PODDAR SPRAHA DIAMOND PHASE-I
by Poddar Housing and Development Limited · Subhash Nagar, MumbaiAlso near Chembur, Govandi, Kurla
Possession date of PODDAR SPRAHA DIAMOND PHASE-I: 30 September 2022, moved from 30 December 2021 (9 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900002986. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (September 2022) has passed.
What do you want to know about PODDAR SPRAHA DIAMOND PHASE-I?
How the possession date of PODDAR SPRAHA DIAMOND PHASE-I has moved
30 December 2021
Completion date given when the project was registered
31 March 2022
Extended at the builder's request (MahaRERA application EXT51900006058)
Reason the builder gave MahaRERA:
“With refernce to MahaRERA order No:- 14/2020 MahaRERA/Secy/Order/26/2020 we would like to further extend project completion till 31-Mar-2022, considering lockdown and Pandemic due to COVID-19 and consequently impacting the migration of Labo…” Read the full reason
“With refernce to MahaRERA order No:- 14/2020 MahaRERA/Secy/Order/26/2020 we would like to further extend project completion till 31-Mar-2022, considering lockdown and Pandemic due to COVID-19 and consequently impacting the migration of Labour, non-availability of material impacting the supply chain of construction material, which is leading to further delay in completion of the project, since we request you to kindly grant us further three months i.e. upto 31-Mar-2022. Also request to waive the fee for extension due to force majeure in accordance with rule 7 of Maharashtra Real Estate Regis…”30 September 2022
Revised completion date on MahaRERA
Source: PODDAR SPRAHA DIAMOND PHASE-I’s extension records on MahaRERA (P51900002986), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PODDAR SPRAHA DIAMOND PHASE-I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the September 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900002986
- Status
- Lapsed (registration period ended)
- Builder
- Poddar Housing and Development Limited
- Location
- Subhash Nagar, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 4 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- September 2022
- Delay so far
- 9 months
- Homes
- 118
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 12
Construction progress of PODDAR SPRAHA DIAMOND PHASE-I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PODDAR SPRAHA DIAMOND WING A | 100% | 100% | 85% | 30% |
| PODDAR SPRAHA DIAMOND WING B | 100% | 100% | 100% | 75% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PODDAR SPRAHA DIAMOND PHASE-I every month.
PODDAR SPRAHA DIAMOND PHASE-I: buildings, flats and land, as filed on MahaRERA
- Buildings: PODDAR SPRAHA DIAMOND WING A (19 floors) · PODDAR SPRAHA DIAMOND WING B (19 floors)
- Land: 1,470 sq m (about 0.4 acres) · sanctioned built-up 4,698 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Poddar Housing And Development has 13 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 lapsed. 3 complaints on MahaRERA across 1 project.
Read Google reviews of PODDAR SPRAHA DIAMOND PHASE-I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PODDAR SPRAHA DIAMOND PHASE-I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PODDAR SPRAHA DIAMOND PHASE-I
What is the possession date of PODDAR SPRAHA DIAMOND PHASE-I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PODDAR SPRAHA DIAMOND PHASE-I in Subhash Nagar, Mumbai is 30 September 2022 — 9 months later than 30 December 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for PODDAR SPRAHA DIAMOND PHASE-I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PODDAR SPRAHA DIAMOND PHASE-I's builder has filed on MahaRERA, the official one, is 30 September 2022, already 9 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PODDAR SPRAHA DIAMOND PHASE-I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I's builder applied to MahaRERA to extend the completion date once: to 31 March 2022, giving the reason "With refernce to MahaRERA order No:- 14/2020 MahaRERA/Secy/Order/26/2020 we would like to further extend project completion till 31-Mar-2022, considering lockdown and Pandemic due to COVID-19 and consequently impacting the migration of Labour, non-availability of material impacting the supply chain of construction material, which is leading to further delay in completion of the project, since we request you to kindly grant us further three months i.e. upto 31-Mar-2022. Also request to waive the fee for extension due to force majeure in accordance with rule 7 of Maharashtra Real Estate Regis…".
What is the RERA number of PODDAR SPRAHA DIAMOND PHASE-I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PODDAR SPRAHA DIAMOND PHASE-I in Subhash Nagar, Mumbai is P51900002986.
Is PODDAR SPRAHA DIAMOND PHASE-I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I is registered as P51900002986 and its status is "Lapsed (registration period ended)".
What is the construction status of PODDAR SPRAHA DIAMOND PHASE-I?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does PODDAR SPRAHA DIAMOND PHASE-I have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PODDAR SPRAHA DIAMOND PHASE-I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I is registered on MahaRERA as P51900002986, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 9 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PODDAR SPRAHA DIAMOND PHASE-I's possession date changes?
The latest dates are on PODDAR SPRAHA DIAMOND PHASE-I's MahaRERA page (P51900002986). GharKundli's Kundli Watch sends a free WhatsApp update on PODDAR SPRAHA DIAMOND PHASE-I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PODDAR SPRAHA DIAMOND PHASE-I have?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I has 2 buildings filed: PODDAR SPRAHA DIAMOND WING A with 19 floors; PODDAR SPRAHA DIAMOND WING B with 19 floors.
How big is the land of PODDAR SPRAHA DIAMOND PHASE-I?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I stands on 1,470 sq m of land (about 0.4 acres), with 4,698 sq m of sanctioned built-up area.
What is the track record of PODDAR SPRAHA DIAMOND PHASE-I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Poddar Housing And Development has 13 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, all within the promised date; 2 lapsed. 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PODDAR SPRAHA DIAMOND PHASE-I?
Google Maps has reviews of PODDAR SPRAHA DIAMOND PHASE-I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PODDAR SPRAHA DIAMOND PHASE-I?
PODDAR SPRAHA DIAMOND PHASE-I by Poddar Housing and Development Limited is in Subhash Nagar, Mumbai (pincode 400071), near Chembur, Govandi, Kurla, Maharashtra, and is registered on MahaRERA as P51900002986, per GharKundli's check of MahaRERA records.
How many homes are in PODDAR SPRAHA DIAMOND PHASE-I?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I has 118 homes in 2 towers registered on MahaRERA.
When was PODDAR SPRAHA DIAMOND PHASE-I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PODDAR SPRAHA DIAMOND PHASE-I was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PODDAR SPRAHA DIAMOND PHASE-I?
No court cases are listed for PODDAR SPRAHA DIAMOND PHASE-I on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of PODDAR SPRAHA DIAMOND PHASE-I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Poddar Housing and Development Limited, which has 12 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of PODDAR SPRAHA DIAMOND PHASE-I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mumbai City
- SWASTIK LEGACY
- THE CANVAS RESIDENCES - CANVAS 1, CANVAS 2, CANVAS 3
- Privia Navkar
- Harsh Oasis
- Waterview
- AL AMIR APARTMENT
- Lodha Sewri Project
- Lodha Promina
Other projects by Poddar Housing and Development Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.