Raichandani Pentagon Towers

by RAICHANDANI CONSTRUCTIONS & DEVELOPERS · Karvenagar Hingne Budruk, Pune 411052Also near Navsahyadri, Vadgaon BudrukRegistered on MahaRERA as “PENTAGON TOWERS”

What’s in the report? →

Possession date of Raichandani Pentagon Towers (MahaRERA P52100021223): 1 July 2024, moved from 30 March 2023 (16 months later), and it has already passed. It has 65 homes. 1 complaint on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100021223. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100021223, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2024) has passed.

What do you want to know about Raichandani Pentagon Towers?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Raichandani Pentagon Towers has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 31 July 2023

    Extended at the builder's request (MahaRERA application EXT52100012438)

    Reason the builder gave MahaRERA: “Covid”
  3. 31 October 2023

    Extended at the builder's request (MahaRERA application EXT52100016874)

    Reason the builder gave MahaRERA:
    “We are applying for extension since construction work is in process and completion certificate from local authority is yet to obtain due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of u…” Read the full reason“We are applying for extension since construction work is in process and completion certificate from local authority is yet to obtain due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Appx 80% project is completed. We request you to kindly extend the project completion date to 31/10/2023.”
  4. 31 January 2024

    Extended at the builder's request (MahaRERA application EXT52100017782)

    Reason the builder gave MahaRERA:
    “Due to Covid-19 pandemic we were not able to construct anymore because of lack of labour contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an exten…” Read the full reason“Due to Covid-19 pandemic we were not able to construct anymore because of lack of labour contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an extension till 31/01/2024 for completion of the project.”
  5. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT52100018840)

    Reason the builder gave MahaRERA: “due to delay in Occupancy certificate from concerned department”
  6. 1 July 2024

    Extended at the builder's request (MahaRERA application EXT52100019462)

    Reason the builder gave MahaRERA: “Project completion is delayed due to delay in obtaining Government Aprovals(i.e. Completion/occupency Certificate). Please grant extension for the project is requested till 1/07/2024.”

Source: Raichandani Pentagon Towers’s extension records on MahaRERA (P52100021223), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Raichandani Pentagon Towers

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100021223
Status
Lapsed (registration period ended)
Builder
RAICHANDANI CONSTRUCTIONS & DEVELOPERS
Location
Karvenagar Hingne Budruk, Pune · 411052
Project type
Others
Registered on
14 Jun 2019
Completion date at registration
March 2023
Latest completion date
July 2024
Delay so far
16 months
Homes
65
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Raichandani Pentagon Towers, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PENTAGON TOWERS100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Raichandani Pentagon Towers every 1–2 months.

Raichandani Pentagon Towers: buildings, flats and land, as filed on MahaRERA

  • Buildings: PENTAGON TOWERS (12 floors)
  • Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 7,699 sq m
  • Land, as filed: C.TS.535 S.NO.11/2 KARVENAGAR HINGNE BUDRUK, PUNE
  • Map: Get directions

The builder’s record and reviews

Raichandani Constructions (a group of 3 linked companies) has 14 projects on MahaRERA since 2019, this one included. Of the 14 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 11 months); 6 still being built, 3 past the promised date (typically 11 months late); 5 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Raichandani Pentagon Towers →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Raichandani Pentagon Towers: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Raichandani Pentagon Towers

What is the possession date of Raichandani Pentagon Towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Raichandani Pentagon Towers in Karvenagar Hingne Budruk, Pune is 1 July 2024 — 16 months later than 30 March 2023, the date given at registration. That date has already passed.

The date has already moved 16 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Raichandani Pentagon Towers?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Raichandani Pentagon Towers's builder has filed on MahaRERA, the official one, is 1 July 2024, already 16 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Raichandani Pentagon Towers extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers's builder applied to MahaRERA to extend the completion date 5 times: to 31 July 2023, giving the reason "Covid"; to 31 October 2023, giving the reason "We are applying for extension since construction work is in process and completion certificate from local authority is yet to obtain due to following reasons: a) Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis. b) Appx 80% project is completed. We request you to kindly extend the project completion date to 31/10/2023."; to 31 January 2024, giving the reason "Due to Covid-19 pandemic we were not able to construct anymore because of lack of labour contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an extension till 31/01/2024 for completion of the project."; to 31 March 2024, giving the reason "due to delay in Occupancy certificate from concerned department"; to 1 July 2024, giving the reason "Project completion is delayed due to delay in obtaining Government Aprovals(i.e. Completion/occupency Certificate). Please grant extension for the project is requested till 1/07/2024.".

What is the RERA number of Raichandani Pentagon Towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Raichandani Pentagon Towers in Karvenagar Hingne Budruk, Pune is P52100021223.

Is Raichandani Pentagon Towers registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers is registered as P52100021223 and its status is "Lapsed (registration period ended)".

What is the current construction status of Raichandani Pentagon Towers? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PENTAGON TOWERS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Raichandani Pentagon Towers have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →

Is Raichandani Pentagon Towers safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers is registered on MahaRERA as P52100021223, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 16 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Raichandani Pentagon Towers?

Raichandani Pentagon Towers isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Raichandani Pentagon Towers?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Raichandani Pentagon Towers: gharkundli.com/tools/property-cost-calculator

Has Raichandani Pentagon Towers received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 1 July 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Raichandani Pentagon Towers?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (1 July 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Raichandani Pentagon Towers uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Raichandani Pentagon Towers was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Raichandani Pentagon Towers's possession date changes?

The latest dates are on Raichandani Pentagon Towers's MahaRERA page (P52100021223). GharKundli's Kundli Watch sends a free WhatsApp update on Raichandani Pentagon Towers every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Raichandani Pentagon Towers have?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers has one building filed: PENTAGON TOWERS with 12 floors.

How big is the land of Raichandani Pentagon Towers?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers stands on 2,000 sq m of land (about 0.5 acres), with 7,699 sq m of sanctioned built-up area.

What is the track record of Raichandani Pentagon Towers's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Constructions (a group of 3 linked companies) has 14 projects on MahaRERA since 2019, this one included. Of the 14 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 11 months); 6 still being built, 3 past the promised date (typically 11 months late); 5 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Raichandani Pentagon Towers?

Google Maps has reviews of Raichandani Pentagon Towers written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Raichandani Pentagon Towers?

Raichandani Pentagon Towers by RAICHANDANI CONSTRUCTIONS & DEVELOPERS is in Karvenagar Hingne Budruk, Pune, pincode 411052 (near Navsahyadri, Vadgaon Budruk), Maharashtra, and is registered on MahaRERA as P52100021223, per GharKundli's check of MahaRERA records. Its land is filed as C.TS.535 S.NO.11/2 KARVENAGAR HINGNE BUDRUK, PUNE. GharKundli lists all 72 MahaRERA projects in Navsahyadri (411052).

How many flats are in Raichandani Pentagon Towers?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers has 65 homes in 1 tower registered on MahaRERA.

When was Raichandani Pentagon Towers registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raichandani Pentagon Towers was registered on MahaRERA on 14 June 2019. GharKundli did not find a title report on the land on file there.

Does Raichandani Pentagon Towers have any legal issues or court cases?

No court cases are listed for Raichandani Pentagon Towers on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Raichandani Pentagon Towers?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAICHANDANI CONSTRUCTIONS & DEVELOPERS, which has 3 other projects registered on MahaRERA.

Other projects in Navsahyadri (411052)

All 72 projects in Navsahyadri (411052) →

Other projects by RAICHANDANI CONSTRUCTIONS & DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.