Shri Sai Vishram CHSL

by Aaryadeep Builders & Developers · Dahisar, MumbaiAlso near Borivali West, I C Colony, Mandapeshwar

Possession date of Shri Sai Vishram CHSL: 31 December 2025, moved from 31 December 2019 (72 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700006499. Status: Lapsed (registration period ended). 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Shri Sai Vishram CHSL?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Shri Sai Vishram CHSL has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800005009)

    Reason the builder gave MahaRERA:
    “The Development plan for 2014-2034 was published by the Municipal Corporation of Greater Mumbai (MCGM) on 25th February 2015. The revised D.P. as stated above was scrapped on 23rd April 2015 due to various anomalies, by the Government of Ma…” Read the full reason“The Development plan for 2014-2034 was published by the Municipal Corporation of Greater Mumbai (MCGM) on 25th February 2015. The revised D.P. as stated above was scrapped on 23rd April 2015 due to various anomalies, by the Government of Maharashtra. The new draft Development Plan (D.P.) was published on 5th February 2016. The MCGM had no clarity for ongoing proposals whether they should apply D.C. Rules 1991 or DCPR 2034. Thus it is a well-known and documented fact that the ambiguity in D.C. Regulations 1991 & DCPR 2034 created confusion and chaos in the MCGM Building Department Further C.…”
  3. 30 December 2022

    Extended at the builder's request (MahaRERA application EXT51800008671)

    Reason the builder gave MahaRERA:
    “Due to the pandemic of Covid 19 and subsequent lockdown of almost14 months, we are facing a shortage of labour. Considering this fact we are sure the work on this project is bound to get delayed. We are trying to finish the remaining work a…” Read the full reason“Due to the pandemic of Covid 19 and subsequent lockdown of almost14 months, we are facing a shortage of labour. Considering this fact we are sure the work on this project is bound to get delayed. We are trying to finish the remaining work as early as possible with whatever resources available at our disposal as of now. The improvement in the pandemic situation is very unpredictable. And hence we request the authority to extend the date of completion up to 30th December, 2022.”
  4. 13 October 2023

    Extended at the builder's request (MahaRERA application EXT51800013926)

    Reason the builder gave MahaRERA:
    “The project had slowed down due to Corona pandemic till August 2021. On September 30th 2021 The Airport Authority Of India asked the MCGM to stop all the permissions given vide their email of the same date. ( Copy attached in Other Column b…” Read the full reason“The project had slowed down due to Corona pandemic till August 2021. On September 30th 2021 The Airport Authority Of India asked the MCGM to stop all the permissions given vide their email of the same date. ( Copy attached in Other Column below). After a process of reapplying, we received the permission after three months on 31/12/2021. Due to this delay of three months our contractor raised some issues of loss due to stoppage of work in this period. The dispute was ultimately resolved after settlement with him in ..... This has caused tremendous financial stress on the project. We have now…”
  5. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT51800015197)

    Reason the builder gave MahaRERA:
    “Dear Sir, We had applied for extension of the project on 22/02/2023 vide extension application no: EXT51800013926. We had submitted the consents of the allottees along with the letter to yourself giving the reasons in brief for the extensio…” Read the full reason“Dear Sir, We had applied for extension of the project on 22/02/2023 vide extension application no: EXT51800013926. We had submitted the consents of the allottees along with the letter to yourself giving the reasons in brief for the extension applied. In both, the consents as well as the covering letter we had requested to extend the project deadline by one year i.e. by 31/12/2023. But somehow due to typographic error in the online application, the date of extension was typed as 13/10/2023 instead of 31/12/2023. We regret this error on our part and hence we had applied for correction in the…”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800024746)

    Reason the builder gave MahaRERA:
    “We were not receiving payments from allottees who have borrowed from banks via housing loan as their banker were asking us to get the project completion date extended from Maharera. Other buyers were also waiting for the same. we have compl…” Read the full reason“We were not receiving payments from allottees who have borrowed from banks via housing loan as their banker were asking us to get the project completion date extended from Maharera. Other buyers were also waiting for the same. we have completed the rehab portion of earlier society members and have applied for part occupancy certificate from MCGM. Now we have made additional finance available and the remaining 15% work of structural construction and 60% of finishing work is being carried out in a phased manner to avoid additional interest cost on fresh borrowings. Once we get the extension a…”

Source: Shri Sai Vishram CHSL’s extension records on MahaRERA (P51700006499), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shri Sai Vishram CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 2 court cases, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700006499
Status
Lapsed (registration period ended)
Builder
Aaryadeep Builders & Developers
Location
Dahisar, Mumbai · 400068
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2025
Delay so far
72 months
Homes
118
Towers
1
Complaints on MahaRERA
7
Court cases listed
2
Appeals at the tribunal
4
Title report on file
Not found

Construction progress of Shri Sai Vishram CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shri Sai Vishram CHSL100%85%85%80%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shri Sai Vishram CHSL every month.

Shri Sai Vishram CHSL: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Shri Sai Vishram CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shri Sai Vishram CHSL: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shri Sai Vishram CHSL

What is the possession date of Shri Sai Vishram CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shri Sai Vishram CHSL in Dahisar, Mumbai is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shri Sai Vishram CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shri Sai Vishram CHSL's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shri Sai Vishram CHSL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2020, giving the reason "The Development plan for 2014-2034 was published by the Municipal Corporation of Greater Mumbai (MCGM) on 25th February 2015. The revised D.P. as stated above was scrapped on 23rd April 2015 due to various anomalies, by the Government of Maharashtra. The new draft Development Plan (D.P.) was published on 5th February 2016. The MCGM had no clarity for ongoing proposals whether they should apply D.C. Rules 1991 or DCPR 2034. Thus it is a well-known and documented fact that the ambiguity in D.C. Regulations 1991 & DCPR 2034 created confusion and chaos in the MCGM Building Department Further C.…"; to 30 December 2022, giving the reason "Due to the pandemic of Covid 19 and subsequent lockdown of almost14 months, we are facing a shortage of labour. Considering this fact we are sure the work on this project is bound to get delayed. We are trying to finish the remaining work as early as possible with whatever resources available at our disposal as of now. The improvement in the pandemic situation is very unpredictable. And hence we request the authority to extend the date of completion up to 30th December, 2022."; to 13 October 2023, giving the reason "The project had slowed down due to Corona pandemic till August 2021. On September 30th 2021 The Airport Authority Of India asked the MCGM to stop all the permissions given vide their email of the same date. ( Copy attached in Other Column below). After a process of reapplying, we received the permission after three months on 31/12/2021. Due to this delay of three months our contractor raised some issues of loss due to stoppage of work in this period. The dispute was ultimately resolved after settlement with him in ..... This has caused tremendous financial stress on the project. We have now…"; to 31 December 2023, giving the reason "Dear Sir, We had applied for extension of the project on 22/02/2023 vide extension application no: EXT51800013926. We had submitted the consents of the allottees along with the letter to yourself giving the reasons in brief for the extension applied. In both, the consents as well as the covering letter we had requested to extend the project deadline by one year i.e. by 31/12/2023. But somehow due to typographic error in the online application, the date of extension was typed as 13/10/2023 instead of 31/12/2023. We regret this error on our part and hence we had applied for correction in the…"; to 31 December 2025, giving the reason "We were not receiving payments from allottees who have borrowed from banks via housing loan as their banker were asking us to get the project completion date extended from Maharera. Other buyers were also waiting for the same. we have completed the rehab portion of earlier society members and have applied for part occupancy certificate from MCGM. Now we have made additional finance available and the remaining 15% work of structural construction and 60% of finishing work is being carried out in a phased manner to avoid additional interest cost on fresh borrowings. Once we get the extension a…".

What is the RERA number of Shri Sai Vishram CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shri Sai Vishram CHSL in Dahisar, Mumbai is P51700006499.

Is Shri Sai Vishram CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL is registered as P51700006499 and its status is "Lapsed (registration period ended)".

What is the construction status of Shri Sai Vishram CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shri Sai Vishram CHSL is 85% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Shri Sai Vishram CHSL have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Shri Sai Vishram CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL is registered on MahaRERA as P51700006499, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 72 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shri Sai Vishram CHSL's possession date changes?

The latest dates are on Shri Sai Vishram CHSL's MahaRERA page (P51700006499). GharKundli's Kundli Watch sends a free WhatsApp update on Shri Sai Vishram CHSL every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shri Sai Vishram CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL has one building filed: Shri Sai Vishram CHSL with 24 floors.

How big is the land of Shri Sai Vishram CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL stands on 2,302 sq m of land (about 0.6 acres), with 7,389 sq m of sanctioned built-up area and 360 sq m of recreational open space.

Where can I read reviews of Shri Sai Vishram CHSL?

Google Maps has reviews of Shri Sai Vishram CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shri Sai Vishram CHSL?

Shri Sai Vishram CHSL by Aaryadeep Builders & Developers is in Dahisar, Mumbai (pincode 400068), near Borivali West, I C Colony, Mandapeshwar, Maharashtra, and is registered on MahaRERA as P51700006499, per GharKundli's check of MahaRERA records.

How many homes are in Shri Sai Vishram CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL has 118 homes in 1 tower registered on MahaRERA.

When was Shri Sai Vishram CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Sai Vishram CHSL was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Shri Sai Vishram CHSL?

2 court cases are listed for Shri Sai Vishram CHSL on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Shri Sai Vishram CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aaryadeep Builders & Developers.

Other projects in pincode 400068

All 180 projects in Dahisar East (400068) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.