NIRMAL HEIGHTS
by Ravechi Constructions · Jnpt, RaigarhAlso near Dronagiri, Vashi, Uran
Possession date of NIRMAL HEIGHTS: 28 February 2021, moved from 31 October 2018 (28 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000008645. Status: Lapsed (registration period ended). 6 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (February 2021) has passed.
What do you want to know about NIRMAL HEIGHTS?
How the possession date of NIRMAL HEIGHTS has moved
31 October 2018
Completion date given when the project was registered
31 August 2020
Extended at the builder's request (MahaRERA application EXT52000000759)
Reason the builder gave MahaRERA: “We regret to inform you that due to material shortage & labour issues. We are unable to complete this project within the time frame”
31 August 2020
Extended at the builder's request (MahaRERA application EXT52000003877)
Reason the builder gave MahaRERA:
“We are Promoter of the Ravechi Constructions, We have undertaken to construction of the Project Name “Nirmal Heights” , Situated at Plot No. 36/53, Sector 51, Dronagiri, URAN As we are in the stage of completion of internal work of above sa…” Read the full reason
“We are Promoter of the Ravechi Constructions, We have undertaken to construction of the Project Name “Nirmal Heights” , Situated at Plot No. 36/53, Sector 51, Dronagiri, URAN As we are in the stage of completion of internal work of above said project which required heavy fund through sales but due to market weakness we facing fund shortage. As well as Due to the heavy rain, material shortage and supply of labour we are unable to complete this project within time frame. Even though our project is completed above 95%, to complete project we required an addition Ten month time extension. So we…”28 February 2021
Revised completion date on MahaRERA
Source: NIRMAL HEIGHTS’s extension records on MahaRERA (P52000008645), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NIRMAL HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 6 complaints, and how it ended
- Construction pace against the February 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000008645
- Status
- Lapsed (registration period ended)
- Builder
- Ravechi Constructions
- Location
- Jnpt, Raigarh · 400707
- Project type
- Others
- Registered on
- 19 Aug 2017
- Completion date at registration
- October 2018
- Latest completion date
- February 2021
- Delay so far
- 28 months
- Homes
- 75
- Towers
- 1
- Complaints on MahaRERA
- 6
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of NIRMAL HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRMAL HEIGHTS | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRMAL HEIGHTS every month.
NIRMAL HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: NIRMAL HEIGHTS (19 floors)
- Land: 1,650 sq m (about 0.4 acres) · sanctioned built-up 2,475 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NIRMAL HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIRMAL HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIRMAL HEIGHTS
What is the possession date of NIRMAL HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRMAL HEIGHTS in Jnpt, Raigarh is 28 February 2021 — 28 months later than 31 October 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for NIRMAL HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRMAL HEIGHTS's builder has filed on MahaRERA, the official one, is 28 February 2021, already 28 months later than the 31 October 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NIRMAL HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 31 August 2020, giving the reason "We regret to inform you that due to material shortage & labour issues. We are unable to complete this project within the time frame"; to 31 August 2020, giving the reason "We are Promoter of the Ravechi Constructions, We have undertaken to construction of the Project Name “Nirmal Heights” , Situated at Plot No. 36/53, Sector 51, Dronagiri, URAN As we are in the stage of completion of internal work of above said project which required heavy fund through sales but due to market weakness we facing fund shortage. As well as Due to the heavy rain, material shortage and supply of labour we are unable to complete this project within time frame. Even though our project is completed above 95%, to complete project we required an addition Ten month time extension. So we…".
What is the RERA number of NIRMAL HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRMAL HEIGHTS in Jnpt, Raigarh is P52000008645.
Is NIRMAL HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS is registered as P52000008645 and its status is "Lapsed (registration period ended)".
What is the construction status of NIRMAL HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NIRMAL HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does NIRMAL HEIGHTS have complaints on MahaRERA?
6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is NIRMAL HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS is registered on MahaRERA as P52000008645, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 28 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIRMAL HEIGHTS's possession date changes?
The latest dates are on NIRMAL HEIGHTS's MahaRERA page (P52000008645). GharKundli's Kundli Watch sends a free WhatsApp update on NIRMAL HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIRMAL HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS has one building filed: NIRMAL HEIGHTS with 19 floors.
How big is the land of NIRMAL HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS stands on 1,650 sq m of land (about 0.4 acres), with 2,475 sq m of sanctioned built-up area.
Where can I read reviews of NIRMAL HEIGHTS?
Google Maps has reviews of NIRMAL HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIRMAL HEIGHTS?
NIRMAL HEIGHTS by Ravechi Constructions is in Jnpt, Raigarh (pincode 400707), near Dronagiri, Vashi, Uran, Maharashtra, and is registered on MahaRERA as P52000008645, per GharKundli's check of MahaRERA records.
How many homes are in NIRMAL HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS has 75 homes in 1 tower registered on MahaRERA.
When was NIRMAL HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAL HEIGHTS was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on NIRMAL HEIGHTS?
No court cases are listed for NIRMAL HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NIRMAL HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ravechi Constructions.
Check it yourself on MahaRERA
- How to check the possession date of NIRMAL HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400707
All 58 projects in Jnpt (400707) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.