DEVASHREE AANGAN
by SHASHIKANT MARUTI DISALE · Village Khanav, RaigarhAlso near Panvel, Powai, Karanjade
Possession date of DEVASHREE AANGAN: 29 April 2027, moved from 9 February 2024 (34 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000013414, and currently active. Its completion date has moved from February 2024 to April 2027: 34 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DEVASHREE AANGAN?
How the possession date of DEVASHREE AANGAN has moved
9 February 2024
Completion date given when the project was registered
31 December 2024
Extended at the builder's request (MahaRERA application EXT52000018908)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”29 December 2026
Extended at the builder's request (MahaRERA application EA29092517976)
Reason the builder gave MahaRERA:
“1. 95% Project complete. 2. 69.7 Percent consent obtained 3. Due to Impact of Covid -19 Pandamic, Financial Constraint, Shortage of Skilled Labour and Construction Materail, Unfavouravle Market Condition these unavoidable circumstances, the…” Read the full reason
“1. 95% Project complete. 2. 69.7 Percent consent obtained 3. Due to Impact of Covid -19 Pandamic, Financial Constraint, Shortage of Skilled Labour and Construction Materail, Unfavouravle Market Condition these unavoidable circumstances, the project has been delayed. 4. The revised date of completion is now 29/12/2026. 5. QPR till date updated, since there is no Tab to upload QPR from March 2025 uploaded here in other tab. 6. Since unable to update professional for Form 2A adn Form 5 update here. 7. We hereby assure the Hon’ble Authority that the project shall be fully completed within this…”29 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: DEVASHREE AANGAN’s extension records on MahaRERA (P52000013414), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DEVASHREE AANGAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000013414
- Status
- Registered and active
- Builder
- SHASHIKANT MARUTI DISALE
- Location
- Village Khanav, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 5 Oct 2017
- Completion date at registration
- February 2024
- Latest completion date
- April 2027
- Delay so far
- 34 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 51
- Sold or booked
- 65%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DEVASHREE AANGAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DEVASHREE AANGAN | 100% | 100% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- DEVASHREE AANGAN: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DEVASHREE AANGAN every month.
DEVASHREE AANGAN: buildings, flats and land, as filed on MahaRERA
- Buildings: DEVASHREE AANGAN (5 floors, 51 units)
- Car parking: 59 covered
- Land: 2,200 sq m (about 0.5 acres) · sanctioned built-up 1,595 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DEVASHREE AANGAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DEVASHREE AANGAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DEVASHREE AANGAN
What is the possession date of DEVASHREE AANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DEVASHREE AANGAN in Village Khanav, Raigarh is 29 April 2027 — 34 months later than 9 February 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for DEVASHREE AANGAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DEVASHREE AANGAN's builder has filed on MahaRERA, the official one, is 29 April 2027, already 34 months later than the 9 February 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DEVASHREE AANGAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 29 December 2026, giving the reason "1. 95% Project complete. 2. 69.7 Percent consent obtained 3. Due to Impact of Covid -19 Pandamic, Financial Constraint, Shortage of Skilled Labour and Construction Materail, Unfavouravle Market Condition these unavoidable circumstances, the project has been delayed. 4. The revised date of completion is now 29/12/2026. 5. QPR till date updated, since there is no Tab to upload QPR from March 2025 uploaded here in other tab. 6. Since unable to update professional for Form 2A adn Form 5 update here. 7. We hereby assure the Hon’ble Authority that the project shall be fully completed within this…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of DEVASHREE AANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DEVASHREE AANGAN in Village Khanav, Raigarh is P52000013414.
Is DEVASHREE AANGAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN is registered as P52000013414 and its status is "Registered and active".
What is the construction status of DEVASHREE AANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DEVASHREE AANGAN is 100% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does DEVASHREE AANGAN have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DEVASHREE AANGAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN is registered on MahaRERA as P52000013414, its completion date has moved 34 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DEVASHREE AANGAN's possession date changes?
The latest dates are on DEVASHREE AANGAN's MahaRERA page (P52000013414). GharKundli's Kundli Watch sends a free WhatsApp update on DEVASHREE AANGAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DEVASHREE AANGAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN has one building filed: DEVASHREE AANGAN with 5 floors and 51 units.
How much parking does DEVASHREE AANGAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 59 covered car parking spaces for DEVASHREE AANGAN.
How big is the land of DEVASHREE AANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN stands on 2,200 sq m of land (about 0.5 acres), with 1,595 sq m of sanctioned built-up area.
Where can I read reviews of DEVASHREE AANGAN?
Google Maps has reviews of DEVASHREE AANGAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DEVASHREE AANGAN?
DEVASHREE AANGAN by SHASHIKANT MARUTI DISALE is in Village Khanav, Raigarh (pincode 410206), near Panvel, Powai, Karanjade, Maharashtra, and is registered on MahaRERA as P52000013414, per GharKundli's check of MahaRERA records.
How many homes are in DEVASHREE AANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN has 51 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.
When was DEVASHREE AANGAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DEVASHREE AANGAN was registered on MahaRERA on 5 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on DEVASHREE AANGAN?
No court cases are listed for DEVASHREE AANGAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of DEVASHREE AANGAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHASHIKANT MARUTI DISALE.
Check it yourself on MahaRERA
- How to check the possession date of DEVASHREE AANGAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 410206
- Wise City RZ-01 Plotted Development - Phase 3
- Crystal Co-Operative Housing Society Limited
- SAI SIDDHI MADHUBAN
- Pandurang Heights
- Sai Nilay
- MUKTA RESIDENCY
- Shanmukhi Spanda
- Shivesh Mahavir
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.