Possession date of Solitaire Business Hub -III, Phase- I, Baner (MahaRERA P52100022782): 31 December 2026, moved from 30 December 2025 (12 months later). 55 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100022782, and currently active.

Source: MahaRERA website — records for P52100022782, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Solitaire Business Hub -III, Phase- I, Baner?

2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Solitaire Business Hub -III, Phase- I, Baner has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA11122518633)

    Reason the builder gave MahaRERA: “As per order of the Hon'ble Chairman (MahaRERA) Dated 23/01/2026. we request you kindly to grant us extension till 31/12/2026.”

Source: Solitaire Business Hub -III, Phase- I, Baner’s extension records on MahaRERA (P52100022782), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Solitaire Business Hub -III, Phase- I, Baner

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 55 complaints and 2 court cases, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100022782
Status
Registered and active
Builder
Baner Land Developers LLP
Location
Baner, Pune · 411045
Project type
Commercial
Registered on
17 Oct 2019
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
0
Sold or booked
99%
Towers
4
Complaints on MahaRERA
55
Court cases listed
2
Appeals at the tribunal
4
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Solitaire Business Hub -III, Phase- I, Baner, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PH -1 Ground To 15th Floor100%100%97%65%
PH - III0%0%0%0%
PH -II-16th to 22nd Floor100%100%97%65%
PH - IV0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PH -1 Ground To 15th Floor: covers 17 floors
  • PH -II-16th to 22nd Floor: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Solitaire Business Hub -III, Phase- I, Baner every 1–2 months.

Solitaire Business Hub -III, Phase- I, Baner: buildings, flats and land, as filed on MahaRERA

  • Buildings: PH -1 Ground To 15th Floor (17 floors, 215 units) · PH -II-16th to 22nd Floor (7 floors, 63 units)
  • Car parking: 387 covered
  • Land: 18,145 sq m (about 4.5 acres) · sanctioned built-up 20,236 sq m · recreational space 919 sq m
  • Land, as filed: S No 9/3 9/4 9/5 9/6 9/7
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Classic Promoters And Builders (a group of 8 linked companies) has 30 projects on MahaRERA since 2017, this one included. Of the 30 GharKundli has checked: 10 finished, 2 within the promised date and 8 needed more time (typically 6 months); 20 still being built, 12 past the promised date (typically 22 months late). 230 complaints on MahaRERA across 17 projects.

Read Google reviews of Solitaire Business Hub -III, Phase- I, Baner →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Solitaire Business Hub -III, Phase- I, Baner: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Solitaire Business Hub -III, Phase- I, Baner

What is the possession date of Solitaire Business Hub -III, Phase- I, Baner?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Solitaire Business Hub -III, Phase- I, Baner in Baner, Pune is 31 December 2026 — 12 months later than 30 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Solitaire Business Hub -III, Phase- I, Baner?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Solitaire Business Hub -III, Phase- I, Baner's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Solitaire Business Hub -III, Phase- I, Baner extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "As per order of the Hon'ble Chairman (MahaRERA) Dated 23/01/2026. we request you kindly to grant us extension till 31/12/2026.".

What is the RERA number of Solitaire Business Hub -III, Phase- I, Baner?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Solitaire Business Hub -III, Phase- I, Baner in Baner, Pune is P52100022782.

Is Solitaire Business Hub -III, Phase- I, Baner registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner is registered as P52100022782 and its status is "Registered and active".

What is the current construction status of Solitaire Business Hub -III, Phase- I, Baner? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Solitaire Business Hub -III, Phase- I, Baner have complaints on MahaRERA?

55 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

55 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is Solitaire Business Hub -III, Phase- I, Baner safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner is registered on MahaRERA as P52100022782, its completion date has moved 12 months since registration and 55 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Solitaire Business Hub -III, Phase- I, Baner?

Solitaire Business Hub -III, Phase- I, Baner is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Solitaire Business Hub -III, Phase- I, Baner?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Solitaire Business Hub -III, Phase- I, Baner: gharkundli.com/tools/property-cost-calculator

Has Solitaire Business Hub -III, Phase- I, Baner received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Solitaire Business Hub -III, Phase- I, Baner uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Solitaire Business Hub -III, Phase- I, Baner was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Solitaire Business Hub -III, Phase- I, Baner have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Solitaire Business Hub-III-Phase-II,Baner (P52100025108, possession 31 Dec 2026); Solitaire Business Hub-III-Phase-III,Baner (P52100024890, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.

How can I get updates if Solitaire Business Hub -III, Phase- I, Baner's possession date changes?

The latest dates are on Solitaire Business Hub -III, Phase- I, Baner's MahaRERA page (P52100022782). GharKundli's Kundli Watch sends a free WhatsApp update on Solitaire Business Hub -III, Phase- I, Baner every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Solitaire Business Hub -III, Phase- I, Baner have?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner has 2 buildings filed: PH -1 Ground To 15th Floor with 17 floors and 215 units; PH -II-16th to 22nd Floor with 7 floors and 63 units.

How much parking does Solitaire Business Hub -III, Phase- I, Baner have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 387 covered car parking spaces for Solitaire Business Hub -III, Phase- I, Baner.

How big is the land of Solitaire Business Hub -III, Phase- I, Baner?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner stands on 18,145 sq m of land (about 4.5 acres), with 20,236 sq m of sanctioned built-up area and 919 sq m of recreational open space.

What is the track record of Solitaire Business Hub -III, Phase- I, Baner's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Classic Promoters And Builders (a group of 8 linked companies) has 30 projects on MahaRERA since 2017, this one included. Of the 30 GharKundli has checked: 10 finished, 2 within the promised date and 8 needed more time (typically 6 months); 20 still being built, 12 past the promised date (typically 22 months late). 230 complaints on MahaRERA across 17 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Solitaire Business Hub -III, Phase- I, Baner?

Google Maps has reviews of Solitaire Business Hub -III, Phase- I, Baner written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 55 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Solitaire Business Hub -III, Phase- I, Baner?

Solitaire Business Hub -III, Phase- I, Baner by Baner Land Developers LLP is in Baner, Pune, pincode 411045 (near Balewadi, Pashan, kothrud), Maharashtra, and is registered on MahaRERA as P52100022782, per GharKundli's check of MahaRERA records. Its land is filed as S No 9/3 9/4 9/5 9/6 9/7. GharKundli lists all 713 MahaRERA projects in Baner (411045).

How many flats are in Solitaire Business Hub -III, Phase- I, Baner, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner has 0 homes in 4 towers registered on MahaRERA, and 99% of them are sold or booked.

When was Solitaire Business Hub -III, Phase- I, Baner registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Solitaire Business Hub -III, Phase- I, Baner was registered on MahaRERA on 17 October 2019. GharKundli did not find a title report on the land on file there.

Does Solitaire Business Hub -III, Phase- I, Baner have any legal issues or court cases?

2 court cases are listed for Solitaire Business Hub -III, Phase- I, Baner on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Solitaire Business Hub -III, Phase- I, Baner?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Baner Land Developers LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in Baner (411045)

All 713 projects in Baner (411045) →

Other projects by Baner Land Developers LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.