Skip to content
GharKundli

VAISHNAVI EMPERIA

by RK GROUP OF INFRA · Dronagiri Uran, RaigarhAlso near Nerul, CBD Belapur, Vashi

Possession date of VAISHNAVI EMPERIA: 29 November 2027, moved from 30 December 2024 (35 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000018020, and currently active. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about VAISHNAVI EMPERIA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VAISHNAVI EMPERIA has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 29 December 2025

    Extended at the builder's request (MahaRERA application EXT52000024607)

    Reason the builder gave MahaRERA: “Due to unforeseen circumstances, the extension is require.”
  3. 29 November 2027

    Extended at the builder's request (MahaRERA application EA02122518494)

    Reason the builder gave MahaRERA:
    “The delay in the project completion was primarily due to financial difficulties faced during the development period. There were periods when the necessary funds were not available, which affected the pace of construction and other related a…” Read the full reason“The delay in the project completion was primarily due to financial difficulties faced during the development period. There were periods when the necessary funds were not available, which affected the pace of construction and other related activities. As a result, certain tasks could not be completed within the originally planned timelines. Our financial situation has improved, and sufficient resources are now available to complete the remaining work. We are committed to completing the project as per the approved plans and complying with all statutory requirements. In view of these circumsta…”

Source: VAISHNAVI EMPERIA’s extension records on MahaRERA (P52000018020), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VAISHNAVI EMPERIA

Ready · November 2026 · 40 filings read

Risk & trust score locked/100
  • Risk & trust score, every point explained
  • What the title report on MahaRERA says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the November 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000018020
Status
Registered and active
Builder
RK GROUP OF INFRA
Location
Dronagiri Uran, Raigarh · 400707
Project type
Others
Registered on
3 Oct 2018
Completion date at registration
December 2024
Latest completion date
November 2027
Delay so far
35 months
Homes
86
Sold or booked
53%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Yes
Latest construction certificate
11 Sep 2026
Builder's other MahaRERA projects
4

Construction progress of VAISHNAVI EMPERIA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VAISHNAVI EMPERIA100%94%52%5%

Commencement certificate (CC), as filed on MahaRERA

  • VAISHNAVI EMPERIA: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VAISHNAVI EMPERIA every month.

VAISHNAVI EMPERIA: buildings, flats and land, as filed on MahaRERA

  • Buildings: VAISHNAVI EMPERIA (21 floors, 94 units)
  • Car parking: 50 covered
  • Land: 3,898 sq m (about 1.0 acres) · sanctioned built-up 3,898 sq m · recreational space 1,064 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

RK Group OF Infra has 6 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of VAISHNAVI EMPERIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VAISHNAVI EMPERIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VAISHNAVI EMPERIA

What is the possession date of VAISHNAVI EMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VAISHNAVI EMPERIA in Dronagiri Uran, Raigarh is 29 November 2027 — 35 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for VAISHNAVI EMPERIA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VAISHNAVI EMPERIA's builder has filed on MahaRERA, the official one, is 29 November 2027, already 35 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VAISHNAVI EMPERIA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2025, giving the reason "Due to unforeseen circumstances, the extension is require."; to 29 November 2027, giving the reason "The delay in the project completion was primarily due to financial difficulties faced during the development period. There were periods when the necessary funds were not available, which affected the pace of construction and other related activities. As a result, certain tasks could not be completed within the originally planned timelines. Our financial situation has improved, and sufficient resources are now available to complete the remaining work. We are committed to completing the project as per the approved plans and complying with all statutory requirements. In view of these circumsta…".

What is the RERA number of VAISHNAVI EMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VAISHNAVI EMPERIA in Dronagiri Uran, Raigarh is P52000018020.

Is VAISHNAVI EMPERIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA is registered as P52000018020 and its status is "Registered and active".

What is the construction status of VAISHNAVI EMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VAISHNAVI EMPERIA is 94% done and internal work 52%. The latest construction certificate the builder filed there is dated 11 September 2026. GharKundli's full report compares construction progress with the deadline.

Does VAISHNAVI EMPERIA have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is VAISHNAVI EMPERIA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA is registered on MahaRERA as P52000018020, its completion date has moved 35 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VAISHNAVI EMPERIA's possession date changes?

The latest dates are on VAISHNAVI EMPERIA's MahaRERA page (P52000018020). GharKundli's Kundli Watch sends a free WhatsApp update on VAISHNAVI EMPERIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VAISHNAVI EMPERIA have?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA has one building filed: VAISHNAVI EMPERIA with 21 floors and 94 units.

How much parking does VAISHNAVI EMPERIA have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 50 covered car parking spaces for VAISHNAVI EMPERIA.

How big is the land of VAISHNAVI EMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA stands on 3,898 sq m of land (about 1.0 acres), with 3,898 sq m of sanctioned built-up area and 1,064 sq m of recreational open space.

What is the track record of VAISHNAVI EMPERIA's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), RK Group OF Infra has 6 projects on MahaRERA since 2018, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VAISHNAVI EMPERIA?

Google Maps has reviews of VAISHNAVI EMPERIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VAISHNAVI EMPERIA?

VAISHNAVI EMPERIA by RK GROUP OF INFRA is in Dronagiri Uran, Raigarh (pincode 400707), near Nerul, CBD Belapur, Vashi, Maharashtra, and is registered on MahaRERA as P52000018020, per GharKundli's check of MahaRERA records.

How many homes are in VAISHNAVI EMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA has 86 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.

When was VAISHNAVI EMPERIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VAISHNAVI EMPERIA was registered on MahaRERA on 3 October 2018. A title report on the land is on file there.

Are there court cases on VAISHNAVI EMPERIA?

No court cases are listed for VAISHNAVI EMPERIA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VAISHNAVI EMPERIA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RK GROUP OF INFRA, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Uran

All 58 projects in Jnpt (400707) →

Other projects by RK GROUP OF INFRA

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.