by Siddharth Properties (Saarrthi) · Mahalunge, Pune 411045Also near Balewadi, Koregaon Park, N.I.A

What’s in the report? →

Possession date of Saarrthi Skybay III (MahaRERA P52100022081): 30 April 2027, moved from 30 March 2024 (33 months later). It has 318 homes, 94% sold or booked. 1 complaint on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100022081, and currently active. Its completion date has moved from March 2024 to April 2027: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100022081, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Saarrthi Skybay III?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Saarrthi Skybay III has moved

  1. 30 March 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52100011133)

    Reason the builder gave MahaRERA:
    “Due to lockdown the project when originally registered could not be launched and started work upon. No bookings were taken under the original completion date of 30/03/2024. We have obtained 100% consent of existing allottees to change date…” Read the full reason“Due to lockdown the project when originally registered could not be launched and started work upon. No bookings were taken under the original completion date of 30/03/2024. We have obtained 100% consent of existing allottees to change date to 31/12/2026 as per attached consent u/s 14(2) read with circular 28/2021”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Saarrthi Skybay III’s extension records on MahaRERA (P52100022081), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Saarrthi Skybay III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100022081
Status
Registered and active
Builder
Siddharth Properties
Location
Mahalunge, Pune · 411045
Project type
Residential / Group Housing
Registered on
25 Aug 2019
Completion date at registration
March 2024
Latest completion date
April 2027
Delay so far
33 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
318
Sold or booked
94%
Towers
2
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Saarrthi Skybay III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A100%100%40%0%
Building B100%100%42%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building A: covers 29 floors
  • Building B: covers 29 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saarrthi Skybay III every 1–2 months.

Saarrthi Skybay III: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building A (29 floors, 162 units) · Building B (29 floors, 156 units)
  • Land: 2,102 sq m (about 0.5 acres) · sanctioned built-up 19,585 sq m · recreational space 3,492 sq m
  • Land, as filed: S. no 60/1 Mahalunge
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Saarrthi Realty And Infra Limited Liability Partnership (a group of 10 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 9 finished, 4 within the promised date and 5 needed more time (typically 17 months); 6 still being built, 5 past the promised date (typically 34 months late); 6 lapsed. 33 complaints on MahaRERA across 11 projects.

Read Google reviews of Saarrthi Skybay III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Saarrthi Skybay III: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Saarrthi Skybay III

What is the possession date of Saarrthi Skybay III?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saarrthi Skybay III in Mahalunge, Pune is 30 April 2027 — 33 months later than 30 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 33 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Saarrthi Skybay III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Saarrthi Skybay III's builder has filed on MahaRERA, the official one, is 30 April 2027, already 33 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Saarrthi Skybay III extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to lockdown the project when originally registered could not be launched and started work upon. No bookings were taken under the original completion date of 30/03/2024. We have obtained 100% consent of existing allottees to change date to 31/12/2026 as per attached consent u/s 14(2) read with circular 28/2021". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Saarrthi Skybay III?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saarrthi Skybay III in Mahalunge, Pune is P52100022081.

Is Saarrthi Skybay III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III is registered as P52100022081 and its status is "Registered and active".

What is the current construction status of Saarrthi Skybay III? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Saarrthi Skybay III have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

1 complaint is filed on this project. Know what went wrong before you pay a token. See how it ended →

Is Saarrthi Skybay III safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III is registered on MahaRERA as P52100022081, its completion date has moved 33 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Saarrthi Skybay III?

Saarrthi Skybay III is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Saarrthi Skybay III?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saarrthi Skybay III: gharkundli.com/tools/property-cost-calculator

Has Saarrthi Skybay III received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Saarrthi Skybay III uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saarrthi Skybay III was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Saarrthi Skybay III have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Saarrthi Skybay (P52100004803, possession 30 Nov 2020); Saarrthi Skybay II (P52100016176, possession 30 Sep 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Saarrthi Skybay III's possession date changes?

The latest dates are on Saarrthi Skybay III's MahaRERA page (P52100022081). GharKundli's Kundli Watch sends a free WhatsApp update on Saarrthi Skybay III every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Saarrthi Skybay III have?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III has 2 buildings filed: Building A with 29 floors and 162 units; Building B with 29 floors and 156 units.

How big is the land of Saarrthi Skybay III?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III stands on 2,102 sq m of land (about 0.5 acres), with 19,585 sq m of sanctioned built-up area and 3,492 sq m of recreational open space.

What is the track record of Saarrthi Skybay III's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Realty And Infra Limited Liability Partnership (a group of 10 linked companies) has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 9 finished, 4 within the promised date and 5 needed more time (typically 17 months); 6 still being built, 5 past the promised date (typically 34 months late); 6 lapsed. 33 complaints on MahaRERA across 11 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Saarrthi Skybay III?

Google Maps has reviews of Saarrthi Skybay III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Saarrthi Skybay III?

Saarrthi Skybay III by Siddharth Properties (Saarrthi) is in Mahalunge, Pune, pincode 411045 (near Balewadi, Koregaon Park, N.I.A), Maharashtra, and is registered on MahaRERA as P52100022081, per GharKundli's check of MahaRERA records. Its land is filed as S. no 60/1 Mahalunge. GharKundli lists all 713 MahaRERA projects in Baner (411045).

How many flats are in Saarrthi Skybay III, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III has 318 homes in 2 towers registered on MahaRERA, and 94% of them are sold or booked.

When was Saarrthi Skybay III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saarrthi Skybay III was registered on MahaRERA on 25 August 2019. GharKundli did not find a title report on the land on file there.

Does Saarrthi Skybay III have any legal issues or court cases?

1 court case is listed for Saarrthi Skybay III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Saarrthi Skybay III?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Siddharth Properties, the company Saarrthi files this project under, which has 8 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Baner (411045)

All 713 projects in Baner (411045) →

Other projects by Siddharth Properties

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.