AMBA RESIDENCY
by N R Builders And Developers · Shanti Nagar, RaigarhAlso near Nagothane
Possession date of AMBA RESIDENCY: 31 December 2028, moved from 30 December 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000032513, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AMBA RESIDENCY?
How the possession date of AMBA RESIDENCY has moved
30 December 2025
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EA25022620006)
Reason the builder gave MahaRERA:
“The project “Amba Residency” comprises two buildings, namely Building C and Building D. Building C has been completed successfully through booking receipts and agreement amounts received from purchasers. However, Building D could not be com…” Read the full reason
“The project “Amba Residency” comprises two buildings, namely Building C and Building D. Building C has been completed successfully through booking receipts and agreement amounts received from purchasers. However, Building D could not be completed within the stipulated time due to the following reasons: • Availability / shortage of materials and labour due to the project being situated in a village-based location at Nagothane. • Inadequate project cash flow • Market absorption lower than anticipated • The project is situated in a village-based location at Nagothane, where demand for resident…”
Source: AMBA RESIDENCY’s extension records on MahaRERA (P52000032513), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AMBA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000032513
- Status
- Registered and active
- Builder
- N R Builders And Developers
- Location
- Shanti Nagar, Raigarh · 402106
- Project type
- Residential / Group Housing
- Registered on
- 10 Jan 2022
- Completion date at registration
- December 2025
- Latest completion date
- December 2028
- Delay so far
- 36 months
- Homes
- 41
- Sold or booked
- 22%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AMBA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING C | 100% | 100% | 100% | 100% |
| BUILDING D | 85% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING C: covers 3 floors
- BUILDING D: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AMBA RESIDENCY every month.
AMBA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING C (5 floors, 11 units) · BUILDING D (9 floors, 30 units)
- Car parking: 10 covered
- Land: 1,513 sq m (about 0.4 acres) · sanctioned built-up 600 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AMBA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AMBA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AMBA RESIDENCY
What is the possession date of AMBA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AMBA RESIDENCY in Shanti Nagar, Raigarh is 31 December 2028 — 36 months later than 30 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for AMBA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AMBA RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2028, already 36 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AMBA RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "The project “Amba Residency” comprises two buildings, namely Building C and Building D. Building C has been completed successfully through booking receipts and agreement amounts received from purchasers. However, Building D could not be completed within the stipulated time due to the following reasons: • Availability / shortage of materials and labour due to the project being situated in a village-based location at Nagothane. • Inadequate project cash flow • Market absorption lower than anticipated • The project is situated in a village-based location at Nagothane, where demand for resident…".
What is the RERA number of AMBA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AMBA RESIDENCY in Shanti Nagar, Raigarh is P52000032513.
Is AMBA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY is registered as P52000032513 and its status is "Registered and active".
What is the construction status of AMBA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does AMBA RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is AMBA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY is registered on MahaRERA as P52000032513, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AMBA RESIDENCY's possession date changes?
The latest dates are on AMBA RESIDENCY's MahaRERA page (P52000032513). GharKundli's Kundli Watch sends a free WhatsApp update on AMBA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AMBA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY has 2 buildings filed: BUILDING C with 5 floors and 11 units; BUILDING D with 9 floors and 30 units.
How much parking does AMBA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for AMBA RESIDENCY.
How big is the land of AMBA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY stands on 1,513 sq m of land (about 0.4 acres), with 600 sq m of sanctioned built-up area.
Where can I read reviews of AMBA RESIDENCY?
Google Maps has reviews of AMBA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AMBA RESIDENCY?
AMBA RESIDENCY by N R Builders And Developers is in Shanti Nagar, Raigarh (pincode 402106), near Nagothane, Maharashtra, and is registered on MahaRERA as P52000032513, per GharKundli's check of MahaRERA records.
How many homes are in AMBA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY has 41 homes in 2 towers registered on MahaRERA, and 22% of them are sold or booked.
When was AMBA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AMBA RESIDENCY was registered on MahaRERA on 10 January 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on AMBA RESIDENCY?
No court cases are listed for AMBA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AMBA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is N R Builders And Developers.
Check it yourself on MahaRERA
- How to check the possession date of AMBA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in Roha
- SKY TOWER PHASE-I
- VASTU VANDAN
- RAJ ESTATE
- VIJAYSHREE APARTMENT
- OM SHANTI HEIGHTS
- MAN SAROJ PLAZA
- MITHILA ICON
- ARISE ARCADE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.