SAI KRUPA

by K T REALTY · Navimumbai, Raigarh

Possession date of SAI KRUPA: 30 September 2027, moved from 1 October 2024 (35 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000027073, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAI KRUPA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI KRUPA has moved

  1. 1 October 2024

    Completion date given when the project was registered

  2. 30 September 2025

    Extended at the builder's request (MahaRERA application EXT52000024727)

    Reason the builder gave MahaRERA:
    “Explanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the ap…” Read the full reason“Explanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of SAI KRUPA’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 01/10/2024 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing prices of the…”
  3. 30 September 2027

    Extended at the builder's request (MahaRERA application EA25082502434)

    Reason the builder gave MahaRERA:
    “Shortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized t…” Read the full reason“Shortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting cr…”

Source: SAI KRUPA’s extension records on MahaRERA (P52000027073), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI KRUPA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000027073
Status
Registered and active
Builder
K T REALTY
Location
Navimumbai, Raigarh · 410209
Project type
Residential / Group Housing
Registered on
13 Nov 2020
Completion date at registration
October 2024
Latest completion date
September 2027
Delay so far
35 months
Homes
63
Sold or booked
99%
Towers
1
Complaints on MahaRERA
1
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SAI KRUPA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI KRUPA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • SAI KRUPA: covers 8 floors

Latest CC order on MahaRERA: dated 17/11/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI KRUPA every month.

SAI KRUPA: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI KRUPA (8 floors, 68 units)
  • Car parking: 15 covered, 3 open
  • Land: 1,073 sq m (about 0.3 acres) · sanctioned built-up 1,777 sq m

The builder’s record and reviews

K T Realty has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 19 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SAI KRUPA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI KRUPA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI KRUPA

What is the possession date of SAI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI KRUPA in Navimumbai, Raigarh is 30 September 2027 — 35 months later than 1 October 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAI KRUPA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI KRUPA's builder has filed on MahaRERA, the official one, is 30 September 2027, already 35 months later than the 1 October 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI KRUPA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2025, giving the reason "Explanatory note regarding the state of development works in the projects and reason for being not completing development works of the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of SAI KRUPA’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 01/10/2024 as the project completion date, we will not be able to complete the project due to various unavoidable reasons. Such as 1) After the impact of the pandemic, the increasing prices of the…"; to 30 September 2027, giving the reason "Shortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting cr…".

What is the RERA number of SAI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI KRUPA in Navimumbai, Raigarh is P52000027073.

Is SAI KRUPA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA is registered as P52000027073 and its status is "Registered and active".

What is the construction status of SAI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI KRUPA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI KRUPA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI KRUPA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA is registered on MahaRERA as P52000027073, its completion date has moved 35 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI KRUPA's possession date changes?

The latest dates are on SAI KRUPA's MahaRERA page (P52000027073). GharKundli's Kundli Watch sends a free WhatsApp update on SAI KRUPA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI KRUPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA has one building filed: SAI KRUPA with 8 floors and 68 units.

How much parking does SAI KRUPA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered and 3 open car parking spaces for SAI KRUPA.

How big is the land of SAI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA stands on 1,073 sq m of land (about 0.3 acres), with 1,777 sq m of sanctioned built-up area.

What is the track record of SAI KRUPA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), K T Realty has 3 projects on MahaRERA since 2019, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 19 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI KRUPA?

Google Maps has reviews of SAI KRUPA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI KRUPA?

SAI KRUPA by K T REALTY is in Navimumbai, Raigarh (pincode 410209), Maharashtra, and is registered on MahaRERA as P52000027073, per GharKundli's check of MahaRERA records.

How many homes are in SAI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA has 63 homes in 1 tower registered on MahaRERA, and 99% of them are sold or booked.

When was SAI KRUPA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI KRUPA was registered on MahaRERA on 13 November 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI KRUPA?

2 court cases are listed for SAI KRUPA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SAI KRUPA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K T REALTY, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Panvel

All 81 projects in Kamothe (410209) →

Other projects by K T REALTY

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.