS have?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS has one building filed: KANAKIA PARIS with 25 floors.
How big is the land of KANAKIA PARIS?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS stands on 7,359 sq m of land (about 1.8 acres), with 47,747 sq m of sanctioned built-up area and 537 sq m of recreational open space.
What is the track record of KANAKIA PARIS's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Kanakia Future Realty (a group of 4 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 15 finished, 13 within the promised date and 2 needed more time (typically 23 months); 4 still being built, none past the promised date yet. 80 complaints on MahaRERA across 13 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KANAKIA PARIS?
Google Maps has reviews of KANAKIA PARIS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 11 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KANAKIA PARIS?
KANAKIA PARIS by KANAKIA SPACES REALTY PRIVATE LIMITED is in Andheri East, Mumbai (pincode 400052), near Khar West, Santacruz West, Bandra West, Maharashtra, and is registered on MahaRERA as P51800000122, per GharKundli's check of MahaRERA records.
How many homes are in KANAKIA PARIS?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS has 470 homes in 1 tower registered on MahaRERA.
When was KANAKIA PARIS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KANAKIA PARIS was registered on MahaRERA on 5 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KANAKIA PARIS?
No court cases are listed for KANAKIA PARIS on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KANAKIA PARIS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KANAKIA SPACES REALTY PRIVATE LIMITED, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KANAKIA PARIS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Andheri East
- SHIVSAI SRA CHS
- CRESCENT WESTERN TRADE CENTER - T2
- 140 SHER - E- PUNJAB
- saroj sadan CHSL
- AMEY APARTMENTS
- 93 PALLADIAN
- ASHTAVINAYAK APARTMENTS
- DIVYA DARPAN CO- OP HSG SOCIETY LTD
Other projects by KANAKIA SPACES REALTY PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.