by Ricardo Constructions Private Limited · Mulund West, MumbaiAlso near Mulund East, Bhandup west, Ghatkopar East
Possession date of Grand Slam and Game Point: 30 August 2028, moved from 30 December 2024 (40 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800005668, and currently active. Its completion date has moved from December 2024 to August 2028: 40 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 57 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Grand Slam and Game Point?
GharKundli’s full report on Grand Slam and Game Point
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 57 complaints and 4 court cases, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800005668
- Status
- Registered and active
- Builder
- Ricardo Constructions Private Limited
- Location
- Mulund West, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- August 2028
- Delay so far
- 40 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 360
- Sold or booked
- 51%
- Towers
- 1
- Complaints on MahaRERA
- 57
- Court cases listed
- 4
- Appeals at the tribunal
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Grand Slam and Game Point, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GRAND SLAM AND GAME POINT | 100% | 1% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GRAND SLAM AND GAME POINT: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Grand Slam and Game Point every month.
Grand Slam and Game Point: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 656 – 786 | 248 |
| 3 BHK | 896 – 1,002 | 112 |
- Buildings: GRAND SLAM AND GAME POINT (48 floors, 360 units)
- Car parking: 435 covered
- Land: 1,008 sq m (about 0.2 acres) · sanctioned built-up 984 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects.
Read Google reviews of Grand Slam and Game Point →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Grand Slam and Game Point: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Grand Slam and Game Point
What is the possession date of Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Grand Slam and Game Point in Mulund West, Mumbai is 30 August 2028 — 40 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Grand Slam and Game Point?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Grand Slam and Game Point's builder has filed on MahaRERA, the official one, is 30 August 2028, already 40 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Grand Slam and Game Point in Mulund West, Mumbai is P51800005668.
Is Grand Slam and Game Point registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point is registered as P51800005668 and its status is "Registered and active".
What is the construction status of Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GRAND SLAM AND GAME POINT is 1% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Grand Slam and Game Point have complaints on MahaRERA?
57 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Grand Slam and Game Point safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point is registered on MahaRERA as P51800005668, its completion date has moved 40 months since registration and 57 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Grand Slam and Game Point's possession date changes?
The latest dates are on Grand Slam and Game Point's MahaRERA page (P51800005668). GharKundli's Kundli Watch sends a free WhatsApp update on Grand Slam and Game Point every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Grand Slam and Game Point have?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point has one building filed: GRAND SLAM AND GAME POINT with 48 floors and 360 units.
What are the flat sizes (carpet area) in Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Grand Slam and Game Point: 2 BHK: 656 to 786 sq ft carpet (248 homes); 3 BHK: 896 to 1002 sq ft carpet (112 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Grand Slam and Game Point have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 435 covered car parking spaces for Grand Slam and Game Point.
How big is the land of Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point stands on 1,008 sq m of land (about 0.2 acres), with 984 sq m of sanctioned built-up area.
What is the track record of Grand Slam and Game Point's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Grand Slam and Game Point?
Google Maps has reviews of Grand Slam and Game Point written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 57 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Grand Slam and Game Point?
Grand Slam and Game Point by Ricardo Constructions Private Limited is in Mulund West, Mumbai (pincode 400080), near Mulund East, Bhandup west, Ghatkopar East, Maharashtra, and is registered on MahaRERA as P51800005668, per GharKundli's check of MahaRERA records.
How many homes are in Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point has 360 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.
When was Grand Slam and Game Point registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Grand Slam and Game Point was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Grand Slam and Game Point?
4 court cases are listed for Grand Slam and Game Point on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Grand Slam and Game Point?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ricardo Constructions Private Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Grand Slam and Game Point
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400080
- OLD HEMANT VILLA CO. OP. HOUSING SOC. LTD.
- Keshavpada
- ARIHANT ROYALE
- THE SANCTUARY - TOWER 5
- Dhanraj Tower
- Madhuvan Nivanta
- Shraddha Paradise Enclave
- Malhar Guide
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.