Skip to content
GharKundli

LINI HOMES

by VIJAY CONSTRUCTION NEXT · Chikhali, PuneAlso near Rupeenagar, Chinchwad East, Akurdi

Possession date of LINI HOMES: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100053001, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about LINI HOMES?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LINI HOMES has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: LINI HOMES’s extension records on MahaRERA (P52100053001), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LINI HOMES

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100053001
Status
Registered and active
Builder
VIJAY CONSTRUCTION NEXT
Location
Chikhali, Pune · 411062
Project type
Residential / Group Housing
Registered on
10 Oct 2023
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
133
Sold or booked
30%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of LINI HOMES, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A BUILDING100%40%10%0%
B BUILDING100%100%10%0%

Commencement certificate (CC), as filed on MahaRERA

  • A BUILDING: covers 23 floors
  • B BUILDING: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LINI HOMES every month.

LINI HOMES: buildings, flats and land, as filed on MahaRERA

  • Buildings: A BUILDING (11 floors, 132 units) · B BUILDING (7 floors, 11 units)
  • Land: 2,931 sq m (about 0.7 acres) · sanctioned built-up 5,266 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of LINI HOMES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LINI HOMES: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LINI HOMES

What is the possession date of LINI HOMES?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LINI HOMES in Chikhali, Pune is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for LINI HOMES?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LINI HOMES's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of LINI HOMES?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of LINI HOMES in Chikhali, Pune is P52100053001.

Is LINI HOMES registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES is registered as P52100053001 and its status is "Registered and active".

What is the construction status of LINI HOMES?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 40% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does LINI HOMES have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is LINI HOMES safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES is registered on MahaRERA as P52100053001, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LINI HOMES's possession date changes?

The latest dates are on LINI HOMES's MahaRERA page (P52100053001). GharKundli's Kundli Watch sends a free WhatsApp update on LINI HOMES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LINI HOMES have?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES has 2 buildings filed: A BUILDING with 11 floors and 132 units; B BUILDING with 7 floors and 11 units.

How big is the land of LINI HOMES?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES stands on 2,931 sq m of land (about 0.7 acres), with 5,266 sq m of sanctioned built-up area.

Where can I read reviews of LINI HOMES?

Google Maps has reviews of LINI HOMES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LINI HOMES?

LINI HOMES by VIJAY CONSTRUCTION NEXT is in Chikhali, Pune (pincode 411062), near Rupeenagar, Chinchwad East, Akurdi, Maharashtra, and is registered on MahaRERA as P52100053001, per GharKundli's check of MahaRERA records.

How many homes are in LINI HOMES?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES has 133 homes in 2 towers registered on MahaRERA, and 30% of them are sold or booked.

When was LINI HOMES registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LINI HOMES was registered on MahaRERA on 10 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on LINI HOMES?

No court cases are listed for LINI HOMES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of LINI HOMES?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIJAY CONSTRUCTION NEXT, which has 1 other project registered on MahaRERA.

All projects with possession due in 2030 in Pune →

Other projects in pincode 411062

All 109 projects in Chikhali (411062) →

Other projects by VIJAY CONSTRUCTION NEXT

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.