COURTYARD
by LAKHANI BUILDERS PVT LTD · Panvel, Raigarh
Possession date of COURTYARD: 30 September 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000051882, and currently active. Its completion date is now September 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about COURTYARD?
How the possession date of COURTYARD has moved
31 May 2027
Completion date given when the project was registered
30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: COURTYARD’s extension records on MahaRERA (P52000051882), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on COURTYARD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000051882
- Status
- Registered and active
- Builder
- LAKHANI BUILDERS PVT LTD
- Location
- Panvel, Raigarh · 410206
- Project type
- Residential / Group Housing
- Registered on
- 7 Jul 2023
- Completion date at registration
- May 2027
- Latest completion date
- September 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 84
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 10
Construction progress of COURTYARD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 90% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 07 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on COURTYARD every month.
COURTYARD: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (8 floors, 84 units)
- Land: 3,181 sq m (about 0.8 acres) · sanctioned built-up 4,513 sq m
- Boundaries filed include: RIVER
The builder’s record and reviews
Lakhani Builders (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 8 months); 7 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. 7 complaints on MahaRERA across 5 projects.
Read Google reviews of COURTYARD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
COURTYARD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about COURTYARD
What is the possession date of COURTYARD?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for COURTYARD in Panvel, Raigarh is 30 September 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for COURTYARD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date COURTYARD's builder has filed on MahaRERA, the official one, is 30 September 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of COURTYARD?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of COURTYARD in Panvel, Raigarh is P52000051882.
Is COURTYARD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD is registered as P52000051882 and its status is "Registered and active".
What is the construction status of COURTYARD?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING A is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does COURTYARD have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is COURTYARD safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD is registered on MahaRERA as P52000051882, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if COURTYARD's possession date changes?
The latest dates are on COURTYARD's MahaRERA page (P52000051882). GharKundli's Kundli Watch sends a free WhatsApp update on COURTYARD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does COURTYARD have?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD has one building filed: WING A with 8 floors and 84 units.
How big is the land of COURTYARD?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD stands on 3,181 sq m of land (about 0.8 acres), with 4,513 sq m of sanctioned built-up area.
What is the track record of COURTYARD's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Lakhani Builders (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 5 finished, 4 within the promised date and 1 needed more time (typically 8 months); 7 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. 7 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of COURTYARD?
Google Maps has reviews of COURTYARD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is COURTYARD?
COURTYARD by LAKHANI BUILDERS PVT LTD is in Panvel, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000051882, per GharKundli's check of MahaRERA records. Its boundaries filed there include RIVER.
How many homes are in COURTYARD?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD has 84 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.
When was COURTYARD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), COURTYARD was registered on MahaRERA on 7 July 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on COURTYARD?
No court cases are listed for COURTYARD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of COURTYARD?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LAKHANI BUILDERS PVT LTD, which has 10 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of COURTYARD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 410206
- Wise City RZ-01 Plotted Development - Phase 3
- Crystal Co-Operative Housing Society Limited
- SAI SIDDHI MADHUBAN
- Pandurang Heights
- Sai Nilay
- MUKTA RESIDENCY
- Shanmukhi Spanda
- Shivesh Mahavir
Other projects by LAKHANI BUILDERS PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.