Godrej Meadows- Phase 2

by Mahalunge Township Developers Private Limited (Godrej) · Mahalunge, Pune 411045

What’s in the report? →

Possession date of Godrej Meadows- Phase 2 (MahaRERA P52100031794): 31 December 2026, moved from 31 December 2025 (12 months later). It has 488 homes, 99% sold or booked. 83 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100031794, and currently active.

Source: MahaRERA website — records for P52100031794, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Godrej Meadows- Phase 2?

4 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Godrej Meadows- Phase 2 has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA23122518928)

    Reason the builder gave MahaRERA:
    “The delay in project completion was caused by a combination of factors beyond the reasonable control of the developer, including abnormal variation in material prices and labour wages, supply chain disruptions due to industry strikes, acute…” Read the full reason“The delay in project completion was caused by a combination of factors beyond the reasonable control of the developer, including abnormal variation in material prices and labour wages, supply chain disruptions due to industry strikes, acute labour shortages, and regulatory construction bans imposed due to environmental concerns. These factors collectively disrupted construction activities, affected productivity, and extended project timelines. The developer has acted in good faith and exercised due diligence in managing the project under challenging conditions. All possible steps have been…”

Source: Godrej Meadows- Phase 2’s extension records on MahaRERA (P52100031794), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Godrej Meadows- Phase 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 83 complaints and 4 court cases, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100031794
Status
Registered and active
Builder
Mahalunge Township Developers Private Limited
Location
Mahalunge, Pune · 411045
Project type
Others
Registered on
12 Nov 2021
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
488
Sold or booked
99%
Towers
3
Complaints on MahaRERA
83
Court cases listed
4
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
7

Construction progress of Godrej Meadows- Phase 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower- 01100%100%98%95%
Tower- 02100%100%99%95%
Commercial Building100%100%100%92%

Commencement certificate (CC), as filed on MahaRERA

  • Tower- 01: covers 33 floors
  • Tower- 02: covers 33 floors
  • Commercial Building: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Godrej Meadows- Phase 2 every 1–2 months.

Godrej Meadows- Phase 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Tower- 01 (33 floors, 244 units) · Tower- 02 (33 floors, 244 units) · Commercial Building (4 floors, 10 units)
  • Land: 9,290 sq m (about 2.3 acres) · sanctioned built-up 37,971 sq m · recreational space 599 sq m
  • Boundaries filed include: CG-05 play-ground
  • Land, as filed: Sector R8- Survey No 42/4 part, 43/1 part and 43/2/1 part
  • Map: Get directions

The builder’s record and reviews

Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 23 finished, 18 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 2 lapsed. 571 complaints on MahaRERA across 62 projects.

Read Google reviews of Godrej Meadows- Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Godrej Meadows- Phase 2: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Godrej Meadows- Phase 2

What is the possession date of Godrej Meadows- Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Godrej Meadows- Phase 2 in Mahalunge, Pune is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Godrej Meadows- Phase 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Godrej Meadows- Phase 2's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Godrej Meadows- Phase 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The delay in project completion was caused by a combination of factors beyond the reasonable control of the developer, including abnormal variation in material prices and labour wages, supply chain disruptions due to industry strikes, acute labour shortages, and regulatory construction bans imposed due to environmental concerns. These factors collectively disrupted construction activities, affected productivity, and extended project timelines. The developer has acted in good faith and exercised due diligence in managing the project under challenging conditions. All possible steps have been…".

What is the RERA number of Godrej Meadows- Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Godrej Meadows- Phase 2 in Mahalunge, Pune is P52100031794.

Is Godrej Meadows- Phase 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 is registered as P52100031794 and its status is "Registered and active".

What is the current construction status of Godrej Meadows- Phase 2? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Godrej Meadows- Phase 2 have complaints on MahaRERA?

83 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

83 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is Godrej Meadows- Phase 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 is registered on MahaRERA as P52100031794, its completion date has moved 12 months since registration and 83 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Godrej Meadows- Phase 2?

Godrej Meadows- Phase 2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Godrej Meadows- Phase 2?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Godrej Meadows- Phase 2: gharkundli.com/tools/property-cost-calculator

Has Godrej Meadows- Phase 2 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Godrej Meadows- Phase 2 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Godrej Meadows- Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Godrej Meadows- Phase 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Godrej Meadows (P52100031791). Check that your agreement names the registration of your own wing.

How can I get updates if Godrej Meadows- Phase 2's possession date changes?

The latest dates are on Godrej Meadows- Phase 2's MahaRERA page (P52100031794). GharKundli's Kundli Watch sends a free WhatsApp update on Godrej Meadows- Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Godrej Meadows- Phase 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 has 3 buildings filed: Tower- 01 with 33 floors and 244 units; Tower- 02 with 33 floors and 244 units; Commercial Building with 4 floors and 10 units.

How big is the land of Godrej Meadows- Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 stands on 9,290 sq m of land (about 2.3 acres), with 37,971 sq m of sanctioned built-up area and 599 sq m of recreational open space.

What is the track record of Godrej Meadows- Phase 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 23 finished, 18 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 2 lapsed. 571 complaints on MahaRERA across 62 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Godrej Meadows- Phase 2?

Google Maps has reviews of Godrej Meadows- Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 83 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Godrej Meadows- Phase 2?

Godrej Meadows- Phase 2 by Mahalunge Township Developers Private Limited (Godrej) is in Mahalunge, Pune, pincode 411045, Maharashtra, and is registered on MahaRERA as P52100031794, per GharKundli's check of MahaRERA records. Its boundaries filed there include CG-05 play-ground. Its land is filed as Sector R8- Survey No 42/4 part, 43/1 part and 43/2/1 part. GharKundli lists all 713 MahaRERA projects in Baner (411045).

How many flats are in Godrej Meadows- Phase 2, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 has 488 homes in 3 towers registered on MahaRERA, and 99% of them are sold or booked.

When was Godrej Meadows- Phase 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Meadows- Phase 2 was registered on MahaRERA on 12 November 2021. GharKundli did not find a title report on the land on file there.

Does Godrej Meadows- Phase 2 have any legal issues or court cases?

4 court cases are listed for Godrej Meadows- Phase 2 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Godrej Meadows- Phase 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Mahalunge Township Developers Private Limited, the company Godrej files this project under, which has 7 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Baner (411045)

All 713 projects in Baner (411045) →

Other projects by Mahalunge Township Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.