CRD Gardenia Apartments 4 - Phase II
by Dr Chandrashekhar Raghunath Dound · Velgaon, Palghar
Possession date of CRD Gardenia Apartments 4 - Phase II: 30 April 2031, moved from 30 December 2023 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000019668, and currently active. Its completion date has moved from December 2023 to April 2031: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about CRD Gardenia Apartments 4 - Phase II?
How the possession date of CRD Gardenia Apartments 4 - Phase II has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT99000013656)
Reason the builder gave MahaRERA:
“Total four buildings are proposed on a single parcel of land bearing Gat no. 48/1A/1B, Velgaon, Palghar. Out of these four buildings, three buildings namely CRD Gardenia Apt 1, 2 and 6 are completed and have received OC. Now as per the unif…” Read the full reason
“Total four buildings are proposed on a single parcel of land bearing Gat no. 48/1A/1B, Velgaon, Palghar. Out of these four buildings, three buildings namely CRD Gardenia Apt 1, 2 and 6 are completed and have received OC. Now as per the unified DCPR , the plans are revised and approved on 10/11/2022. As per the new approval, Plans of Apt no. 4 are completely changed. The construction of this Apt 4 is not started yet and there are no sales in the building. Now wing B of Building No 4 and podium which is building no 3 is proposed to be part of this registered project “CRD Gardenia Apartments 4…”31 December 2030
Extended at the builder's request (MahaRERA application EA19052621016)
Reason the builder gave MahaRERA:
“The current facts of the case are being explained hereunder. The reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. It is evident from Table C of Form 3 and sold booked inven…” Read the full reason
“The current facts of the case are being explained hereunder. The reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. It is evident from Table C of Form 3 and sold booked inventory as on 31/03/2025 that there are no units sold in the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 31/12/2026. Due to no sale in the project, the applicant landed into the financial difficulties which spiraled the event of stoppage of co…”30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: CRD Gardenia Apartments 4 - Phase II’s extension records on MahaRERA (P99000019668), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CRD Gardenia Apartments 4 - Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- CRD Gardenia Apartments 1P99000009462
- CRD Gardenia Apartments 2P99000010008
- CRD Gardenia Apartments 2 - Phase IIP99000019691
- CRD Gardenia Apartments 2 - Phase IIIP99000049393 · possession 31 Dec 2023
- CRD Gardenia Apartments 3P99000007757
- CRD Gardenia Apartments 4P99000009579 · possession 30 Apr 2031
- CRD Gardenia Apartments 5P99000008719
- CRD Gardenia Apartments 6P99000009989
- CRD Gardenia Apartments 6 - Phase IIP99000019665
- CRD Gardenia Apartments 6 - Phase IIIP99000049411 · possession 31 Dec 2023
- CRD Gardenia Apartments 7P99000009987
- MahaRERA registration
- P99000019668
- Status
- Registered and active
- Builder
- Dr Chandrashekhar Raghunath Dound
- Location
- Velgaon, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 20 Feb 2019
- Completion date at registration
- December 2023
- Latest completion date
- April 2031
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 47
- Sold or booked
- 6%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 12
Construction progress of CRD Gardenia Apartments 4 - Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 0% | 0% | 0% | 0% |
| Wing B | 0% | 0% | 0% | 0% |
| Podium | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing B: covers plinth
- Podium: covers plinth
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CRD Gardenia Apartments 4 - Phase II every month.
CRD Gardenia Apartments 4 - Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing B (8 floors, 47 units) · Podium (1 floors, 5 units)
- Car parking: 37 open
- Land: 1,868 sq m (about 0.5 acres) · sanctioned built-up 3,475 sq m
- Boundaries filed include: Manor Velgaon Road
The builder’s record and reviews
CRD Blue Ocean (a group of 2 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 2 past the promised date (typically 24 months late). No complaints on MahaRERA.
Read Google reviews of CRD Gardenia Apartments 4 - Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CRD Gardenia Apartments 4 - Phase II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CRD Gardenia Apartments 4 - Phase II
What is the possession date of CRD Gardenia Apartments 4 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CRD Gardenia Apartments 4 - Phase II in Velgaon, Palghar is 30 April 2031 — 84 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for CRD Gardenia Apartments 4 - Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CRD Gardenia Apartments 4 - Phase II's builder has filed on MahaRERA, the official one, is 30 April 2031, already 84 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CRD Gardenia Apartments 4 - Phase II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2024, giving the reason "Total four buildings are proposed on a single parcel of land bearing Gat no. 48/1A/1B, Velgaon, Palghar. Out of these four buildings, three buildings namely CRD Gardenia Apt 1, 2 and 6 are completed and have received OC. Now as per the unified DCPR , the plans are revised and approved on 10/11/2022. As per the new approval, Plans of Apt no. 4 are completely changed. The construction of this Apt 4 is not started yet and there are no sales in the building. Now wing B of Building No 4 and podium which is building no 3 is proposed to be part of this registered project “CRD Gardenia Apartments 4…"; to 31 December 2030, giving the reason "The current facts of the case are being explained hereunder. The reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. It is evident from Table C of Form 3 and sold booked inventory as on 31/03/2025 that there are no units sold in the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 31/12/2026. Due to no sale in the project, the applicant landed into the financial difficulties which spiraled the event of stoppage of co…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of CRD Gardenia Apartments 4 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CRD Gardenia Apartments 4 - Phase II in Velgaon, Palghar is P99000019668.
Is CRD Gardenia Apartments 4 - Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II is registered as P99000019668 and its status is "Registered and active".
What is the construction status of CRD Gardenia Apartments 4 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does CRD Gardenia Apartments 4 - Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is CRD Gardenia Apartments 4 - Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II is registered on MahaRERA as P99000019668, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does CRD Gardenia Apartments 4 - Phase II have other wings or phases?
Yes. MahaRERA lists 11 other registrations of the same project, each with its own possession date: CRD Gardenia Apartments 1 (P99000009462); CRD Gardenia Apartments 2 (P99000010008); CRD Gardenia Apartments 2 - Phase II (P99000019691); CRD Gardenia Apartments 2 - Phase III (P99000049393, possession 31 Dec 2023); CRD Gardenia Apartments 3 (P99000007757); CRD Gardenia Apartments 4 (P99000009579, possession 30 Apr 2031); and 5 more. Check that your agreement names the registration of your own wing.
How can I get updates if CRD Gardenia Apartments 4 - Phase II's possession date changes?
The latest dates are on CRD Gardenia Apartments 4 - Phase II's MahaRERA page (P99000019668). GharKundli's Kundli Watch sends a free WhatsApp update on CRD Gardenia Apartments 4 - Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CRD Gardenia Apartments 4 - Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II has 2 buildings filed: Wing B with 8 floors and 47 units; Podium with 1 floors and 5 units.
How much parking does CRD Gardenia Apartments 4 - Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 37 open car parking spaces for CRD Gardenia Apartments 4 - Phase II.
How big is the land of CRD Gardenia Apartments 4 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II stands on 1,868 sq m of land (about 0.5 acres), with 3,475 sq m of sanctioned built-up area.
What is the track record of CRD Gardenia Apartments 4 - Phase II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Blue Ocean (a group of 2 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 2 past the promised date (typically 24 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CRD Gardenia Apartments 4 - Phase II?
Google Maps has reviews of CRD Gardenia Apartments 4 - Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CRD Gardenia Apartments 4 - Phase II?
CRD Gardenia Apartments 4 - Phase II by Dr Chandrashekhar Raghunath Dound is in Velgaon, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000019668, per GharKundli's check of MahaRERA records. Its boundaries filed there include Manor Velgaon Road.
How many homes are in CRD Gardenia Apartments 4 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II has 47 homes in 3 towers registered on MahaRERA, and 6% of them are sold or booked.
When was CRD Gardenia Apartments 4 - Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), CRD Gardenia Apartments 4 - Phase II was registered on MahaRERA on 20 February 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on CRD Gardenia Apartments 4 - Phase II?
No court cases are listed for CRD Gardenia Apartments 4 - Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of CRD Gardenia Apartments 4 - Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Dr Chandrashekhar Raghunath Dound, which has 12 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CRD Gardenia Apartments 4 - Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Palghar →
Other projects in Palghar
- CRD Gardenia Apartments 2 - Phase III
- CRD Gardenia Apartments 2 - Phase II
- Sunshine Complex
- Elite Residency
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
Other projects by Dr Chandrashekhar Raghunath Dound
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.