LAKHANIS ORCHID WOODS
by LAKHANI CONSTRUCTIONS LLP · Khopoli, RaigarhAlso near Chinchavali Shekin, Jagdish Nagar
Possession date of LAKHANIS ORCHID WOODS: 30 November 2027, moved from 31 July 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000002927, and currently active. Its completion date has moved from July 2023 to November 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 15 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about LAKHANIS ORCHID WOODS?
How the possession date of LAKHANIS ORCHID WOODS has moved
31 July 2023
Completion date given when the project was registered
30 July 2024
Extended at the builder's request (MahaRERA application EXT52000017266)
Reason the builder gave MahaRERA:
“1-In the year 2022 -23 there was extended monsoon till month of Nov 22 which has impacted our infrastructure and were not able to mobilize the construction material. 2-There is a ban from Maharashtra Government on Quarries due to that the c…” Read the full reason
“1-In the year 2022 -23 there was extended monsoon till month of Nov 22 which has impacted our infrastructure and were not able to mobilize the construction material. 2-There is a ban from Maharashtra Government on Quarries due to that the construction material was not available at site due to which the entire activity got affected.”30 July 2027
Extended at the builder's request (MahaRERA application EXT52000024471)
Reason the builder gave MahaRERA:
“This Project is for 11 Buildings knowns as “A”, “B”, “C”, “D”, “E”, “F”, “G”, “H”, “I”, “J” & “K” in 2 phases. In 1st Phase we are constructing 6 buildings viz. “A”, “B”, “C”, “D”, “E” & “F” and have completed the 4 buildings viz. 7 buildin…” Read the full reason
“This Project is for 11 Buildings knowns as “A”, “B”, “C”, “D”, “E”, “F”, “G”, “H”, “I”, “J” & “K” in 2 phases. In 1st Phase we are constructing 6 buildings viz. “A”, “B”, “C”, “D”, “E” & “F” and have completed the 4 buildings viz. 7 buildings viz. “A”, “B”, “C”, “D” and have obtained OC for “A”, “B” & “D” building and have applied for OC for the “C” building. The remaining 2 building viz. “E” and “F” are on the verge of completion very soon. We are also planning to start booking for 2nd phase buildings viz. “G”, “H”, “I”, “J” & “K” which required 3 years time. The reason for delay is as und…”30 November 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: LAKHANIS ORCHID WOODS’s extension records on MahaRERA (P52000002927), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on LAKHANIS ORCHID WOODS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 15 complaints, and how it ended
- Construction pace against the November 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000002927
- Status
- Registered and active
- Builder
- LAKHANI CONSTRUCTIONS LLP
- Location
- Khopoli, Raigarh · 410202
- Project type
- Others
- Registered on
- 4 Aug 2017
- Completion date at registration
- July 2023
- Latest completion date
- November 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 617
- Towers
- 21
- Complaints on MahaRERA
- 15
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
Construction progress of LAKHANIS ORCHID WOODS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 100% | 100% | 75% |
| A WING PROPOSED | 0% | 0% | 0% | 0% |
| B WING | 100% | 100% | 100% | 75% |
| C WING | 100% | 100% | 60% | 19% |
| D WING | 100% | 100% | 100% | 90% |
| E WING | 100% | 100% | 35% | 10% |
| F WING | 100% | 100% | 35% | 13% |
| G WING | 100% | 30% | 0% | 0% |
| H WING | 0% | 0% | 0% | 0% |
| I WING | 0% | 0% | 0% | 0% |
| J WING | 0% | 0% | 0% | 0% |
| K WING | 0% | 0% | 0% | 0% |
| B WING PROPOSED | 0% | 0% | 0% | 0% |
| C WING PROPOSED | 0% | 0% | 0% | 0% |
| F WING PROPOSED | 0% | 0% | 0% | 0% |
| G WING PROPOSED | 0% | 0% | 0% | 0% |
| H WING PROPOSED | 0% | 0% | 0% | 0% |
| I WING PROPOSED | 0% | 0% | 0% | 0% |
| J WING PROPOSED | 0% | 0% | 0% | 0% |
| K WING PROPOSED | 0% | 0% | 0% | 0% |
| COMMERCIAL | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAKHANIS ORCHID WOODS every month.
LAKHANIS ORCHID WOODS: buildings, flats and land, as filed on MahaRERA
- Buildings: A WING (13 floors) · B WING (14 floors) · C WING (14 floors) · D WING (13 floors) · E WING (14 floors) · F WING (13 floors) · G WING (9 floors) · H WING (9 floors) · and 3 more
- Land: 20,000 sq m (about 4.9 acres) · sanctioned built-up 21,478 sq m · recreational space 1,937 sq m
- Boundaries filed include: GARDEN
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of LAKHANIS ORCHID WOODS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LAKHANIS ORCHID WOODS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LAKHANIS ORCHID WOODS
What is the possession date of LAKHANIS ORCHID WOODS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LAKHANIS ORCHID WOODS in Khopoli, Raigarh is 30 November 2027 — 48 months later than 31 July 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for LAKHANIS ORCHID WOODS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LAKHANIS ORCHID WOODS's builder has filed on MahaRERA, the official one, is 30 November 2027, already 48 months later than the 31 July 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of LAKHANIS ORCHID WOODS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS's builder applied to MahaRERA to extend the completion date 2 times: to 30 July 2024, giving the reason "1-In the year 2022 -23 there was extended monsoon till month of Nov 22 which has impacted our infrastructure and were not able to mobilize the construction material. 2-There is a ban from Maharashtra Government on Quarries due to that the construction material was not available at site due to which the entire activity got affected."; to 30 July 2027, giving the reason "This Project is for 11 Buildings knowns as “A”, “B”, “C”, “D”, “E”, “F”, “G”, “H”, “I”, “J” & “K” in 2 phases. In 1st Phase we are constructing 6 buildings viz. “A”, “B”, “C”, “D”, “E” & “F” and have completed the 4 buildings viz. 7 buildings viz. “A”, “B”, “C”, “D” and have obtained OC for “A”, “B” & “D” building and have applied for OC for the “C” building. The remaining 2 building viz. “E” and “F” are on the verge of completion very soon. We are also planning to start booking for 2nd phase buildings viz. “G”, “H”, “I”, “J” & “K” which required 3 years time. The reason for delay is as und…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of LAKHANIS ORCHID WOODS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LAKHANIS ORCHID WOODS in Khopoli, Raigarh is P52000002927.
Is LAKHANIS ORCHID WOODS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS is registered as P52000002927 and its status is "Registered and active".
What is the construction status of LAKHANIS ORCHID WOODS?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 21 towers. GharKundli's full report compares construction progress with the deadline.
Does LAKHANIS ORCHID WOODS have complaints on MahaRERA?
15 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is LAKHANIS ORCHID WOODS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS is registered on MahaRERA as P52000002927, its completion date has moved 48 months since registration and 15 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LAKHANIS ORCHID WOODS's possession date changes?
The latest dates are on LAKHANIS ORCHID WOODS's MahaRERA page (P52000002927). GharKundli's Kundli Watch sends a free WhatsApp update on LAKHANIS ORCHID WOODS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LAKHANIS ORCHID WOODS have?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS has 11 buildings filed: A WING with 13 floors; B WING with 14 floors; C WING with 14 floors; D WING with 13 floors; E WING with 14 floors; F WING with 13 floors; and 5 more.
How big is the land of LAKHANIS ORCHID WOODS?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS stands on 20,000 sq m of land (about 4.9 acres), with 21,478 sq m of sanctioned built-up area and 1,937 sq m of recreational open space.
Where can I read reviews of LAKHANIS ORCHID WOODS?
Google Maps has reviews of LAKHANIS ORCHID WOODS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 15 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LAKHANIS ORCHID WOODS?
LAKHANIS ORCHID WOODS by LAKHANI CONSTRUCTIONS LLP is in Khopoli, Raigarh (pincode 410202), near Chinchavali Shekin, Jagdish Nagar, Maharashtra, and is registered on MahaRERA as P52000002927, per GharKundli's check of MahaRERA records. Its boundaries filed there include GARDEN.
How many homes are in LAKHANIS ORCHID WOODS?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS has 617 homes in 21 towers registered on MahaRERA.
When was LAKHANIS ORCHID WOODS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAKHANIS ORCHID WOODS was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on LAKHANIS ORCHID WOODS?
No court cases are listed for LAKHANIS ORCHID WOODS on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of LAKHANIS ORCHID WOODS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAKHANI CONSTRUCTIONS LLP.
Check it yourself on MahaRERA
- How to check the possession date of LAKHANIS ORCHID WOODS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Khopoli
- DECCAN RESIDENCY C WING
- ROYAL PARADISE
- SERENITY 2
- SWARANJALI HEIGHTS
- VAYM TOWERS
- SUDARSHAN HEIGHTS
- City Of Music Phase II
- SAFFRON TOWER
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.