Skip to content
GharKundli

CRD Gardenia Apartments 2

by Dr Chandrashekhar Raghunath Dound · Palghar

Possession: CRD Gardenia Apartments 2 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000010008. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about CRD Gardenia Apartments 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CRD Gardenia Apartments 2 has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000001350)

    Reason the builder gave MahaRERA:
    “As per the revision in layout and revised approval, the height of the apartment is increased from Ground + 4 to Ground + 7 stories and the built up area of the apartment is also increased. We are registering the additional area as different…” Read the full reason“As per the revision in layout and revised approval, the height of the apartment is increased from Ground + 4 to Ground + 7 stories and the built up area of the apartment is also increased. We are registering the additional area as different project. But due to this revision; the time required for construction of this apartment will increase. Therefore we require extended date of completion to which all our existing customers have given consent.”
  3. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT99000009831)

    Reason the builder gave MahaRERA:
    “Due to the COVID 19 pandemic , it was difficult to continue to the construction work at the same speed as prior to March 2020. The factories & workers of vendors supplying lift, windows and doors were affected and were not able to deliver m…” Read the full reason“Due to the COVID 19 pandemic , it was difficult to continue to the construction work at the same speed as prior to March 2020. The factories & workers of vendors supplying lift, windows and doors were affected and were not able to deliver material in time. Therefore we are requesting to extend the completion period of the project by atleast nine month.”
  4. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT99000012626)

    Reason the builder gave MahaRERA: “The construction work of the building is complete and we have applied for occupation certificate on 29/06/2022. Since the occupation certificate is still not issued by the concerned authorities, we need extension for the project.”

Source: CRD Gardenia Apartments 2’s extension records on MahaRERA (P99000010008), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CRD Gardenia Apartments 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P99000010008
Status
Completed
Builder
Dr Chandrashekhar Raghunath Dound
Location
Palghar · 401404
Project type
Residential / Group Housing
Registered on
23 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2022
Delay so far
36 months
Homes
38
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
12

Construction progress of CRD Gardenia Apartments 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%100%50%0%
Wing B100%100%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CRD Gardenia Apartments 2 every month.

CRD Gardenia Apartments 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wing A (5 floors) · Wing B (5 floors)
  • Land: 1,574 sq m (about 0.4 acres) · sanctioned built-up 1,949 sq m
  • Boundaries filed include: Manor Velgaon Road

The builder’s record and reviews

CRD Blue Ocean (a group of 2 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 34 months); 3 still being built, 2 past the promised date (typically 24 months late). No complaints on MahaRERA.

Read Google reviews of CRD Gardenia Apartments 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CRD Gardenia Apartments 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CRD Gardenia Apartments 2

What is the possession date of CRD Gardenia Apartments 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CRD Gardenia Apartments 2 in Palghar is 31 December 2022 — 36 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for CRD Gardenia Apartments 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CRD Gardenia Apartments 2's builder has filed on MahaRERA, the official one, is 31 December 2022, already 36 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CRD Gardenia Apartments 2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "As per the revision in layout and revised approval, the height of the apartment is increased from Ground + 4 to Ground + 7 stories and the built up area of the apartment is also increased. We are registering the additional area as different project. But due to this revision; the time required for construction of this apartment will increase. Therefore we require extended date of completion to which all our existing customers have given consent."; to 31 March 2022, giving the reason "Due to the COVID 19 pandemic , it was difficult to continue to the construction work at the same speed as prior to March 2020. The factories & workers of vendors supplying lift, windows and doors were affected and were not able to deliver material in time. Therefore we are requesting to extend the completion period of the project by atleast nine month."; to 31 December 2022, giving the reason "The construction work of the building is complete and we have applied for occupation certificate on 29/06/2022. Since the occupation certificate is still not issued by the concerned authorities, we need extension for the project.".

What is the RERA number of CRD Gardenia Apartments 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CRD Gardenia Apartments 2 in Palghar is P99000010008.

Is CRD Gardenia Apartments 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2 is registered as P99000010008 and its status is "Completed".

What is the construction status of CRD Gardenia Apartments 2?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does CRD Gardenia Apartments 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is CRD Gardenia Apartments 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2 is registered on MahaRERA as P99000010008, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does CRD Gardenia Apartments 2 have other wings or phases?

Yes. MahaRERA lists 11 other registrations of the same project, each with its own possession date: CRD Gardenia Apartments 1 (P99000009462); CRD Gardenia Apartments 2 - Phase II (P99000019691, possession 31 Dec 2022); CRD Gardenia Apartments 2 - Phase III (P99000049393, possession 31 Dec 2023); CRD Gardenia Apartments 3 (P99000007757); CRD Gardenia Apartments 4 (P99000009579, possession 30 Apr 2031); CRD Gardenia Apartments 4 - Phase II (P99000019668, possession 30 Apr 2031); and 5 more. Check that your agreement names the registration of your own wing.

How can I get updates if CRD Gardenia Apartments 2's possession date changes?

The latest dates are on CRD Gardenia Apartments 2's MahaRERA page (P99000010008). GharKundli's Kundli Watch sends a free WhatsApp update on CRD Gardenia Apartments 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CRD Gardenia Apartments 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2 has 2 buildings filed: Wing A with 5 floors; Wing B with 5 floors.

How big is the land of CRD Gardenia Apartments 2?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2 stands on 1,574 sq m of land (about 0.4 acres), with 1,949 sq m of sanctioned built-up area.

What is the track record of CRD Gardenia Apartments 2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Blue Ocean (a group of 2 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 34 months); 3 still being built, 2 past the promised date (typically 24 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of CRD Gardenia Apartments 2?

Google Maps has reviews of CRD Gardenia Apartments 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CRD Gardenia Apartments 2?

CRD Gardenia Apartments 2 by Dr Chandrashekhar Raghunath Dound is in Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000010008, per GharKundli's check of MahaRERA records. Its boundaries filed there include Manor Velgaon Road.

How many homes are in CRD Gardenia Apartments 2?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2 has 38 homes in 2 towers registered on MahaRERA.

When was CRD Gardenia Apartments 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), CRD Gardenia Apartments 2 was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on CRD Gardenia Apartments 2?

No court cases are listed for CRD Gardenia Apartments 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of CRD Gardenia Apartments 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Dr Chandrashekhar Raghunath Dound, which has 12 other projects registered on MahaRERA.

Other projects in pincode 401404

All 421 projects in Palghar (401404) →

Other projects by Dr Chandrashekhar Raghunath Dound

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.