by CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED · Ulwe, RaigarhAlso near Panvel

Possession date of Plot No -03, Sector -16A, Kharkopar RaiIway Station East: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000033542, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Plot No -03, Sector -16A, Kharkopar RaiIway Station East

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000033542
Status
Registered and active
Builder
CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED
Location
Ulwe, Raigarh · 410206
Project type
Others
Registered on
22 Feb 2022
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
2,136
Towers
19
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
21

Construction progress of Plot No -03, Sector -16A, Kharkopar RaiIway Station East, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
EA-14100%100%50%0%
EA-15100%100%50%10%
EA -16100%100%50%10%
EA -17100%100%90%20%
EA -18100%100%75%10%
EA -19100%100%60%20%
EA-20100%100%100%20%
EA -21100%100%85%40%
EA-22100%100%55%20%
EA-23100%100%65%40%
EA-24100%100%80%20%
EA-25100%100%65%10%
EA-26100%100%60%20%
EA -27100%100%95%20%
EA-28100%100%100%20%
EA- 29100%60%0%0%
EA-30100%100%15%0%
EA- 31100%60%0%0%
EA-32100%100%30%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Plot No -03, Sector -16A, Kharkopar RaiIway Station East every month.

Plot No -03, Sector -16A, Kharkopar RaiIway Station East: buildings, flats and land, as filed on MahaRERA

  • Buildings: EA-14 (16 floors) · EA-15 (16 floors) · EA -16 (16 floors) · EA -17 (16 floors) · EA -18 (16 floors) · EA -19 (16 floors) · EA-20 (16 floors) · EA -21 (16 floors) · and 11 more
  • Land: 48,168 sq m (about 11.9 acres) · sanctioned built-up 65,796 sq m · recreational space 7,672 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Plot No -03, Sector -16A, Kharkopar RaiIway Station East →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Plot No -03, Sector -16A, Kharkopar RaiIway Station East: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Plot No -03, Sector -16A, Kharkopar RaiIway Station East

What is the possession date of Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Plot No -03, Sector -16A, Kharkopar RaiIway Station East in Ulwe, Raigarh is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Plot No -03, Sector -16A, Kharkopar RaiIway Station East's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Plot No -03, Sector -16A, Kharkopar RaiIway Station East in Ulwe, Raigarh is P52000033542.

Is Plot No -03, Sector -16A, Kharkopar RaiIway Station East registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East is registered as P52000033542 and its status is "Registered and active".

What is the construction status of Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 60% to 100% across 19 towers. GharKundli's full report compares construction progress with the deadline.

Does Plot No -03, Sector -16A, Kharkopar RaiIway Station East have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Plot No -03, Sector -16A, Kharkopar RaiIway Station East safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East is registered on MahaRERA as P52000033542, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Plot No -03, Sector -16A, Kharkopar RaiIway Station East's possession date changes?

The latest dates are on Plot No -03, Sector -16A, Kharkopar RaiIway Station East's MahaRERA page (P52000033542). GharKundli's Kundli Watch sends a free WhatsApp update on Plot No -03, Sector -16A, Kharkopar RaiIway Station East every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Plot No -03, Sector -16A, Kharkopar RaiIway Station East have?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East has 19 buildings filed: EA-14 with 16 floors; EA-15 with 16 floors; EA -16 with 16 floors; EA -17 with 16 floors; EA -18 with 16 floors; EA -19 with 16 floors; and 13 more.

How big is the land of Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East stands on 48,168 sq m of land (about 11.9 acres), with 65,796 sq m of sanctioned built-up area and 7,672 sq m of recreational open space.

Where can I read reviews of Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

Google Maps has reviews of Plot No -03, Sector -16A, Kharkopar RaiIway Station East written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

Plot No -03, Sector -16A, Kharkopar RaiIway Station East by CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED is in Ulwe, Raigarh (pincode 410206), near Panvel, Maharashtra, and is registered on MahaRERA as P52000033542, per GharKundli's check of MahaRERA records.

How many homes are in Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East has 2,136 homes in 19 towers registered on MahaRERA.

When was Plot No -03, Sector -16A, Kharkopar RaiIway Station East registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Plot No -03, Sector -16A, Kharkopar RaiIway Station East was registered on MahaRERA on 22 February 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

No court cases are listed for Plot No -03, Sector -16A, Kharkopar RaiIway Station East on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Plot No -03, Sector -16A, Kharkopar RaiIway Station East?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED, which has 21 other projects registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.