Anika Gokul Niwas

by ALOK ARUN SHETH · Karvenagar Hingane, Pune 411052Also near Kothrud, Dahanukar Colony, Karve nagar

What’s in the report? →

Possession date of Anika Gokul Niwas (MahaRERA P52100045465): 31 December 2026, moved from 31 December 2025 (12 months later). It has 39 homes, 73% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100045465, and currently active.

Source: MahaRERA website — records for P52100045465, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Anika Gokul Niwas?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Anika Gokul Niwas has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA04022619720)

    Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”

Source: Anika Gokul Niwas’s extension records on MahaRERA (P52100045465), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Anika Gokul Niwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100045465
Status
Registered and active
Builder
ALOK ARUN SHETH
Location
Karvenagar Hingane, Pune · 411052
Project type
Others
Registered on
19 May 2022
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
39
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Anika Gokul Niwas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ANIKA GOKUL NIWAS100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • ANIKA GOKUL NIWAS: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anika Gokul Niwas every 1–2 months.

Anika Gokul Niwas: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Arun Pitamber Sheth (a group of 3 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 6 months); 6 still being built, 2 past the promised date (typically 10 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Anika Gokul Niwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anika Gokul Niwas: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Anika Gokul Niwas

What is the possession date of Anika Gokul Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anika Gokul Niwas in Karvenagar Hingane, Pune is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Anika Gokul Niwas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anika Gokul Niwas's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Anika Gokul Niwas extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.".

What is the RERA number of Anika Gokul Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Anika Gokul Niwas in Karvenagar Hingane, Pune is P52100045465.

Is Anika Gokul Niwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas is registered as P52100045465 and its status is "Registered and active".

What is the current construction status of Anika Gokul Niwas? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANIKA GOKUL NIWAS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Anika Gokul Niwas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Anika Gokul Niwas safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas is registered on MahaRERA as P52100045465, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Anika Gokul Niwas?

Anika Gokul Niwas is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Anika Gokul Niwas?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Anika Gokul Niwas: gharkundli.com/tools/property-cost-calculator

Has Anika Gokul Niwas received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Anika Gokul Niwas uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Anika Gokul Niwas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Anika Gokul Niwas's possession date changes?

The latest dates are on Anika Gokul Niwas's MahaRERA page (P52100045465). GharKundli's Kundli Watch sends a free WhatsApp update on Anika Gokul Niwas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Anika Gokul Niwas have?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas has one building filed: ANIKA GOKUL NIWAS with 8 floors and 45 units.

How big is the land of Anika Gokul Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas stands on 631 sq m of land (about 0.2 acres), with 1,476 sq m of sanctioned built-up area.

What is the track record of Anika Gokul Niwas's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Arun Pitamber Sheth (a group of 3 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 6 months); 6 still being built, 2 past the promised date (typically 10 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Anika Gokul Niwas?

Google Maps has reviews of Anika Gokul Niwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Anika Gokul Niwas?

Anika Gokul Niwas by ALOK ARUN SHETH is in Karvenagar Hingane, Pune, pincode 411052 (near Kothrud, Dahanukar Colony, Karve nagar), Maharashtra, and is registered on MahaRERA as P52100045465, per GharKundli's check of MahaRERA records. Its land is filed as S. NO. 19/1+8B, PLOT NO. 41/2. GharKundli lists all 72 MahaRERA projects in Navsahyadri (411052).

How many flats are in Anika Gokul Niwas, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas has 39 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was Anika Gokul Niwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Anika Gokul Niwas was registered on MahaRERA on 19 May 2022. GharKundli did not find a title report on the land on file there.

Does Anika Gokul Niwas have any legal issues or court cases?

No court cases are listed for Anika Gokul Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Anika Gokul Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALOK ARUN SHETH.

All projects with possession due in 2026 in Pune →

Other projects in Navsahyadri (411052)

All 72 projects in Navsahyadri (411052) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.