Vijayraj Residency
by Vijayraj Realtors · Vile Parle east, MumbaiAlso near Vile Parle West, Andheri East, Vileparle east
Possession date of Vijayraj Residency: 30 April 2028, moved from 31 July 2024 (41 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800004495, and currently active. Its completion date has moved from July 2024 to April 2028: 41 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 19 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vijayraj Residency?
GharKundli’s full report on Vijayraj Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 19 complaints, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004495
- Status
- Registered and active
- Builder
- Vijayraj Realtors
- Location
- Vile Parle east, Mumbai · 400057
- Project type
- Mixed
- Registered on
- 9 Aug 2017
- Completion date at registration
- July 2024
- Latest completion date
- April 2028
- Delay so far
- 41 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 167
- Sold or booked
- 49%
- Towers
- 1
- Complaints on MahaRERA
- 19
- Court cases listed
- 0
- Appeals at the tribunal
- 27
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Vijayraj Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Composite Building | 100% | 100% | 61% | 45% |
Commencement certificate (CC), as filed on MahaRERA
- Composite Building: covers CC Issued up-to 7 Floors
Latest CC order on MahaRERA: dated 28/05/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vijayraj Residency every month.
Vijayraj Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 264 – 498 | 116 |
| 2 BHK | 605 – 704 | 28 |
| 3 BHK | 978 – 1,034 | 14 |
| Multi Purpose Room | 207 – 494 | 9 |
| Shops | 161 – 1,176 | 3 |
- Buildings: Composite Building (10 floors, 170 units)
- Car parking: 119 covered
- Land: 2,139 sq m (about 0.5 acres) · sanctioned built-up 8,322 sq m · recreational space 172 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vijayraj Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vijayraj Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vijayraj Residency
What is the possession date of Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vijayraj Residency in Vile Parle east, Mumbai is 30 April 2028 — 41 months later than 31 July 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Vijayraj Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vijayraj Residency's builder has filed on MahaRERA, the official one, is 30 April 2028, already 41 months later than the 31 July 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vijayraj Residency in Vile Parle east, Mumbai is P51800004495.
Is Vijayraj Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency is registered as P51800004495 and its status is "Registered and active".
What is the construction status of Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Composite Building is 100% done and internal work 61%. GharKundli's full report compares construction progress with the deadline.
Does Vijayraj Residency have complaints on MahaRERA?
19 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Vijayraj Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency is registered on MahaRERA as P51800004495, its completion date has moved 41 months since registration and 19 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vijayraj Residency's possession date changes?
The latest dates are on Vijayraj Residency's MahaRERA page (P51800004495). GharKundli's Kundli Watch sends a free WhatsApp update on Vijayraj Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vijayraj Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency has one building filed: Composite Building with 10 floors and 170 units.
What are the flat sizes (carpet area) in Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vijayraj Residency: 1 BHK: 264 to 498 sq ft carpet (116 homes); 2 BHK: 605 to 704 sq ft carpet (28 homes); 3 BHK: 978 to 1034 sq ft carpet (14 homes); Multi Purpose Room: 207 to 494 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Vijayraj Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 119 covered car parking spaces for Vijayraj Residency.
How big is the land of Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency stands on 2,139 sq m of land (about 0.5 acres), with 8,322 sq m of sanctioned built-up area and 172 sq m of recreational open space.
Where can I read reviews of Vijayraj Residency?
Google Maps has reviews of Vijayraj Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 19 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vijayraj Residency?
Vijayraj Residency by Vijayraj Realtors is in Vile Parle east, Mumbai (pincode 400057), near Vile Parle West, Andheri East, Vileparle east, Maharashtra, and is registered on MahaRERA as P51800004495, per GharKundli's check of MahaRERA records.
How many homes are in Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency has 167 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.
When was Vijayraj Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vijayraj Residency was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Vijayraj Residency?
No court cases are listed for Vijayraj Residency on MahaRERA, and 27 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Vijayraj Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Vijayraj Realtors, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vijayraj Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400057
- Shubhada Co-operative Housing Society Ltd.
- Neumec godawari
- PEARL HERITAGE
- ZODIAC ANJANESHWAR
- ARHAM HERITAGE
- PARIMAL
- Munisuvrat Chhaya
- Pruthvi Symphony
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.