Possession date of MAN SAROJ PLAZA: 30 October 2027, moved from 31 March 2025 (27 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000054278, and currently active. Its completion date has moved from March 2025 to October 2027: 27 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MAN SAROJ PLAZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MAN SAROJ PLAZA has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA02062621198)

    Reason the builder gave MahaRERA:
    “Shortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized t…” Read the full reason“Shortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting cr…”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MAN SAROJ PLAZA’s extension records on MahaRERA (P52000054278), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAN SAROJ PLAZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000054278
Status
Registered and active
Builder
NILESH MANGILAL JAIN
Location
Nagothane, Raigarh · 402106
Project type
Others
Registered on
15 Jan 2024
Completion date at registration
March 2025
Latest completion date
October 2027
Delay so far
27 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
16
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MAN SAROJ PLAZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAN SAROJ PLAZA100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

  • MAN SAROJ PLAZA: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAN SAROJ PLAZA every month.

MAN SAROJ PLAZA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Nilesh Mangilal Jain has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA.

Read Google reviews of MAN SAROJ PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAN SAROJ PLAZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MAN SAROJ PLAZA

What is the possession date of MAN SAROJ PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MAN SAROJ PLAZA in Nagothane, Raigarh is 30 October 2027 — 27 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MAN SAROJ PLAZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAN SAROJ PLAZA's builder has filed on MahaRERA, the official one, is 30 October 2027, already 27 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAN SAROJ PLAZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "Shortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting cr…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MAN SAROJ PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MAN SAROJ PLAZA in Nagothane, Raigarh is P52000054278.

Is MAN SAROJ PLAZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA is registered as P52000054278 and its status is "Registered and active".

What is the construction status of MAN SAROJ PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MAN SAROJ PLAZA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does MAN SAROJ PLAZA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MAN SAROJ PLAZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA is registered on MahaRERA as P52000054278, its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MAN SAROJ PLAZA's possession date changes?

The latest dates are on MAN SAROJ PLAZA's MahaRERA page (P52000054278). GharKundli's Kundli Watch sends a free WhatsApp update on MAN SAROJ PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAN SAROJ PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA has one building filed: MAN SAROJ PLAZA with 5 floors and 30 units.

How much parking does MAN SAROJ PLAZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 3 covered car parking spaces for MAN SAROJ PLAZA.

How big is the land of MAN SAROJ PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA stands on 375 sq m of land (about 0.1 acres), with 931 sq m of sanctioned built-up area.

What is the track record of MAN SAROJ PLAZA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nilesh Mangilal Jain has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MAN SAROJ PLAZA?

Google Maps has reviews of MAN SAROJ PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MAN SAROJ PLAZA?

MAN SAROJ PLAZA by NILESH MANGILAL JAIN is in Nagothane, Raigarh (pincode 402106), Maharashtra, and is registered on MahaRERA as P52000054278, per GharKundli's check of MahaRERA records.

How many homes are in MAN SAROJ PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA has 16 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was MAN SAROJ PLAZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MAN SAROJ PLAZA was registered on MahaRERA on 15 January 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on MAN SAROJ PLAZA?

No court cases are listed for MAN SAROJ PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MAN SAROJ PLAZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NILESH MANGILAL JAIN.

All projects with possession due in 2027 in Raigad →

Other projects in pincode 402106

All 12 projects in Nagothane (402106) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.