Emerald Bay Building 3

by Pune Projects LLP · Mundhva AV, Pune 411036

What’s in the report? →

Possession date of Emerald Bay Building 3 (MahaRERA P52100026022): 30 April 2027, moved from 30 June 2025 (18 months later). It has 84 homes, 98% sold or booked. 19 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100026022, and currently active. Its completion date has moved from June 2025 to April 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project.

Source: MahaRERA website — records for P52100026022, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Emerald Bay Building 3?

5 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Emerald Bay Building 3 has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52100024298)

    Reason the builder gave MahaRERA:
    “We state that the registration validity of the said project is going to expire on June 30, 2025, and pursuant to the same we have filed an application seeking further extension till Dec 2026 as provided under Section 7 of the act. The delay…” Read the full reason“We state that the registration validity of the said project is going to expire on June 30, 2025, and pursuant to the same we have filed an application seeking further extension till Dec 2026 as provided under Section 7 of the act. The delay to achieve completion of the project is neither wilful or deliberate but due to various factors such as fallout of COIVD Pandemic, labour exodus, issues with project execution contractors and certain mitigation circumstances. We also wish to state and submit wish to state that the building is standalone building in which we have completed more than 48% o…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Emerald Bay Building 3’s extension records on MahaRERA (P52100026022), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Emerald Bay Building 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 19 complaints and 5 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100026022
Status
Registered and active
Builder
Pune Projects LLP
Location
Mundhva AV, Pune · 411036
Project type
Residential / Group Housing
Registered on
9 Aug 2020
Completion date at registration
June 2025
Latest completion date
April 2027
Delay so far
18 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
84
Sold or booked
98%
Towers
1
Complaints on MahaRERA
19
Court cases listed
5
Appeals at the tribunal
1
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of Emerald Bay Building 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building 3100%64%17%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building 3: covers 25 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Emerald Bay Building 3 every 1–2 months.

Emerald Bay Building 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building 3 (25 floors, 84 units)
  • Land: 735 sq m (about 0.2 acres) · sanctioned built-up 9,605 sq m
  • Boundaries filed include: Mula-Mutha River
  • Land, as filed: Sy No 9 to 14
  • Map: Get directions

The builder’s record and reviews

Puravankara (a group of 5 linked companies) has 38 projects on MahaRERA since 2017, this one included. Of the 38 GharKundli has checked: 1 finished, all within the promised date; 37 still being built, 8 past the promised date (typically 12 months late). 241 complaints on MahaRERA across 13 projects.

Read Google reviews of Emerald Bay Building 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Emerald Bay Building 3: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Emerald Bay Building 3

What is the possession date of Emerald Bay Building 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Emerald Bay Building 3 in Mundhva AV, Pune is 30 April 2027 — 18 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Emerald Bay Building 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Emerald Bay Building 3's builder has filed on MahaRERA, the official one, is 30 April 2027, already 18 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Emerald Bay Building 3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We state that the registration validity of the said project is going to expire on June 30, 2025, and pursuant to the same we have filed an application seeking further extension till Dec 2026 as provided under Section 7 of the act. The delay to achieve completion of the project is neither wilful or deliberate but due to various factors such as fallout of COIVD Pandemic, labour exodus, issues with project execution contractors and certain mitigation circumstances. We also wish to state and submit wish to state that the building is standalone building in which we have completed more than 48% o…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Emerald Bay Building 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Emerald Bay Building 3 in Mundhva AV, Pune is P52100026022.

Is Emerald Bay Building 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 is registered as P52100026022 and its status is "Registered and active".

What is the current construction status of Emerald Bay Building 3? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building 3 is 64% done and internal work 17%. GharKundli's full report compares construction progress with the deadline.

Does Emerald Bay Building 3 have complaints on MahaRERA?

19 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

19 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is Emerald Bay Building 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 is registered on MahaRERA as P52100026022, its completion date has moved 18 months since registration and 19 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Emerald Bay Building 3?

Emerald Bay Building 3 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Emerald Bay Building 3?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Emerald Bay Building 3: gharkundli.com/tools/property-cost-calculator

Has Emerald Bay Building 3 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Emerald Bay Building 3 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Emerald Bay Building 3 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Emerald Bay Building 3 have other wings or phases?

Yes. MahaRERA lists 5 other registrations of the same project, each with its own possession date: Emerald Bay Building 2 (P52100026016, possession 30 Apr 2027); Emerald Bay Building 10 (P52100026110, possession 30 Apr 2030); Emerald Bay Building 11 (P52100026020, possession 30 Apr 2027); Emerald Bay Building 12 (P52100026132, possession 30 Jun 2031); Emerald Bay Building 13 (P52100026099, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Emerald Bay Building 3's possession date changes?

The latest dates are on Emerald Bay Building 3's MahaRERA page (P52100026022). GharKundli's Kundli Watch sends a free WhatsApp update on Emerald Bay Building 3 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Emerald Bay Building 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 has one building filed: Building 3 with 25 floors and 84 units.

How big is the land of Emerald Bay Building 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 stands on 735 sq m of land (about 0.2 acres), with 9,605 sq m of sanctioned built-up area.

What is the track record of Emerald Bay Building 3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Puravankara (a group of 5 linked companies) has 38 projects on MahaRERA since 2017, this one included. Of the 38 GharKundli has checked: 1 finished, all within the promised date; 37 still being built, 8 past the promised date (typically 12 months late). 241 complaints on MahaRERA across 13 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Emerald Bay Building 3?

Google Maps has reviews of Emerald Bay Building 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 19 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Emerald Bay Building 3?

Emerald Bay Building 3 by Pune Projects LLP is in Mundhva AV, Pune, pincode 411036, Maharashtra, and is registered on MahaRERA as P52100026022, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mula-Mutha River. Its land is filed as Sy No 9 to 14. GharKundli lists all 241 MahaRERA projects in Mundhwa (411036).

How many flats are in Emerald Bay Building 3, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 has 84 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.

When was Emerald Bay Building 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Emerald Bay Building 3 was registered on MahaRERA on 9 August 2020. GharKundli did not find a title report on the land on file there.

Does Emerald Bay Building 3 have any legal issues or court cases?

5 court cases are listed for Emerald Bay Building 3 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Emerald Bay Building 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pune Projects LLP, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →