Itrend Futura
by Highpoint Landmark LLP · Mahalunge, Pune
Possession date of Itrend Futura: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100050688, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Itrend Futura?
How the possession date of Itrend Futura has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Itrend Futura’s extension records on MahaRERA (P52100050688), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Itrend Futura
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100050688
- Status
- Registered and active
- Builder
- Highpoint Landmark LLP
- Location
- Mahalunge, Pune · 411045
- Project type
- Others
- Registered on
- 28 Apr 2023
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 1,330
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Itrend Futura, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building A | 100% | 4% | 0% | 0% |
| Building B | 100% | 100% | 51% | 0% |
| Bulding C | 100% | 100% | 48% | 0% |
| Building D | 100% | 8% | 0% | 0% |
| Building E | 100% | 100% | 65% | 0% |
| Building F | 100% | 35% | 4% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Itrend Futura every month.
Itrend Futura: buildings, flats and land, as filed on MahaRERA
- Buildings: Building A (26 floors) · Building B (28 floors) · Bulding C (29 floors) · Building D (26 floors) · Building E (26 floors) · Building F (26 floors)
- Land: 24,281 sq m (about 6.0 acres) · sanctioned built-up 1,24,600 sq m · recreational space 2,428 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Itrend Futura →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Itrend Futura: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Itrend Futura
What is the possession date of Itrend Futura?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Itrend Futura in Mahalunge, Pune is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Itrend Futura?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Itrend Futura's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Itrend Futura?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Itrend Futura in Mahalunge, Pune is P52100050688.
Is Itrend Futura registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura is registered as P52100050688 and its status is "Registered and active".
What is the construction status of Itrend Futura?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 4% to 100% across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does Itrend Futura have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Itrend Futura safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura is registered on MahaRERA as P52100050688, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Itrend Futura's possession date changes?
The latest dates are on Itrend Futura's MahaRERA page (P52100050688). GharKundli's Kundli Watch sends a free WhatsApp update on Itrend Futura every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Itrend Futura have?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura has 6 buildings filed: Building A with 26 floors; Building B with 28 floors; Bulding C with 29 floors; Building D with 26 floors; Building E with 26 floors; Building F with 26 floors.
How big is the land of Itrend Futura?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura stands on 24,281 sq m of land (about 6.0 acres), with 1,24,600 sq m of sanctioned built-up area and 2,428 sq m of recreational open space.
Where can I read reviews of Itrend Futura?
Google Maps has reviews of Itrend Futura written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Itrend Futura?
Itrend Futura by Highpoint Landmark LLP is in Mahalunge, Pune (pincode 411045), Maharashtra, and is registered on MahaRERA as P52100050688, per GharKundli's check of MahaRERA records.
How many homes are in Itrend Futura?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura has 1,330 homes in 6 towers registered on MahaRERA.
When was Itrend Futura registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Itrend Futura was registered on MahaRERA on 28 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Itrend Futura?
1 court case is listed for Itrend Futura on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Itrend Futura?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Highpoint Landmark LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Itrend Futura
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Pune →
Other projects in Mahalunge
- SKYLINES
- Raheja Vistas - T1 & T2
- Dahlia
- SARA EKADANT
- Godrej Hill Retreat 2
- Godrej Meadows- Phase 2
- Godrej Green Vistas
- Godrej Green Cove
Other projects by Highpoint Landmark LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.