Skip to content
GharKundli

Xrbia Warai / Neral - Ph 2

by XRBIA WARAI DEVELOPERS PRIVATE LIMITED · Warai, Raigarh

Possession date of Xrbia Warai / Neral - Ph 2: 29 December 2022, moved from 30 June 2021 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000004499. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project. 24 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about Xrbia Warai / Neral - Ph 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Xrbia Warai / Neral - Ph 2 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 29 June 2022

    Extended at the builder's request (MahaRERA application EXT52000009652)

    Reason the builder gave MahaRERA: “Construction activity couldn’t be carried out during year 2019 due to excessive rainfall in theproject area. Also Reduced Labour and Material availability due to continued and intermittentlockdowns.”
  3. 29 December 2022

    Revised completion date on MahaRERA

Source: Xrbia Warai / Neral - Ph 2’s extension records on MahaRERA (P52000004499), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Xrbia Warai / Neral - Ph 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 24 complaints, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000004499
Status
Lapsed (registration period ended)
Builder
XRBIA WARAI DEVELOPERS PRIVATE LIMITED
Location
Warai, Raigarh · 410201
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2022
Delay so far
18 months
Homes
1,281
Towers
20
Complaints on MahaRERA
24
Court cases listed
0
Appeals at the tribunal
2
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Xrbia Warai / Neral - Ph 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A3100%100%57%0%
A4100%100%57%0%
B4100%100%100%80%
C1100%100%62%0%
C2100%100%66%0%
C3100%100%50%0%
C4100%100%60%0%
C6100%100%94%43%
C8100%100%91%0%
C9100%100%98%43%
D8100%100%100%85%
E1100%100%60%0%
F1100%100%76%0%
K1100%100%100%80%
K2100%100%100%30%
K3100%100%98%30%
K4100%100%88%0%
K6100%100%91%0%
K7100%100%52%0%
K8100%11%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Xrbia Warai / Neral - Ph 2 every month.

Xrbia Warai / Neral - Ph 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: A3 (9 floors) · A4 (9 floors) · B4 (5 floors) · C1 (7 floors) · C2 (7 floors) · C3 (7 floors) · C4 (5 floors) · C6 (5 floors) · and 12 more
  • Land: 9,127 sq m (about 2.3 acres) · sanctioned built-up 49,991 sq m · recreational space 9,035 sq m
  • Boundaries filed include: River

The builder’s record and reviews

Xrbia Warai Developers has 8 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, none past the promised date yet; 3 lapsed. 56 complaints on MahaRERA across 3 projects.

Read Google reviews of Xrbia Warai / Neral - Ph 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Xrbia Warai / Neral - Ph 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Xrbia Warai / Neral - Ph 2

What is the possession date of Xrbia Warai / Neral - Ph 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Xrbia Warai / Neral - Ph 2 in Warai, Raigarh is 29 December 2022 — 18 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Xrbia Warai / Neral - Ph 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Xrbia Warai / Neral - Ph 2's builder has filed on MahaRERA, the official one, is 29 December 2022, already 18 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Xrbia Warai / Neral - Ph 2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2's builder applied to MahaRERA to extend the completion date once: to 29 June 2022, giving the reason "Construction activity couldn’t be carried out during year 2019 due to excessive rainfall in theproject area. Also Reduced Labour and Material availability due to continued and intermittentlockdowns.".

What is the RERA number of Xrbia Warai / Neral - Ph 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Xrbia Warai / Neral - Ph 2 in Warai, Raigarh is P52000004499.

Is Xrbia Warai / Neral - Ph 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2 is registered as P52000004499 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Xrbia Warai / Neral - Ph 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 11% to 100% across 20 towers. GharKundli's full report compares construction progress with the deadline.

Does Xrbia Warai / Neral - Ph 2 have complaints on MahaRERA?

24 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Xrbia Warai / Neral - Ph 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2 is registered on MahaRERA as P52000004499, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration, 24 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Xrbia Warai / Neral - Ph 2 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Xrbia Warai / Neral - Ph 1 (P52000002828, possession 29 Dec 2022); Xrbia Warai / Neral - Ph 3 (P52000002246, possession 30 Mar 2023). Check that your agreement names the registration of your own wing.

How can I get updates if Xrbia Warai / Neral - Ph 2's possession date changes?

The latest dates are on Xrbia Warai / Neral - Ph 2's MahaRERA page (P52000004499). GharKundli's Kundli Watch sends a free WhatsApp update on Xrbia Warai / Neral - Ph 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Xrbia Warai / Neral - Ph 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2 has 20 buildings filed: A3 with 9 floors; A4 with 9 floors; B4 with 5 floors; C1 with 7 floors; C2 with 7 floors; C3 with 7 floors; and 14 more.

How big is the land of Xrbia Warai / Neral - Ph 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2 stands on 9,127 sq m of land (about 2.3 acres), with 49,991 sq m of sanctioned built-up area and 9,035 sq m of recreational open space.

What is the track record of Xrbia Warai / Neral - Ph 2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai Developers has 8 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 still being built, none past the promised date yet; 3 lapsed. 56 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Xrbia Warai / Neral - Ph 2?

Google Maps has reviews of Xrbia Warai / Neral - Ph 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 24 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Xrbia Warai / Neral - Ph 2?

Xrbia Warai / Neral - Ph 2 by XRBIA WARAI DEVELOPERS PRIVATE LIMITED is in Warai, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000004499, per GharKundli's check of MahaRERA records. Its boundaries filed there include River.

How many homes are in Xrbia Warai / Neral - Ph 2?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2 has 1,281 homes in 20 towers registered on MahaRERA.

When was Xrbia Warai / Neral - Ph 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Xrbia Warai / Neral - Ph 2 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Xrbia Warai / Neral - Ph 2?

No court cases are listed for Xrbia Warai / Neral - Ph 2 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Xrbia Warai / Neral - Ph 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is XRBIA WARAI DEVELOPERS PRIVATE LIMITED, which has 7 other projects registered on MahaRERA.

Other projects in Karjat

All 311 projects in Karjat (410201) →

Other projects by XRBIA WARAI DEVELOPERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.