SRK GOLD
by M/S SRK CONSTRUCTIONS · Balewadi, PuneAlso near Baner, N.I.A
Possession date of SRK GOLD: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100050855, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SRK GOLD?
How the possession date of SRK GOLD has moved
31 March 2028
Completion date given when the project was registered
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SRK GOLD’s extension records on MahaRERA (P52100050855), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SRK GOLD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100050855
- Status
- Registered and active
- Builder
- M/S SRK CONSTRUCTIONS
- Location
- Balewadi, Pune · 411045
- Project type
- Others
- Registered on
- 9 May 2023
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 29%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SRK GOLD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SRK GOLD | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- SRK GOLD: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SRK GOLD every month.
SRK GOLD: buildings, flats and land, as filed on MahaRERA
- Buildings: SRK GOLD (7 floors, 14 units)
- Car parking: 14 covered
- Land: 450 sq m (about 0.1 acres) · sanctioned built-up 1,571 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SRK GOLD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SRK GOLD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SRK GOLD
What is the possession date of SRK GOLD?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SRK GOLD in Balewadi, Pune is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SRK GOLD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SRK GOLD's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SRK GOLD?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SRK GOLD in Balewadi, Pune is P52100050855.
Is SRK GOLD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD is registered as P52100050855 and its status is "Registered and active".
What is the construction status of SRK GOLD?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SRK GOLD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SRK GOLD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SRK GOLD safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD is registered on MahaRERA as P52100050855, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SRK GOLD's possession date changes?
The latest dates are on SRK GOLD's MahaRERA page (P52100050855). GharKundli's Kundli Watch sends a free WhatsApp update on SRK GOLD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SRK GOLD have?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD has one building filed: SRK GOLD with 7 floors and 14 units.
How much parking does SRK GOLD have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 14 covered car parking spaces for SRK GOLD.
How big is the land of SRK GOLD?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD stands on 450 sq m of land (about 0.1 acres), with 1,571 sq m of sanctioned built-up area.
Where can I read reviews of SRK GOLD?
Google Maps has reviews of SRK GOLD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SRK GOLD?
SRK GOLD by M/S SRK CONSTRUCTIONS is in Balewadi, Pune (pincode 411045), near Baner, N.I.A, Maharashtra, and is registered on MahaRERA as P52100050855, per GharKundli's check of MahaRERA records.
How many homes are in SRK GOLD?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD has 0 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.
When was SRK GOLD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SRK GOLD was registered on MahaRERA on 9 May 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SRK GOLD?
No court cases are listed for SRK GOLD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SRK GOLD?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/S SRK CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of SRK GOLD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Balewadi
- AARAMBH
- The Midas Residences Phase 5
- The Midas Residences Phase 6
- PLATINUM MARVELLE
- VERTICA PHASE 2
- VERTICA PHASE 3
- DREAM GLORIOUS
- 27WEST
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.