Shree Neha CHSL
by HARI OM SAI GRIHANRMITI PVT LTD · Mulund East, Mumbai 400081Also near Mulund West
What’s in the report? →Possession date of Shree Neha CHSL (MahaRERA P51800019288): 30 September 2025, moved from 30 May 2022 (40 months later), and it has already passed. It has 44 homes (1 BHK and 2 BHK, 393–537 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800019288. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800019288, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (September 2025) has passed.
What do you want to know about Shree Neha CHSL?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shree Neha CHSL has moved
30 May 2022
Completion date given when the project was registered
31 March 2023
Extended at the builder's request (MahaRERA application EXT51800012080)
Reason the builder gave MahaRERA: “Due to Outbreak of COVID 19”
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800016796)
Reason the builder gave MahaRERA:
“Due to the Covid pandemic situation, the project was unable to meet the original timeline and had to be extended until March 31, 2023. In accordance with this extension, the Developer has successfully completed the substantial work of Devel…” Read the full reason
“Due to the Covid pandemic situation, the project was unable to meet the original timeline and had to be extended until March 31, 2023. In accordance with this extension, the Developer has successfully completed the substantial work of Development, including RCC work, brick and block work, as per the approved plan. However, the remaining finishing and residual work require additional time to align with the March 2023 timeline. Furthermore, the necessary consent from the allottees has been obtained as per the required form outlined in circular no. 0717019 dated February 8, 2019. Enclosed with…”30 September 2025
Extended at the builder's request (MahaRERA application EXT51800019042)
Reason the builder gave MahaRERA:
“All RCC superstructure work and internal work has been completed and 5% of the parking tower work is pending and due to this fire work is pending in this area and we are awaiting for Fire NOC and once its received we will proceed for the OC…” Read the full reason
“All RCC superstructure work and internal work has been completed and 5% of the parking tower work is pending and due to this fire work is pending in this area and we are awaiting for Fire NOC and once its received we will proceed for the OC file. also attaching architect letter for completion of the work done without obtaining consent from”
Source: Shree Neha CHSL’s extension records on MahaRERA (P51800019288), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Neha CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800019288
- Status
- Lapsed (registration period ended)
- Builder
- HARI OM SAI GRIHANRMITI PVT LTD
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 21 Jan 2019
- Completion date at registration
- May 2022
- Latest completion date
- September 2025
- Delay so far
- 40 months
- Homes
- 44
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shree Neha CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE NEHA CO OPERATIVE HOUSING SOCIETY LTD | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Neha CHSL every 1–2 months.
Shree Neha CHSL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 393 – 416 | 29 |
| 2 BHK | 537 | 15 |
- Buildings: SHREE NEHA CO OPERATIVE HOUSING SOCIETY LTD (18 floors)
- Land: 762 sq m (about 0.2 acres) · sanctioned built-up 2,055 sq m
- Land, as filed: 1081
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Neha CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Neha CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shree Neha CHSL
What is the possession date of Shree Neha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Neha CHSL in Mulund East, Mumbai is 30 September 2025 — 40 months later than 30 May 2022, the date given at registration. That date has already passed.
The date has already moved 40 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shree Neha CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Neha CHSL's builder has filed on MahaRERA, the official one, is 30 September 2025, already 40 months later than the 30 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Neha CHSL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2023, giving the reason "Due to Outbreak of COVID 19"; to 31 December 2023, giving the reason "Due to the Covid pandemic situation, the project was unable to meet the original timeline and had to be extended until March 31, 2023. In accordance with this extension, the Developer has successfully completed the substantial work of Development, including RCC work, brick and block work, as per the approved plan. However, the remaining finishing and residual work require additional time to align with the March 2023 timeline. Furthermore, the necessary consent from the allottees has been obtained as per the required form outlined in circular no. 0717019 dated February 8, 2019. Enclosed with…"; to 30 September 2025, giving the reason "All RCC superstructure work and internal work has been completed and 5% of the parking tower work is pending and due to this fire work is pending in this area and we are awaiting for Fire NOC and once its received we will proceed for the OC file. also attaching architect letter for completion of the work done without obtaining consent from".
What is the RERA number of Shree Neha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Neha CHSL in Mulund East, Mumbai is P51800019288.
Is Shree Neha CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL is registered as P51800019288 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shree Neha CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE NEHA CO OPERATIVE HOUSING SOCIETY LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Shree Neha CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shree Neha CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL is registered on MahaRERA as P51800019288, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 40 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shree Neha CHSL?
Shree Neha CHSL isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shree Neha CHSL are 393 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shree Neha CHSL?
For a flat in Shree Neha CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shree Neha CHSL received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shree Neha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Shree Neha CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Shree Neha CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Neha CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shree Neha CHSL's possession date changes?
The latest dates are on Shree Neha CHSL's MahaRERA page (P51800019288). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Neha CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Neha CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL has one building filed: SHREE NEHA CO OPERATIVE HOUSING SOCIETY LTD with 18 floors.
What are the flat sizes (carpet area) in Shree Neha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shree Neha CHSL: 1 BHK: 393 to 416 sq ft carpet (29 homes); 2 BHK: 537 sq ft carpet (15 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Shree Neha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL stands on 762 sq m of land (about 0.2 acres), with 2,055 sq m of sanctioned built-up area.
What are the reviews of Shree Neha CHSL?
Google Maps has reviews of Shree Neha CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shree Neha CHSL?
Shree Neha CHSL by HARI OM SAI GRIHANRMITI PVT LTD is in Mulund East, Mumbai, pincode 400081 (near Mulund West), Maharashtra, and is registered on MahaRERA as P51800019288, per GharKundli's check of MahaRERA records. Its land is filed as 1081. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).
How many flats are in Shree Neha CHSL, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL has 44 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Shree Neha CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Neha CHSL was registered on MahaRERA on 21 January 2019. GharKundli did not find a title report on the land on file there.
Does Shree Neha CHSL have any legal issues or court cases?
No court cases are listed for Shree Neha CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shree Neha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HARI OM SAI GRIHANRMITI PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of Shree Neha CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund East (400081)
- Satre Elite
- Pearl
- Rbi Employees Shree Sahawas Co Op HSG Soc LTD
- New Usha Vihar Chsl
- Bimal Apartment CHSL
- Guru Ashish
- Ganesh Dham
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.