Bhaveshwar Nagar Building No. 3
by Yog Reality · Ghatkopar East, MumbaiAlso near Ghatkopar Kirol, Chembur, Rajawadi
Possession: Bhaveshwar Nagar Building No. 3 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003355. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Bhaveshwar Nagar Building No. 3?
How the possession date of Bhaveshwar Nagar Building No. 3 has moved
31 March 2019
Completion date given when the project was registered
31 March 2021
Extended at the builder's request (MahaRERA application EXT51800001611)
Reason the builder gave MahaRERA:
“Two reasons, on submitting seprate PRC with corrected area of final plot no. 25 & handing over of PTC tenements to SRA, FULL OCCUPATION CERTIFICATE will be granted by planning authority SRA to M/s Yog Reality for building named ‘Bhaveshwar…” Read the full reason
“Two reasons, on submitting seprate PRC with corrected area of final plot no. 25 & handing over of PTC tenements to SRA, FULL OCCUPATION CERTIFICATE will be granted by planning authority SRA to M/s Yog Reality for building named ‘Bhaveshwar Nagar Building No.3’. The copies of the said order from competent authority and high court is uploaded for verification. The consent/NOC for extenetion from all new flat purchasers is also uploaded for verification. Also a detailed explanation on 2 reasons for delay in project is uploaded for ready reference and verification.”31 March 2021
Extended at the builder's request (MahaRERA application EXT51800005983)
Reason the builder gave MahaRERA:
“We vide letter dated 10/02/2020, have explained the Association of Allottees of Bhaveshwar Nagar Building No.3 the reasons for delay in project timeline registered with the Maharashtra Real Estate Regulatory Authority under registration No.…” Read the full reason
“We vide letter dated 10/02/2020, have explained the Association of Allottees of Bhaveshwar Nagar Building No.3 the reasons for delay in project timeline registered with the Maharashtra Real Estate Regulatory Authority under registration No. P51800003355 which is beyond our control. Accordingly, on 16/03/2020, the Association of Allottees of Bhaveshwar Nagar Building No.3 as per section 7(3) of the MAHA RERA Act, have given us their consent for extension of project completion upto 31/03/2021 wherein 63 numbers of Allottees were present out of total 98 numbers of Allottees of project. Out of…”30 March 2022
Revised completion date on MahaRERA
Source: Bhaveshwar Nagar Building No. 3’s extension records on MahaRERA (P51800003355), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhaveshwar Nagar Building No. 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the March 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003355
- Status
- Completed
- Builder
- Yog Reality
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Mixed
- Registered on
- 5 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- March 2022
- Delay so far
- 36 months
- Homes
- 98
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Title report on file
- Not found
Construction progress of Bhaveshwar Nagar Building No. 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bhaveshwar Nagar Building No 3 | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhaveshwar Nagar Building No. 3 every month.
Bhaveshwar Nagar Building No. 3: buildings, flats and land, as filed on MahaRERA
- Buildings: Bhaveshwar Nagar Building No 3 (19 floors)
- Land: 1,150 sq m (about 0.3 acres) · sanctioned built-up 3,669 sq m
- Boundaries filed include: Bhaveshwar Cross Road, Bhojraj Damji Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Bhaveshwar Nagar Building No. 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhaveshwar Nagar Building No. 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bhaveshwar Nagar Building No. 3
What is the possession date of Bhaveshwar Nagar Building No. 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Bhaveshwar Nagar Building No. 3 in Ghatkopar East, Mumbai is 30 March 2022 — 36 months later than 31 March 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Bhaveshwar Nagar Building No. 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhaveshwar Nagar Building No. 3's builder has filed on MahaRERA, the official one, is 30 March 2022, already 36 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhaveshwar Nagar Building No. 3 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2021, giving the reason "Two reasons, on submitting seprate PRC with corrected area of final plot no. 25 & handing over of PTC tenements to SRA, FULL OCCUPATION CERTIFICATE will be granted by planning authority SRA to M/s Yog Reality for building named ‘Bhaveshwar Nagar Building No.3’. The copies of the said order from competent authority and high court is uploaded for verification. The consent/NOC for extenetion from all new flat purchasers is also uploaded for verification. Also a detailed explanation on 2 reasons for delay in project is uploaded for ready reference and verification."; to 31 March 2021, giving the reason "We vide letter dated 10/02/2020, have explained the Association of Allottees of Bhaveshwar Nagar Building No.3 the reasons for delay in project timeline registered with the Maharashtra Real Estate Regulatory Authority under registration No. P51800003355 which is beyond our control. Accordingly, on 16/03/2020, the Association of Allottees of Bhaveshwar Nagar Building No.3 as per section 7(3) of the MAHA RERA Act, have given us their consent for extension of project completion upto 31/03/2021 wherein 63 numbers of Allottees were present out of total 98 numbers of Allottees of project. Out of…".
What is the RERA number of Bhaveshwar Nagar Building No. 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Bhaveshwar Nagar Building No. 3 in Ghatkopar East, Mumbai is P51800003355.
Is Bhaveshwar Nagar Building No. 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3 is registered as P51800003355 and its status is "Completed".
What is the construction status of Bhaveshwar Nagar Building No. 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3's status on MahaRERA is "Completed". As filed by the builder, slab work on Bhaveshwar Nagar Building No 3 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Bhaveshwar Nagar Building No. 3 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bhaveshwar Nagar Building No. 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3 is registered on MahaRERA as P51800003355, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bhaveshwar Nagar Building No. 3's possession date changes?
The latest dates are on Bhaveshwar Nagar Building No. 3's MahaRERA page (P51800003355). GharKundli's Kundli Watch sends a free WhatsApp update on Bhaveshwar Nagar Building No. 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhaveshwar Nagar Building No. 3 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3 has one building filed: Bhaveshwar Nagar Building No 3 with 19 floors.
How big is the land of Bhaveshwar Nagar Building No. 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3 stands on 1,150 sq m of land (about 0.3 acres), with 3,669 sq m of sanctioned built-up area.
Where can I read reviews of Bhaveshwar Nagar Building No. 3?
Google Maps has reviews of Bhaveshwar Nagar Building No. 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bhaveshwar Nagar Building No. 3?
Bhaveshwar Nagar Building No. 3 by Yog Reality is in Ghatkopar East, Mumbai (pincode 400077), near Ghatkopar Kirol, Chembur, Rajawadi, Maharashtra, and is registered on MahaRERA as P51800003355, per GharKundli's check of MahaRERA records. Its boundaries filed there include Bhaveshwar Cross Road, Bhojraj Damji Road.
How many homes are in Bhaveshwar Nagar Building No. 3?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3 has 98 homes in 1 tower registered on MahaRERA.
When was Bhaveshwar Nagar Building No. 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Bhaveshwar Nagar Building No. 3 was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bhaveshwar Nagar Building No. 3?
3 court cases are listed for Bhaveshwar Nagar Building No. 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Bhaveshwar Nagar Building No. 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Yog Reality.
Check it yourself on MahaRERA
- How to check the possession date of Bhaveshwar Nagar Building No. 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ghatkopar East
- Jai Arihant
- Terraform Dwarka - Wing D
- Avis Residency
- Omkaar Pride
- Manhattan Residency (A4) - upto 14th Floor
- Om Shreepal
- PALATINA
- North Sea Heights (A1) - upto 14th floor
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.