GANGA SHANKAR HEIGHTS
by Vikrant Anil Turekar · Pushpak New, Raigarh
Possession date of GANGA SHANKAR HEIGHTS: 30 January 2027, moved from 30 September 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000029379, and currently active. Its completion date has moved from September 2023 to January 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GANGA SHANKAR HEIGHTS?
How the possession date of GANGA SHANKAR HEIGHTS has moved
30 September 2023
Completion date given when the project was registered
29 September 2024
Extended at the builder's request (MahaRERA application EXT52000018869)
Reason the builder gave MahaRERA: “We are under process of completion of our project we need extension till 29 sep 2024”
30 September 2026
Extended at the builder's request (MahaRERA application EXT52000027200)
Reason the builder gave MahaRERA: “We have mentioned in details why we delay our project and how we can complete our project till 30-09-2026”
30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GANGA SHANKAR HEIGHTS’s extension records on MahaRERA (P52000029379), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GANGA SHANKAR HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000029379
- Status
- Registered and active
- Builder
- Vikrant Anil Turekar
- Location
- Pushpak New, Raigarh · 410206
- Project type
- Others
- Registered on
- 29 May 2021
- Completion date at registration
- September 2023
- Latest completion date
- January 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 40
- Sold or booked
- 16%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of GANGA SHANKAR HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GANGA SHANKAR HEIGHTS | 100% | 85% | 0% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- GANGA SHANKAR HEIGHTS: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GANGA SHANKAR HEIGHTS every month.
GANGA SHANKAR HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: GANGA SHANKAR HEIGHTS (8 floors, 45 units)
- Land: 670 sq m (about 0.2 acres) · sanctioned built-up 1,004 sq m
The builder’s record and reviews
Vikrant Anil Turekar has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 27 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project.
Read Google reviews of GANGA SHANKAR HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GANGA SHANKAR HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GANGA SHANKAR HEIGHTS
What is the possession date of GANGA SHANKAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GANGA SHANKAR HEIGHTS in Pushpak New, Raigarh is 30 January 2027 — 36 months later than 30 September 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GANGA SHANKAR HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GANGA SHANKAR HEIGHTS's builder has filed on MahaRERA, the official one, is 30 January 2027, already 36 months later than the 30 September 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GANGA SHANKAR HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 29 September 2024, giving the reason "We are under process of completion of our project we need extension till 29 sep 2024"; to 30 September 2026, giving the reason "We have mentioned in details why we delay our project and how we can complete our project till 30-09-2026". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of GANGA SHANKAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GANGA SHANKAR HEIGHTS in Pushpak New, Raigarh is P52000029379.
Is GANGA SHANKAR HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS is registered as P52000029379 and its status is "Registered and active".
What is the construction status of GANGA SHANKAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GANGA SHANKAR HEIGHTS is 85% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does GANGA SHANKAR HEIGHTS have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GANGA SHANKAR HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS is registered on MahaRERA as P52000029379, its completion date has moved 36 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GANGA SHANKAR HEIGHTS's possession date changes?
The latest dates are on GANGA SHANKAR HEIGHTS's MahaRERA page (P52000029379). GharKundli's Kundli Watch sends a free WhatsApp update on GANGA SHANKAR HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GANGA SHANKAR HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS has one building filed: GANGA SHANKAR HEIGHTS with 8 floors and 45 units.
How big is the land of GANGA SHANKAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS stands on 670 sq m of land (about 0.2 acres), with 1,004 sq m of sanctioned built-up area.
What is the track record of GANGA SHANKAR HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikrant Anil Turekar has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 27 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GANGA SHANKAR HEIGHTS?
Google Maps has reviews of GANGA SHANKAR HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GANGA SHANKAR HEIGHTS?
GANGA SHANKAR HEIGHTS by Vikrant Anil Turekar is in Pushpak New, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000029379, per GharKundli's check of MahaRERA records.
How many homes are in GANGA SHANKAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS has 40 homes in 1 tower registered on MahaRERA, and 16% of them are sold or booked.
When was GANGA SHANKAR HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GANGA SHANKAR HEIGHTS was registered on MahaRERA on 29 May 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on GANGA SHANKAR HEIGHTS?
No court cases are listed for GANGA SHANKAR HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of GANGA SHANKAR HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vikrant Anil Turekar, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of GANGA SHANKAR HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Pushpak New
- SAHEJANAND
- SAI ELEGANCE
- ROCKGOLD RUBY
- GANGA HEIGHTS
- Sai Heights
- Monika Residency
- MADHAV HEIGHTS
- Savitri Ashirwad Apartment
Other projects by Vikrant Anil Turekar
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.