Krishnan Vinayak Shraddha Tower

by K K KRISHNAN CONSTRUCTION COMPANY PVT LTD · Bandra East, Mumbai 400051Also near BKC, Bandra Kurla Complex, AndheriRegistered on MahaRERA as “VINAYAK SHRADDHA TOWER”

What’s in the report? →

Possession date of Krishnan Vinayak Shraddha Tower (MahaRERA P51800003341): 31 December 2025, moved from 30 March 2023 (33 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800003341. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800003341, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Krishnan Vinayak Shraddha Tower?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Krishnan Vinayak Shraddha Tower has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800015267)

    Reason the builder gave MahaRERA:
    “It is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we were negotiating with several financial institutions and in…” Read the full reason“It is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we were negotiating with several financial institutions and inventors. From which, we have introduced an investor as a co-promoter and resumed the construction activity in full threshold recently. We have received consent from existing allottees and seeking extension to complete the construction with complete willingness. Kindly grant us the extension”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025923)

    Reason the builder gave MahaRERA:
    “We faced financial crisis during covid and were unable to raise funds, hence we introduced a co-promoter who agreed to fund the project construction. Our existing tenants of rehab and new buyers are aware of the situation and they are suppo…” Read the full reason“We faced financial crisis during covid and were unable to raise funds, hence we introduced a co-promoter who agreed to fund the project construction. Our existing tenants of rehab and new buyers are aware of the situation and they are supporting us to complete the construction hence given consent for extension. With new co-promoter, we are settling the funding issue and hoping to complete the work in coming months.”

Source: Krishnan Vinayak Shraddha Tower’s extension records on MahaRERA (P51800003341), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Krishnan Vinayak Shraddha Tower

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800003341
Status
Lapsed (registration period ended)
Builder
K K KRISHNAN CONSTRUCTION COMPANY PVT LTD
Location
Bandra East, Mumbai · 400051
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
March 2023
Latest completion date
December 2025
Delay so far
33 months
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Krishnan Vinayak Shraddha Tower, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
INDIRAKRUPA100%100%100%100%
VINAYAK SHRADDHA TOWER100%100%85%85%
MUNICIPAL PRIMARY SCHOOL100%40%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krishnan Vinayak Shraddha Tower every 1–2 months.

Krishnan Vinayak Shraddha Tower: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

K K Krishnan Construction has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 5 complaints on MahaRERA across 1 project.

Read Google reviews of Krishnan Vinayak Shraddha Tower →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Krishnan Vinayak Shraddha Tower: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Krishnan Vinayak Shraddha Tower

What is the possession date of Krishnan Vinayak Shraddha Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Krishnan Vinayak Shraddha Tower in Bandra East, Mumbai is 31 December 2025 — 33 months later than 30 March 2023, the date given at registration. That date has already passed.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Krishnan Vinayak Shraddha Tower?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Krishnan Vinayak Shraddha Tower's builder has filed on MahaRERA, the official one, is 31 December 2025, already 33 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Krishnan Vinayak Shraddha Tower extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2024, giving the reason "It is a redevelopment project. Due to pandemic, the financial condition to conduct the construction and fulfill the rentals to tenants and other expenses was not suitable, hence we were negotiating with several financial institutions and inventors. From which, we have introduced an investor as a co-promoter and resumed the construction activity in full threshold recently. We have received consent from existing allottees and seeking extension to complete the construction with complete willingness. Kindly grant us the extension"; to 31 December 2025, giving the reason "We faced financial crisis during covid and were unable to raise funds, hence we introduced a co-promoter who agreed to fund the project construction. Our existing tenants of rehab and new buyers are aware of the situation and they are supporting us to complete the construction hence given consent for extension. With new co-promoter, we are settling the funding issue and hoping to complete the work in coming months.".

What is the RERA number of Krishnan Vinayak Shraddha Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Krishnan Vinayak Shraddha Tower in Bandra East, Mumbai is P51800003341.

Is Krishnan Vinayak Shraddha Tower registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower is registered as P51800003341 and its status is "Lapsed (registration period ended)".

What is the current construction status of Krishnan Vinayak Shraddha Tower? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 40% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Krishnan Vinayak Shraddha Tower have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Krishnan Vinayak Shraddha Tower safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower is registered on MahaRERA as P51800003341, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Krishnan Vinayak Shraddha Tower?

Krishnan Vinayak Shraddha Tower isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Krishnan Vinayak Shraddha Tower?

For a flat in Krishnan Vinayak Shraddha Tower (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Krishnan Vinayak Shraddha Tower received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Krishnan Vinayak Shraddha Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Krishnan Vinayak Shraddha Tower uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Krishnan Vinayak Shraddha Tower was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Krishnan Vinayak Shraddha Tower's possession date changes?

The latest dates are on Krishnan Vinayak Shraddha Tower's MahaRERA page (P51800003341). GharKundli's Kundli Watch sends a free WhatsApp update on Krishnan Vinayak Shraddha Tower every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Krishnan Vinayak Shraddha Tower have?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower has 3 buildings filed: INDIRAKRUPA with 15 floors; VINAYAK SHRADDHA TOWER with 17 floors; MUNICIPAL PRIMARY SCHOOL with 8 floors.

How big is the land of Krishnan Vinayak Shraddha Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower stands on 1,845 sq m of land (about 0.5 acres), with 6,327 sq m of sanctioned built-up area.

What is the track record of Krishnan Vinayak Shraddha Tower's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), K K Krishnan Construction has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 5 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Krishnan Vinayak Shraddha Tower?

Google Maps has reviews of Krishnan Vinayak Shraddha Tower written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Krishnan Vinayak Shraddha Tower?

Krishnan Vinayak Shraddha Tower by K K KRISHNAN CONSTRUCTION COMPANY PVT LTD is in Bandra East, Mumbai, pincode 400051 (near BKC, Bandra Kurla Complex, Andheri), Maharashtra, and is registered on MahaRERA as P51800003341, per GharKundli's check of MahaRERA records. Its land is filed as 617 629. GharKundli lists all 80 MahaRERA projects in Bandra East (400051).

When was Krishnan Vinayak Shraddha Tower registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krishnan Vinayak Shraddha Tower was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Does Krishnan Vinayak Shraddha Tower have any legal issues or court cases?

No court cases are listed for Krishnan Vinayak Shraddha Tower on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Krishnan Vinayak Shraddha Tower?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K K KRISHNAN CONSTRUCTION COMPANY PVT LTD, which has 3 other projects registered on MahaRERA.

Other projects in Bandra East (400051)