Skip to content
GharKundli

NS HEIGHTS

by NS BUILDERS & DEVELOPERS · Vile Parle East, MumbaiAlso near Vile Parle West, Juhu, Andheri West

Possession: NS HEIGHTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002156. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about NS HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NS HEIGHTS has moved

  1. 30 March 2021

    Completion date given when the project was registered

  2. 30 March 2022

    Extended at the builder's request (MahaRERA application EXT51800009190)

    Reason the builder gave MahaRERA:
    “Respected Sir, You are aware that since last 1 year due to Covid Pandemic the progress of our project is being seriously affected for the reason the workers engaged in subject project migrated to the native place and after during the lockdo…” Read the full reason“Respected Sir, You are aware that since last 1 year due to Covid Pandemic the progress of our project is being seriously affected for the reason the workers engaged in subject project migrated to the native place and after during the lockdown period. Very few workers resumed during unlock period due to which the progress couldn’t achieve to the target schedule. Even since last week again the pandemic has grown which has again resulted in a slow progress of the project. Please note that due to unavoidable circumstances we find it difficult to complete the entire project as per schedule and b…”
  3. 31 March 2023

    Extended at the builder's request (MahaRERA application EXT51800012576)

    Reason the builder gave MahaRERA:
    “We would like to inform you that the construction work of the above project has been completed in all respect. We already have obtained various required noc’s to obtain occupation certificate and also applied for Occupation Certificate on 1…” Read the full reason“We would like to inform you that the construction work of the above project has been completed in all respect. We already have obtained various required noc’s to obtain occupation certificate and also applied for Occupation Certificate on 14.09.2022, a copy of which is enclosed herewith for ready reference. Further we inform you that the above project is clubbed under SRA Scheme 33 (14) (D). Under the said scheme we shall hand over the PTC tenement to SRA. The finishing work of the PTC tenement is also completed. And O.C. awaited. We shall hand over the PTC tenement to SRA on or before Dece…”
  4. 31 October 2023

    Extended at the builder's request (MahaRERA application EXT51800015181)

    Reason the builder gave MahaRERA:
    “To, Date: 28.07.2023 The Secretary, MAHARERA AUTHORITY, Mumbai. Sub: Plot No. 44, CTS No. 272 of Village Vile Parle (W) situated at Corner of N. S. Road No. 3, Vile Parle (W), Mumbai – 400 056. Re: Maharera Registration Number- P51800002156…” Read the full reason“To, Date: 28.07.2023 The Secretary, MAHARERA AUTHORITY, Mumbai. Sub: Plot No. 44, CTS No. 272 of Village Vile Parle (W) situated at Corner of N. S. Road No. 3, Vile Parle (W), Mumbai – 400 056. Re: Maharera Registration Number- P51800002156. Respected Sir, This is to inform you that we have registered our above referred subject project under serial no. P51800002156. We would like to inform you that the construction work of the above project has been completed in all respect and the building is ready for possession. We already have obtained various required noc’s to obtain Occupation Certifi…”

Source: NS HEIGHTS’s extension records on MahaRERA (P51800002156), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NS HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002156
Status
Completed
Builder
NS BUILDERS & DEVELOPERS
Location
Vile Parle East, Mumbai · 400056
Project type
Others
Registered on
31 Jul 2017
Completion date at registration
March 2021
Latest completion date
October 2023
Delay so far
31 months
Homes
17
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of NS HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NS HEIGHTS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NS HEIGHTS every month.

NS HEIGHTS: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Pyramid Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 25 months); 1 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project.

Read Google reviews of NS HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NS HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NS HEIGHTS

What is the possession date of NS HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NS HEIGHTS in Vile Parle East, Mumbai is 31 October 2023 — 31 months later than 30 March 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NS HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NS HEIGHTS's builder has filed on MahaRERA, the official one, is 31 October 2023, already 31 months later than the 30 March 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NS HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2022, giving the reason "Respected Sir, You are aware that since last 1 year due to Covid Pandemic the progress of our project is being seriously affected for the reason the workers engaged in subject project migrated to the native place and after during the lockdown period. Very few workers resumed during unlock period due to which the progress couldn’t achieve to the target schedule. Even since last week again the pandemic has grown which has again resulted in a slow progress of the project. Please note that due to unavoidable circumstances we find it difficult to complete the entire project as per schedule and b…"; to 31 March 2023, giving the reason "We would like to inform you that the construction work of the above project has been completed in all respect. We already have obtained various required noc’s to obtain occupation certificate and also applied for Occupation Certificate on 14.09.2022, a copy of which is enclosed herewith for ready reference. Further we inform you that the above project is clubbed under SRA Scheme 33 (14) (D). Under the said scheme we shall hand over the PTC tenement to SRA. The finishing work of the PTC tenement is also completed. And O.C. awaited. We shall hand over the PTC tenement to SRA on or before Dece…"; to 31 October 2023, giving the reason "To, Date: 28.07.2023 The Secretary, MAHARERA AUTHORITY, Mumbai. Sub: Plot No. 44, CTS No. 272 of Village Vile Parle (W) situated at Corner of N. S. Road No. 3, Vile Parle (W), Mumbai – 400 056. Re: Maharera Registration Number- P51800002156. Respected Sir, This is to inform you that we have registered our above referred subject project under serial no. P51800002156. We would like to inform you that the construction work of the above project has been completed in all respect and the building is ready for possession. We already have obtained various required noc’s to obtain Occupation Certifi…".

What is the RERA number of NS HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NS HEIGHTS in Vile Parle East, Mumbai is P51800002156.

Is NS HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS is registered as P51800002156 and its status is "Completed".

What is the construction status of NS HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work on NS HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NS HEIGHTS have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NS HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS is registered on MahaRERA as P51800002156, its MahaRERA status is "Completed", its completion date has moved 31 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NS HEIGHTS's possession date changes?

The latest dates are on NS HEIGHTS's MahaRERA page (P51800002156). GharKundli's Kundli Watch sends a free WhatsApp update on NS HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NS HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS has one building filed: NS HEIGHTS with 21 floors.

How big is the land of NS HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS stands on 571 sq m of land (about 0.1 acres), with 1,904 sq m of sanctioned built-up area.

What is the track record of NS HEIGHTS's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Pyramid Construction (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 25 months); 1 still being built, none past the promised date yet. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NS HEIGHTS?

Google Maps has reviews of NS HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NS HEIGHTS?

NS HEIGHTS by NS BUILDERS & DEVELOPERS is in Vile Parle East, Mumbai (pincode 400056), near Vile Parle West, Juhu, Andheri West, Maharashtra, and is registered on MahaRERA as P51800002156, per GharKundli's check of MahaRERA records.

How many homes are in NS HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS has 17 homes in 1 tower registered on MahaRERA.

When was NS HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NS HEIGHTS was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NS HEIGHTS?

No court cases are listed for NS HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NS HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NS BUILDERS & DEVELOPERS.

Other projects in pincode 400056

All 88 projects in Vile Parle West (400056) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.