Shree Sadguru Krupa Mandavkar Complex

by Shree Ratnadeep Developers · Nagothane, Raigarh

Possession date of Shree Sadguru Krupa Mandavkar Complex: 30 October 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1270002501891, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Shree Sadguru Krupa Mandavkar Complex?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shree Sadguru Krupa Mandavkar Complex has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA16072621769)

    Reason the builder gave MahaRERA:
    “1.The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site whic…” Read the full reason“1.The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes con-siderably more time than the conventional methods. 2.The area is which project is to be constructed and completed is entirely a residential ar-ea, therefore there are limitations in time of construction work on daily basis including no work development on week end. 3.The project has been adversely affected by a shortage in the availability and…”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shree Sadguru Krupa Mandavkar Complex’s extension records on MahaRERA (PM1270002501891), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shree Sadguru Krupa Mandavkar Complex

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1270002501891
Status
Registered and active
Builder
Shree Ratnadeep Developers
Location
Nagothane, Raigarh · 402106
Project type
Mixed
Registered on
26 Dec 2025
Completion date at registration
June 2026
Latest completion date
October 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
27
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shree Sadguru Krupa Mandavkar Complex, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building 10%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • Building 1: covers Ground/Stilt + 6 Habitable Floors

Latest CC order on MahaRERA: dated 22/07/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Sadguru Krupa Mandavkar Complex every month.

Shree Sadguru Krupa Mandavkar Complex: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building 1 (7 floors, 32 units)
  • Car parking: 6 covered, 1 open
  • Land: 645 sq m (about 0.2 acres) · sanctioned built-up 1,497 sq m
  • Boundaries filed include: Grampanchayat Road 6 Mtr, Mr Deshpande's Common Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Ritesh Futarmal Doshi has 3 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date. No complaints on MahaRERA.

Read Google reviews of Shree Sadguru Krupa Mandavkar Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Sadguru Krupa Mandavkar Complex: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shree Sadguru Krupa Mandavkar Complex

What is the possession date of Shree Sadguru Krupa Mandavkar Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Sadguru Krupa Mandavkar Complex in Nagothane, Raigarh is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Shree Sadguru Krupa Mandavkar Complex?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Sadguru Krupa Mandavkar Complex's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shree Sadguru Krupa Mandavkar Complex extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "1.The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes con-siderably more time than the conventional methods. 2.The area is which project is to be constructed and completed is entirely a residential ar-ea, therefore there are limitations in time of construction work on daily basis including no work development on week end. 3.The project has been adversely affected by a shortage in the availability and…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shree Sadguru Krupa Mandavkar Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Sadguru Krupa Mandavkar Complex in Nagothane, Raigarh is PM1270002501891.

Is Shree Sadguru Krupa Mandavkar Complex registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex is registered as PM1270002501891 and its status is "Registered and active".

What is the construction status of Shree Sadguru Krupa Mandavkar Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Shree Sadguru Krupa Mandavkar Complex have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shree Sadguru Krupa Mandavkar Complex safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex is registered on MahaRERA as PM1270002501891, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shree Sadguru Krupa Mandavkar Complex's possession date changes?

The latest dates are on Shree Sadguru Krupa Mandavkar Complex's MahaRERA page (PM1270002501891). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Sadguru Krupa Mandavkar Complex every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Sadguru Krupa Mandavkar Complex have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex has one building filed: Building 1 with 7 floors and 32 units.

How much parking does Shree Sadguru Krupa Mandavkar Complex have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered and 1 open car parking spaces for Shree Sadguru Krupa Mandavkar Complex.

How big is the land of Shree Sadguru Krupa Mandavkar Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex stands on 645 sq m of land (about 0.2 acres), with 1,497 sq m of sanctioned built-up area.

What is the track record of Shree Sadguru Krupa Mandavkar Complex's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ritesh Futarmal Doshi has 3 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Shree Sadguru Krupa Mandavkar Complex?

Google Maps has reviews of Shree Sadguru Krupa Mandavkar Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shree Sadguru Krupa Mandavkar Complex?

Shree Sadguru Krupa Mandavkar Complex by Shree Ratnadeep Developers is in Nagothane, Raigarh (pincode 402106), Maharashtra, and is registered on MahaRERA as PM1270002501891, per GharKundli's check of MahaRERA records. Its boundaries filed there include Grampanchayat Road 6 Mtr, Mr Deshpande's Common Road.

How many homes are in Shree Sadguru Krupa Mandavkar Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex has 27 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was Shree Sadguru Krupa Mandavkar Complex registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Sadguru Krupa Mandavkar Complex was registered on MahaRERA on 26 December 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on Shree Sadguru Krupa Mandavkar Complex?

No court cases are listed for Shree Sadguru Krupa Mandavkar Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Shree Sadguru Krupa Mandavkar Complex?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Ratnadeep Developers.

All projects with possession due in 2027 in Raigad →

Other projects in pincode 402106

All 12 projects in Nagothane (402106) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.