Skip to content
GharKundli

TEN BKC

by MIG (Bandra) Realtors & Builders Private Limited · Bandra East, MumbaiAlso near BKC, Khernagar, Sion

Possession date of TEN BKC: 5 June 2025, moved from 6 June 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800004889. Status: Lapsed (registration period ended). MahaRERA has issued 2 regulatory orders on this project. 82 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about TEN BKC?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TEN BKC has moved

  1. 6 June 2023

    Completion date given when the project was registered

  2. 5 June 2024

    Extended at the builder's request (MahaRERA application EXT51800012262)

    Reason the builder gave MahaRERA:
    “1. We, hereby apply for extension of registration u/s 6 of the Act r/w Rule 7 of the Rules in respect of Project: TEN BKC, No. P51800004889 which expires on 6th June 2023. This is a redevelopment project. The obligation to undertake constru…” Read the full reason“1. We, hereby apply for extension of registration u/s 6 of the Act r/w Rule 7 of the Rules in respect of Project: TEN BKC, No. P51800004889 which expires on 6th June 2023. This is a redevelopment project. The obligation to undertake construction was that of the Co-promoter, Radius Estates & Developers Pvt. Ltd.(Radius). Radius has gone into CIRP under Insolvency Code and a Resolution plan submitted by Adani Goodhomes Pvt. Ltd. has been approved by the Committee of Creditors (83.93% voting in favour). Project Completion Date proposed in the Resolution Plan is 6th June 2024. Adani has also be…”
  3. 5 June 2025

    Extended at the builder's request (MahaRERA application EXT51800019816)

    Reason the builder gave MahaRERA:
    “the date of 6th June 2024 was proposed in the Resolution Plan which was submitted by Adani Goodhomes Pvt. Ltd. with the Committee of Creditors in December 2021, it was on the basis of a site condition, where work could commence immediately…” Read the full reason“the date of 6th June 2024 was proposed in the Resolution Plan which was submitted by Adani Goodhomes Pvt. Ltd. with the Committee of Creditors in December 2021, it was on the basis of a site condition, where work could commence immediately on 1st January 2022. However, after the Resolution Plan was approved by the Committee of Creditors on 21st December 2021 and Adani Goodhomes Pvt. Ltd. was permitted to enter upon the site on 27th December 2021 under the Construction Management Agreement, and after entering the site, Adani Goodhomes Private Limited commenced collating all the drawings of t…”

Source: TEN BKC’s extension records on MahaRERA (P51800004889), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TEN BKC

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 82 complaints and 35 court cases, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004889
Status
Lapsed (registration period ended)
Builder
MIG (Bandra) Realtors & Builders Private Limited
Location
Bandra East, Mumbai · 400051
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2023
Latest completion date
June 2025
Delay so far
24 months
Homes
1
Sold or booked
0%
Towers
15
Complaints on MahaRERA
82
Court cases listed
35
Appeals at the tribunal
58
MahaRERA regulatory orders
2
Title report on file
Not found

Construction progress of TEN BKC, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing 1100%100%65%28%
WING 2100%100%58%28%
WING 3100%100%43%28%
WING 4100%100%56%28%
WING 5100%100%95%81%
WING 6100%100%95%81%
WING 7100%100%94%89%
WING 8100%100%98%89%
WING 9100%100%71%28%
WING 10100%100%76%28%
WING 11100%100%63%28%
WING 12100%100%72%28%
WING 13100%100%99%72%
WING 14100%100%69%28%
WING 15100%100%59%28%

Commencement certificate (CC), as filed on MahaRERA

  • Wing 1: covers 27 floors
  • WING 2: covers 27 floors
  • WING 3: covers 27 floors
  • WING 4: covers 27 floors
  • WING 5: covers 34 floors
  • WING 6: covers 34 floors
  • WING 7: covers 34 floors
  • WING 8: covers 34 floors
  • WING 9: covers 34 floors
  • WING 10: covers 27 floors
  • WING 11: covers 27 floors
  • WING 12: covers 27 floors
  • WING 13: covers 27 floors
  • WING 14: covers 27 floors
  • WING 15: covers 27 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TEN BKC every month.

TEN BKC: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Unspecified—2772
4 BHK2,2391
  • Buildings: Wing 1 (27 floors, 1 units) · WING 2 (27 floors) · WING 3 (27 floors) · WING 4 (27 floors) · WING 5 (34 floors) · WING 6 (34 floors) · WING 7 (34 floors) · WING 8 (34 floors) · and 7 more
  • Land: 20,149 sq m (about 5.0 acres) · sanctioned built-up 58,365 sq m · recreational space 4,242 sq m
  • Boundaries filed include: N Dharmadhikari Road, approx 9 mtrs wide road, Madhusudan Kalelkar Road, approx 12 mtrs wide road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TEN BKC →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TEN BKC: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TEN BKC

What is the possession date of TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TEN BKC in Bandra East, Mumbai is 5 June 2025 — 24 months later than 6 June 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for TEN BKC?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TEN BKC's builder has filed on MahaRERA, the official one, is 5 June 2025, already 24 months later than the 6 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TEN BKC extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC's builder applied to MahaRERA to extend the completion date 2 times: to 5 June 2024, giving the reason "1. We, hereby apply for extension of registration u/s 6 of the Act r/w Rule 7 of the Rules in respect of Project: TEN BKC, No. P51800004889 which expires on 6th June 2023. This is a redevelopment project. The obligation to undertake construction was that of the Co-promoter, Radius Estates & Developers Pvt. Ltd.(Radius). Radius has gone into CIRP under Insolvency Code and a Resolution plan submitted by Adani Goodhomes Pvt. Ltd. has been approved by the Committee of Creditors (83.93% voting in favour). Project Completion Date proposed in the Resolution Plan is 6th June 2024. Adani has also be…"; to 5 June 2025, giving the reason "the date of 6th June 2024 was proposed in the Resolution Plan which was submitted by Adani Goodhomes Pvt. Ltd. with the Committee of Creditors in December 2021, it was on the basis of a site condition, where work could commence immediately on 1st January 2022. However, after the Resolution Plan was approved by the Committee of Creditors on 21st December 2021 and Adani Goodhomes Pvt. Ltd. was permitted to enter upon the site on 27th December 2021 under the Construction Management Agreement, and after entering the site, Adani Goodhomes Private Limited commenced collating all the drawings of t…".

What is the RERA number of TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TEN BKC in Bandra East, Mumbai is P51800004889.

Is TEN BKC registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC is registered as P51800004889 and its status is "Lapsed (registration period ended)".

What is the construction status of TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 15 towers. GharKundli's full report compares construction progress with the deadline.

Does TEN BKC have complaints on MahaRERA?

82 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TEN BKC safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC is registered on MahaRERA as P51800004889, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 82 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TEN BKC's possession date changes?

The latest dates are on TEN BKC's MahaRERA page (P51800004889). GharKundli's Kundli Watch sends a free WhatsApp update on TEN BKC every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TEN BKC have?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC has 15 buildings filed: Wing 1 with 27 floors and 1 units; WING 2 with 27 floors; WING 3 with 27 floors; WING 4 with 27 floors; WING 5 with 34 floors; WING 6 with 34 floors; and 9 more.

What are the flat sizes (carpet area) in TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for TEN BKC: 4 BHK: 2239 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC stands on 20,149 sq m of land (about 5.0 acres), with 58,365 sq m of sanctioned built-up area and 4,242 sq m of recreational open space.

Where can I read reviews of TEN BKC?

Google Maps has reviews of TEN BKC written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 82 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TEN BKC?

TEN BKC by MIG (Bandra) Realtors & Builders Private Limited is in Bandra East, Mumbai (pincode 400051), near BKC, Khernagar, Sion, Maharashtra, and is registered on MahaRERA as P51800004889, per GharKundli's check of MahaRERA records. Its boundaries filed there include N Dharmadhikari Road, approx 9 mtrs wide road, Madhusudan Kalelkar Road, approx 12 mtrs wide road.

How many homes are in TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC has 1 home in 15 towers registered on MahaRERA, and 0% of them are sold or booked.

When was TEN BKC registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TEN BKC was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on TEN BKC?

35 court cases are listed for TEN BKC on MahaRERA, and 58 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of TEN BKC?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MIG (Bandra) Realtors & Builders Private Limited.

Other projects in pincode 400051

All 79 projects in Bandra East (400051) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.