THE HEIGHTS
by DHRUVI PROPERTIES PVT LTD · Marol, MumbaiAlso near J.B. Nagar, Sakinaka, Seepz
Possession date of THE HEIGHTS: 30 April 2027, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800007232, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about THE HEIGHTS?
How the possession date of THE HEIGHTS has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010339)
Reason the builder gave MahaRERA:
“Due to shortage of labours and contractor because of COVID the work is not able to complete on time. 90% of the work is done therefore we need an extention of period to be able to complete the project. all required additional documents have…” Read the full reason
“Due to shortage of labours and contractor because of COVID the work is not able to complete on time. 90% of the work is done therefore we need an extention of period to be able to complete the project. all required additional documents have been uploaded”31 December 2024
Extended at the builder's request (MahaRERA application EXT51800012013)
Reason the builder gave MahaRERA:
“THE PROJECT IS COMPLETED IN ALL ASPECTS BUT THE MAIN COMPANY THAT IS HOLDING THE RIGHTS TO THE PLOT (IE KSL & INDUSTRIES LTD) PROMOTER IN CURRENTLY IN NCLT AND UNDER MONITORIUM THEREFORE THE COMPANY IS UNABLE TO APPLY FOR THE OC. IT IS THE…” Read the full reason
“THE PROJECT IS COMPLETED IN ALL ASPECTS BUT THE MAIN COMPANY THAT IS HOLDING THE RIGHTS TO THE PLOT (IE KSL & INDUSTRIES LTD) PROMOTER IN CURRENTLY IN NCLT AND UNDER MONITORIUM THEREFORE THE COMPANY IS UNABLE TO APPLY FOR THE OC. IT IS THE RESPONSIBILITY OF KSL TO APPLY AND OBTAIN OC AS PER THE AGREEMENT BUT SINCE THE COMPANY IS SUB-JUDICED IN NCLT AND UNDER MONITORIUM THE OC IS NOT RECEIVED. 46 OF THE TOTAL PURCHASERS SIGNATURES HAVE BEEN TAKEN AND MUTUALLY AGREED TO PUSH THE DATE FOR GETTING THE OC TO 31/12/2024.”31 December 2026
Extended at the builder's request (MahaRERA application EXT51800025080)
Reason the builder gave MahaRERA:
“Due to material shortages, labor shortages, and insufficient funding, the construction work for the project is currently on hold. Additionally, the completion certificate is still pending. However, sufficient funds are now available. We kin…” Read the full reason
“Due to material shortages, labor shortages, and insufficient funding, the construction work for the project is currently on hold. Additionally, the completion certificate is still pending. However, sufficient funds are now available. We kindly request an extension for the project completion”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: THE HEIGHTS’s extension records on MahaRERA (P51800007232), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on THE HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800007232
- Status
- Registered and active
- Builder
- DHRUVI PROPERTIES PVT LTD
- Location
- Marol, Mumbai · 400059
- Project type
- Mixed
- Registered on
- 17 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- April 2027
- Delay so far
- 66 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 90
- Towers
- 2
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of THE HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| EMPRES HEIGHTS B | 100% | 90% | 90% | 50% |
| EMPRESS HEIGHTS A | 100% | 90% | 90% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE HEIGHTS every month.
THE HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: EMPRES HEIGHTS B (12 floors) · EMPRESS HEIGHTS A (11 floors)
- Land: 4,798 sq m (about 1.2 acres) · sanctioned built-up 2,548 sq m · recreational space 720 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of THE HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
THE HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about THE HEIGHTS
What is the possession date of THE HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE HEIGHTS in Marol, Mumbai is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for THE HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date THE HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of THE HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "Due to shortage of labours and contractor because of COVID the work is not able to complete on time. 90% of the work is done therefore we need an extention of period to be able to complete the project. all required additional documents have been uploaded"; to 31 December 2024, giving the reason "THE PROJECT IS COMPLETED IN ALL ASPECTS BUT THE MAIN COMPANY THAT IS HOLDING THE RIGHTS TO THE PLOT (IE KSL & INDUSTRIES LTD) PROMOTER IN CURRENTLY IN NCLT AND UNDER MONITORIUM THEREFORE THE COMPANY IS UNABLE TO APPLY FOR THE OC. IT IS THE RESPONSIBILITY OF KSL TO APPLY AND OBTAIN OC AS PER THE AGREEMENT BUT SINCE THE COMPANY IS SUB-JUDICED IN NCLT AND UNDER MONITORIUM THE OC IS NOT RECEIVED. 46 OF THE TOTAL PURCHASERS SIGNATURES HAVE BEEN TAKEN AND MUTUALLY AGREED TO PUSH THE DATE FOR GETTING THE OC TO 31/12/2024."; to 31 December 2026, giving the reason "Due to material shortages, labor shortages, and insufficient funding, the construction work for the project is currently on hold. Additionally, the completion certificate is still pending. However, sufficient funds are now available. We kindly request an extension for the project completion". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of THE HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE HEIGHTS in Marol, Mumbai is P51800007232.
Is THE HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS is registered as P51800007232 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of THE HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 90% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does THE HEIGHTS have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is THE HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS is registered on MahaRERA as P51800007232, its completion date has moved 66 months since registration, 7 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if THE HEIGHTS's possession date changes?
The latest dates are on THE HEIGHTS's MahaRERA page (P51800007232). GharKundli's Kundli Watch sends a free WhatsApp update on THE HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does THE HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS has 2 buildings filed: EMPRES HEIGHTS B with 12 floors; EMPRESS HEIGHTS A with 11 floors.
How big is the land of THE HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS stands on 4,798 sq m of land (about 1.2 acres), with 2,548 sq m of sanctioned built-up area and 720 sq m of recreational open space.
Where can I read reviews of THE HEIGHTS?
Google Maps has reviews of THE HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is THE HEIGHTS?
THE HEIGHTS by DHRUVI PROPERTIES PVT LTD is in Marol, Mumbai (pincode 400059), near J.B. Nagar, Sakinaka, Seepz, Maharashtra, and is registered on MahaRERA as P51800007232, per GharKundli's check of MahaRERA records.
How many homes are in THE HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS has 90 homes in 2 towers registered on MahaRERA.
When was THE HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), THE HEIGHTS was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on THE HEIGHTS?
No court cases are listed for THE HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of THE HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DHRUVI PROPERTIES PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of THE HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400059
- LUMA TOWERS A & B
- Trade Square 4th to 7th Floor
- MUBARAK MANZIL CHSL
- MINT
- LEELA BUSINESS PARK - II
- Privilon
- AQUINA
- SUDARSAN SATYANIVAS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.