by P. G. ENTERPRISES · Malad West, MumbaiAlso near Borivali, Vile Parle East, Malad East

Possession date of OM PALACE: 31 July 2023, moved from 30 June 2019 (49 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800002838. Status: Lapsed (registration period ended). 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2023) has passed.

What do you want to know about OM PALACE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of OM PALACE has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 29 June 2020

    Extended at the builder's request (MahaRERA application EXT51800001973)

    Reason the builder gave MahaRERA:
    “Declaration We are hereby explaining the delay in completion of the project on time. The primary reason of delay was obtaining approvals ontime for the Rehab Building and Sale Building. Enormous numbers of compliances, lengthy procedures fo…” Read the full reason“Declaration We are hereby explaining the delay in completion of the project on time. The primary reason of delay was obtaining approvals ontime for the Rehab Building and Sale Building. Enormous numbers of compliances, lengthy procedures for required permissions, unfavourable market conditions and non availability of the Staff due to National general elections attributed to this delay which was beyond our control.Hence we are seeking an extended date of completion of the project.”
  3. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT51800012325)

    Reason the builder gave MahaRERA:
    “We are hereby explaining the delay in completion the project on time. The primary reasons of delay was non availability of the Staff due to COVID-19 pandemic and delay in obtaining approvals on-time for the Rehab Building and Sale Building.…” Read the full reason“We are hereby explaining the delay in completion the project on time. The primary reasons of delay was non availability of the Staff due to COVID-19 pandemic and delay in obtaining approvals on-time for the Rehab Building and Sale Building. As well as we obtained Part OC for Rehab Building & handover the possession to Rehab Tenants. Now we are trying to Full OC of Rehab Building & Sale Building so we are seeking an extended date of completion of the project.”

Source: OM PALACE’s extension records on MahaRERA (P51800002838), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on OM PALACE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints and 1 court case, and how it ended
  • Construction pace against the July 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002838
Status
Lapsed (registration period ended)
Builder
P. G. ENTERPRISES
Location
Malad West, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
4 Aug 2017
Completion date at registration
June 2019
Latest completion date
July 2023
Delay so far
49 months
Homes
140
Towers
2
Complaints on MahaRERA
8
Court cases listed
1
Appeals at the tribunal
5
Title report on file
Not found

Construction progress of OM PALACE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
OM PALACE100%100%60%0%
SNEHAL SADAN SRA CHSL100%100%98%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on OM PALACE every month.

OM PALACE: buildings, flats and land, as filed on MahaRERA

  • Buildings: OM PALACE (23 floors) · SNEHAL SADAN SRA CHSL (28 floors)
  • Land: 1,584 sq m (about 0.4 acres) · sanctioned built-up 4,679 sq m · recreational space 103 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of OM PALACE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

OM PALACE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about OM PALACE

What is the possession date of OM PALACE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OM PALACE in Malad West, Mumbai is 31 July 2023 — 49 months later than 30 June 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for OM PALACE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date OM PALACE's builder has filed on MahaRERA, the official one, is 31 July 2023, already 49 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of OM PALACE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2020, giving the reason "Declaration We are hereby explaining the delay in completion of the project on time. The primary reason of delay was obtaining approvals ontime for the Rehab Building and Sale Building. Enormous numbers of compliances, lengthy procedures for required permissions, unfavourable market conditions and non availability of the Staff due to National general elections attributed to this delay which was beyond our control.Hence we are seeking an extended date of completion of the project."; to 31 July 2023, giving the reason "We are hereby explaining the delay in completion the project on time. The primary reasons of delay was non availability of the Staff due to COVID-19 pandemic and delay in obtaining approvals on-time for the Rehab Building and Sale Building. As well as we obtained Part OC for Rehab Building & handover the possession to Rehab Tenants. Now we are trying to Full OC of Rehab Building & Sale Building so we are seeking an extended date of completion of the project.".

What is the RERA number of OM PALACE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OM PALACE in Malad West, Mumbai is P51800002838.

Is OM PALACE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE is registered as P51800002838 and its status is "Lapsed (registration period ended)".

What is the construction status of OM PALACE?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does OM PALACE have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is OM PALACE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE is registered on MahaRERA as P51800002838, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 49 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if OM PALACE's possession date changes?

The latest dates are on OM PALACE's MahaRERA page (P51800002838). GharKundli's Kundli Watch sends a free WhatsApp update on OM PALACE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does OM PALACE have?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE has 2 buildings filed: OM PALACE with 23 floors; SNEHAL SADAN SRA CHSL with 28 floors.

How big is the land of OM PALACE?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE stands on 1,584 sq m of land (about 0.4 acres), with 4,679 sq m of sanctioned built-up area and 103 sq m of recreational open space.

Where can I read reviews of OM PALACE?

Google Maps has reviews of OM PALACE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is OM PALACE?

OM PALACE by P. G. ENTERPRISES is in Malad West, Mumbai (pincode 400064), near Borivali, Vile Parle East, Malad East, Maharashtra, and is registered on MahaRERA as P51800002838, per GharKundli's check of MahaRERA records.

How many homes are in OM PALACE?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE has 140 homes in 2 towers registered on MahaRERA.

When was OM PALACE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), OM PALACE was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on OM PALACE?

1 court case is listed for OM PALACE on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of OM PALACE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is P. G. ENTERPRISES.