Prakriti Park-Gulmohar (B Wing)

by Khwaish Enterprises · Panvel, Raigarh

Possession date of Prakriti Park-Gulmohar (B Wing): 30 April 2029, moved from 30 December 2023 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000006751, and currently active. Its completion date has moved from December 2023 to April 2029: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Prakriti Park-Gulmohar (B Wing)?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Prakriti Park-Gulmohar (B Wing)

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000006751
Status
Registered and active
Builder
Khwaish Enterprises
Location
Panvel, Raigarh · 410206
Project type
Others
Registered on
16 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2029
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
106
Sold or booked
33%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Prakriti Park-Gulmohar (B Wing), as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Prakriti Park Gulmohar B wing100%30%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Prakriti Park Gulmohar B wing: covers 13 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prakriti Park-Gulmohar (B Wing) every month.

Prakriti Park-Gulmohar (B Wing): buildings, flats and land, as filed on MahaRERA

  • Buildings: Prakriti Park Gulmohar B wing (14 floors, 125 units)
  • Car parking: 68 covered, 29 open
  • Land: 5,470 sq m (about 1.4 acres) · sanctioned built-up 6,736 sq m

The builder’s record and reviews

Khwaish Enterprises has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 18 months late). 6 complaints on MahaRERA across 2 projects.

Read Google reviews of Prakriti Park-Gulmohar (B Wing) →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prakriti Park-Gulmohar (B Wing): buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Prakriti Park-Gulmohar (B Wing)

What is the possession date of Prakriti Park-Gulmohar (B Wing)?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prakriti Park-Gulmohar (B Wing) in Panvel, Raigarh is 30 April 2029 — 60 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Prakriti Park-Gulmohar (B Wing)?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prakriti Park-Gulmohar (B Wing)'s builder has filed on MahaRERA, the official one, is 30 April 2029, already 60 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Prakriti Park-Gulmohar (B Wing)?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prakriti Park-Gulmohar (B Wing) in Panvel, Raigarh is P52000006751.

Is Prakriti Park-Gulmohar (B Wing) registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing) is registered as P52000006751 and its status is "Registered and active".

What is the construction status of Prakriti Park-Gulmohar (B Wing)?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing)'s status on MahaRERA is "Registered and active". As filed by the builder, slab work on Prakriti Park Gulmohar B wing is 30% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Prakriti Park-Gulmohar (B Wing) have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Prakriti Park-Gulmohar (B Wing) safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing) is registered on MahaRERA as P52000006751, its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Prakriti Park-Gulmohar (B Wing)'s possession date changes?

The latest dates are on Prakriti Park-Gulmohar (B Wing)'s MahaRERA page (P52000006751). GharKundli's Kundli Watch sends a free WhatsApp update on Prakriti Park-Gulmohar (B Wing) every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prakriti Park-Gulmohar (B Wing) have?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing) has one building filed: Prakriti Park Gulmohar B wing with 14 floors and 125 units.

How much parking does Prakriti Park-Gulmohar (B Wing) have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 68 covered and 29 open car parking spaces for Prakriti Park-Gulmohar (B Wing).

How big is the land of Prakriti Park-Gulmohar (B Wing)?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing) stands on 5,470 sq m of land (about 1.4 acres), with 6,736 sq m of sanctioned built-up area.

What is the track record of Prakriti Park-Gulmohar (B Wing)'s builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Khwaish Enterprises has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 3 past the promised date (typically 18 months late). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Prakriti Park-Gulmohar (B Wing)?

Google Maps has reviews of Prakriti Park-Gulmohar (B Wing) written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Prakriti Park-Gulmohar (B Wing)?

Prakriti Park-Gulmohar (B Wing) by Khwaish Enterprises is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000006751, per GharKundli's check of MahaRERA records.

How many homes are in Prakriti Park-Gulmohar (B Wing)?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing) has 106 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was Prakriti Park-Gulmohar (B Wing) registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prakriti Park-Gulmohar (B Wing) was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Prakriti Park-Gulmohar (B Wing)?

No court cases are listed for Prakriti Park-Gulmohar (B Wing) on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Prakriti Park-Gulmohar (B Wing)?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Khwaish Enterprises, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2029 in Raigad →

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.