Srkd Komal

by SRKD LANDMARK LLP · Karvenagar, Pune 411052Also near Hingne Budruk, Karve Nagar, Hingane KhurdRegistered on MahaRERA as “Komal”

What’s in the report? →

Possession date of Srkd Komal (MahaRERA P52100047236): 30 June 2026, moved from 31 January 2025 (17 months later), and it has already passed. It has 14 homes, 80% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100047236. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100047236, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2026) has passed.

What do you want to know about Srkd Komal?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Srkd Komal has moved

  1. 31 January 2025

    Completion date given when the project was registered

  2. 31 July 2025

    Extended at the builder's request (MahaRERA application EXT52100027364)

    Reason the builder gave MahaRERA: “I was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EA16082502384)

    Reason the builder gave MahaRERA: “1. LACK OF LABOUR 2. NON AVAILIBILITY OF MATERIAL 3. DELAY IN REVISED SANCTION”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA16012619472)

    Reason the builder gave MahaRERA: “We have already applied for the Occupancy Certificate to the planning authority i.e. Pune Municipal Corporation in the month of September 2025 but we could not get the OC till now due to some unavoidable circumstances.”

Source: Srkd Komal’s extension records on MahaRERA (P52100047236), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Srkd Komal

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100047236
Status
Lapsed (registration period ended)
Builder
SRKD LANDMARK LLP
Location
Karvenagar, Pune · 411052
Project type
Residential / Group Housing
Registered on
12 Oct 2022
Completion date at registration
January 2025
Latest completion date
June 2026
Delay so far
17 months
Homes
14
Sold or booked
80%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Srkd Komal, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Komal100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Komal: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Srkd Komal every 1–2 months.

Srkd Komal: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Srkd Landmark has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Srkd Komal →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Srkd Komal: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Srkd Komal

What is the possession date of Srkd Komal?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Srkd Komal in Karvenagar, Pune is 30 June 2026 — 17 months later than 31 January 2025, the date given at registration. That date has already passed.

The date has already moved 17 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Srkd Komal?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Srkd Komal's builder has filed on MahaRERA, the official one, is 30 June 2026, already 17 months later than the 31 January 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Srkd Komal extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal's builder applied to MahaRERA to extend the completion date 3 times: to 31 July 2025, giving the reason "I was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion."; to 31 December 2025, giving the reason "1. LACK OF LABOUR 2. NON AVAILIBILITY OF MATERIAL 3. DELAY IN REVISED SANCTION"; to 30 June 2026, giving the reason "We have already applied for the Occupancy Certificate to the planning authority i.e. Pune Municipal Corporation in the month of September 2025 but we could not get the OC till now due to some unavoidable circumstances.".

What is the RERA number of Srkd Komal?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Srkd Komal in Karvenagar, Pune is P52100047236.

Is Srkd Komal registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal is registered as P52100047236 and its status is "Lapsed (registration period ended)".

What is the current construction status of Srkd Komal? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Komal is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Srkd Komal have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Srkd Komal safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal is registered on MahaRERA as P52100047236, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Srkd Komal?

Srkd Komal isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Srkd Komal?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Srkd Komal: gharkundli.com/tools/property-cost-calculator

Has Srkd Komal received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Srkd Komal?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Srkd Komal a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal is a redevelopment: 2 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Srkd Komal uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Srkd Komal was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Srkd Komal's possession date changes?

The latest dates are on Srkd Komal's MahaRERA page (P52100047236). GharKundli's Kundli Watch sends a free WhatsApp update on Srkd Komal every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Srkd Komal have?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal has one building filed: Komal with 5 floors and 14 units.

How much parking does Srkd Komal have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered car parking spaces for Srkd Komal.

How big is the land of Srkd Komal?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal stands on 500 sq m of land (about 0.1 acres), with 909 sq m of sanctioned built-up area.

What is the track record of Srkd Komal's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Landmark has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 15 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Srkd Komal?

Google Maps has reviews of Srkd Komal written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Srkd Komal?

Srkd Komal by SRKD LANDMARK LLP is in Karvenagar, Pune, pincode 411052 (near Hingne Budruk, Karve Nagar, Hingane Khurd), Maharashtra, and is registered on MahaRERA as P52100047236, per GharKundli's check of MahaRERA records. Its boundaries filed there include Gaothan Road. Its land is filed as S No. 1, Hissa No. 26/1/2, Karvenagar. GharKundli lists all 72 MahaRERA projects in Navsahyadri (411052).

How many flats are in Srkd Komal, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal has 14 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.

When was Srkd Komal registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Srkd Komal was registered on MahaRERA on 12 October 2022. GharKundli did not find a title report on the land on file there.

Does Srkd Komal have any legal issues or court cases?

No court cases are listed for Srkd Komal on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Srkd Komal?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SRKD LANDMARK LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Navsahyadri (411052)

All 72 projects in Navsahyadri (411052) →

Other projects by SRKD LANDMARK LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.