ABIDA MANSION

by AYUB ISHAQUE MOHAMMED KHAN · Mamdapur, Raigarh

Possession date of ABIDA MANSION: 30 November 2027, moved from 31 December 2025 (19 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000053008, and currently active. Its completion date has moved from December 2025 to November 2027: 19 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ABIDA MANSION?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ABIDA MANSION has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 July 2027

    Extended at the builder's request (MahaRERA application EA20052621029)

    Reason the builder gave MahaRERA: “1) Poor booking response from customer. 2) Because of poor response our work was very slow”
  3. 30 November 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ABIDA MANSION’s extension records on MahaRERA (P52000053008), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ABIDA MANSION

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000053008
Status
Registered and active
Builder
AYUB ISHAQUE MOHAMMED KHAN
Location
Mamdapur, Raigarh · 410101
Project type
Others
Registered on
10 Oct 2023
Completion date at registration
December 2025
Latest completion date
November 2027
Delay so far
19 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
35
Sold or booked
13%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of ABIDA MANSION, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ABIDA MANSION100%77%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • ABIDA MANSION: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ABIDA MANSION every month.

ABIDA MANSION: buildings, flats and land, as filed on MahaRERA

  • Buildings: ABIDA MANSION (8 floors, 38 units)
  • Car parking: 6 covered
  • Land: 829 sq m (about 0.2 acres) · sanctioned built-up 1,244 sq m

The builder’s record and reviews

Ayub Ishaque Mohammed Khan has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of ABIDA MANSION →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ABIDA MANSION: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ABIDA MANSION

What is the possession date of ABIDA MANSION?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ABIDA MANSION in Mamdapur, Raigarh is 30 November 2027 — 19 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ABIDA MANSION?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ABIDA MANSION's builder has filed on MahaRERA, the official one, is 30 November 2027, already 19 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ABIDA MANSION extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION's builder applied to MahaRERA to extend the completion date once: to 31 July 2027, giving the reason "1) Poor booking response from customer. 2) Because of poor response our work was very slow". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ABIDA MANSION?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ABIDA MANSION in Mamdapur, Raigarh is P52000053008.

Is ABIDA MANSION registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION is registered as P52000053008 and its status is "Registered and active".

What is the construction status of ABIDA MANSION?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ABIDA MANSION is 77% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does ABIDA MANSION have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is ABIDA MANSION safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION is registered on MahaRERA as P52000053008, its completion date has moved 19 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ABIDA MANSION's possession date changes?

The latest dates are on ABIDA MANSION's MahaRERA page (P52000053008). GharKundli's Kundli Watch sends a free WhatsApp update on ABIDA MANSION every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ABIDA MANSION have?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION has one building filed: ABIDA MANSION with 8 floors and 38 units.

How much parking does ABIDA MANSION have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for ABIDA MANSION.

How big is the land of ABIDA MANSION?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION stands on 829 sq m of land (about 0.2 acres), with 1,244 sq m of sanctioned built-up area.

What is the track record of ABIDA MANSION's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ayub Ishaque Mohammed Khan has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 6 months late); 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ABIDA MANSION?

Google Maps has reviews of ABIDA MANSION written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ABIDA MANSION?

ABIDA MANSION by AYUB ISHAQUE MOHAMMED KHAN is in Mamdapur, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000053008, per GharKundli's check of MahaRERA records.

How many homes are in ABIDA MANSION?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION has 35 homes in 1 tower registered on MahaRERA, and 13% of them are sold or booked.

When was ABIDA MANSION registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ABIDA MANSION was registered on MahaRERA on 10 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on ABIDA MANSION?

No court cases are listed for ABIDA MANSION on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of ABIDA MANSION?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AYUB ISHAQUE MOHAMMED KHAN, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Raigad →

Other projects in Mamdapur

All 362 projects in Neral (410101) →

Other projects by AYUB ISHAQUE MOHAMMED KHAN

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.