by UNIQUE AMS SPACES LLP · Kiwale, PuneAlso near Dehu Road Cantt

Possession date of FLOW KIWALE: 31 December 2026, moved from 31 March 2026 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100051788, and currently active.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about FLOW KIWALE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of FLOW KIWALE has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA27082622406)

    Reason the builder gave MahaRERA: “Occupancy Certificate received on 27/12/2024. Need to complete the compliances for RERA Completion. So extension required.”

Source: FLOW KIWALE’s extension records on MahaRERA (P52100051788), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on FLOW KIWALE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100051788
Status
Registered and active
Builder
UNIQUE AMS SPACES LLP
Location
Kiwale, Pune · 412101
Project type
Commercial
Registered on
3 Jul 2023
Completion date at registration
March 2026
Latest completion date
December 2026
Delay so far
9 months
Homes
0
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of FLOW KIWALE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Flow Kiwale0%100%80%20%

Commencement certificate (CC), as filed on MahaRERA

  • Flow Kiwale: covers 1 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on FLOW KIWALE every month.

FLOW KIWALE: buildings, flats and land, as filed on MahaRERA

  • Buildings: Flow Kiwale (2 floors, 25 units)
  • Land: 2,619 sq m (about 0.6 acres) · sanctioned built-up 1,754 sq m · recreational space 3,224 sq m

The builder’s record and reviews

Unique AMS Spaces (a group of 3 linked companies) has 10 projects on MahaRERA since 2023, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 1 project.

Read Google reviews of FLOW KIWALE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

FLOW KIWALE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about FLOW KIWALE

What is the possession date of FLOW KIWALE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for FLOW KIWALE in Kiwale, Pune is 31 December 2026 — 9 months later than 31 March 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for FLOW KIWALE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date FLOW KIWALE's builder has filed on MahaRERA, the official one, is 31 December 2026, already 9 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of FLOW KIWALE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Occupancy Certificate received on 27/12/2024. Need to complete the compliances for RERA Completion. So extension required.".

What is the RERA number of FLOW KIWALE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of FLOW KIWALE in Kiwale, Pune is P52100051788.

Is FLOW KIWALE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE is registered as P52100051788 and its status is "Registered and active".

What is the construction status of FLOW KIWALE?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Flow Kiwale is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does FLOW KIWALE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is FLOW KIWALE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE is registered on MahaRERA as P52100051788, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if FLOW KIWALE's possession date changes?

The latest dates are on FLOW KIWALE's MahaRERA page (P52100051788). GharKundli's Kundli Watch sends a free WhatsApp update on FLOW KIWALE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does FLOW KIWALE have?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE has one building filed: Flow Kiwale with 2 floors and 25 units.

How big is the land of FLOW KIWALE?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE stands on 2,619 sq m of land (about 0.6 acres), with 1,754 sq m of sanctioned built-up area and 3,224 sq m of recreational open space.

What is the track record of FLOW KIWALE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Unique AMS Spaces (a group of 3 linked companies) has 10 projects on MahaRERA since 2023, this one included. Of the 6 GharKundli has checked: 1 finished, all within the promised date; 5 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of FLOW KIWALE?

Google Maps has reviews of FLOW KIWALE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is FLOW KIWALE?

FLOW KIWALE by UNIQUE AMS SPACES LLP is in Kiwale, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100051788, per GharKundli's check of MahaRERA records.

How many homes are in FLOW KIWALE?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE has 0 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was FLOW KIWALE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), FLOW KIWALE was registered on MahaRERA on 3 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on FLOW KIWALE?

No court cases are listed for FLOW KIWALE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of FLOW KIWALE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is UNIQUE AMS SPACES LLP, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in pincode 412101

All 408 projects in Ravet (412101) →

Other projects by UNIQUE AMS SPACES LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.