SHIKARA ESTATES PHASE - II

by Shikara Constructions Pvt. Ltd. · Chipale Village, RaigarhAlso near Panvel

Possession date of SHIKARA ESTATES PHASE - II: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000080638, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHIKARA ESTATES PHASE - II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHIKARA ESTATES PHASE - II has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHIKARA ESTATES PHASE - II’s extension records on MahaRERA (P52000080638), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHIKARA ESTATES PHASE - II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000080638
Status
Registered and active
Builder
Shikara Constructions Pvt. Ltd.
Location
Chipale Village, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
23 Jun 2025
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
7
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of SHIKARA ESTATES PHASE - II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A1%5%100%100%
WING B1%5%100%100%
WING C1%5%100%100%
WING D1%5%100%100%
WING E1%5%100%100%
WING F1%5%100%100%
WING G1%5%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIKARA ESTATES PHASE - II every month.

SHIKARA ESTATES PHASE - II: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (5 floors) · WING B (5 floors) · WING C (5 floors) · WING D (5 floors) · WING E (5 floors) · WING F (5 floors) · WING G (5 floors)
  • Car parking: 76 covered
  • Land: 6,580 sq m (about 1.6 acres) · sanctioned built-up 6,577 sq m · recreational space 660 sq m

The builder’s record and reviews

Shikara Constructions has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 18 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of SHIKARA ESTATES PHASE - II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHIKARA ESTATES PHASE - II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHIKARA ESTATES PHASE - II

What is the possession date of SHIKARA ESTATES PHASE - II?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHIKARA ESTATES PHASE - II in Chipale Village, Raigarh is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHIKARA ESTATES PHASE - II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIKARA ESTATES PHASE - II's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SHIKARA ESTATES PHASE - II?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHIKARA ESTATES PHASE - II in Chipale Village, Raigarh is P52000080638.

Is SHIKARA ESTATES PHASE - II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHIKARA ESTATES PHASE - II is registered as P52000080638 and its status is "Registered and active".

What is the construction status of SHIKARA ESTATES PHASE - II?

According to GharKundli's check of MahaRERA records (updated October 2026), SHIKARA ESTATES PHASE - II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 5% done across 7 towers. GharKundli's full report compares construction progress with the deadline.

Does SHIKARA ESTATES PHASE - II have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHIKARA ESTATES PHASE - II safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHIKARA ESTATES PHASE - II is registered on MahaRERA as P52000080638, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHIKARA ESTATES PHASE - II's possession date changes?

The latest dates are on SHIKARA ESTATES PHASE - II's MahaRERA page (P52000080638). GharKundli's Kundli Watch sends a free WhatsApp update on SHIKARA ESTATES PHASE - II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHIKARA ESTATES PHASE - II have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHIKARA ESTATES PHASE - II has 7 buildings filed: WING A with 5 floors; WING B with 5 floors; WING C with 5 floors; WING D with 5 floors; WING E with 5 floors; WING F with 5 floors; and 1 more.

How much parking does SHIKARA ESTATES PHASE - II have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 76 covered car parking spaces for SHIKARA ESTATES PHASE - II.

How big is the land of SHIKARA ESTATES PHASE - II?

According to GharKundli's check of MahaRERA records (updated October 2026), SHIKARA ESTATES PHASE - II stands on 6,580 sq m of land (about 1.6 acres), with 6,577 sq m of sanctioned built-up area and 660 sq m of recreational open space.

What is the track record of SHIKARA ESTATES PHASE - II's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shikara Constructions has 6 projects on MahaRERA since 2018, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 18 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHIKARA ESTATES PHASE - II?

Google Maps has reviews of SHIKARA ESTATES PHASE - II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHIKARA ESTATES PHASE - II?

SHIKARA ESTATES PHASE - II by Shikara Constructions Pvt. Ltd. is in Chipale Village, Raigarh (pincode 410206), near Panvel, Maharashtra, and is registered on MahaRERA as P52000080638, per GharKundli's check of MahaRERA records.

When was SHIKARA ESTATES PHASE - II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHIKARA ESTATES PHASE - II was registered on MahaRERA on 23 June 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on SHIKARA ESTATES PHASE - II?

No court cases are listed for SHIKARA ESTATES PHASE - II on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SHIKARA ESTATES PHASE - II?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shikara Constructions Pvt. Ltd., which has 5 other projects registered on MahaRERA.

All projects with possession due in 2029 in Raigad →

Other projects in pincode 410206

All 2,664 projects in Panvel (410206) →

Other projects by Shikara Constructions Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.