Godrej Greens
by DREAM WORLD LANDMARKS LLP (Godrej) · Undri, Pune 412207
What’s in the report? →Possession: Godrej Greens (MahaRERA P52100000985) is marked completed on MahaRERA. It has 952 homes, 88% sold or booked. 34 complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100000985. Status: Completed. MahaRERA has issued a regulatory order on this project.
Source: MahaRERA website — records for P52100000985, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Godrej Greens?
19 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Godrej Greens has moved
30 September 2022
Completion date given when the project was registered
31 March 2023
Extended at the builder's request (MahaRERA application EXT52100012601)
Reason the builder gave MahaRERA: “on account of (I) COVID-19 Pandemic; (ii) shortage in supply of construction material, hardware, and equipment; and (iii) labour shortage - the overall completion of Project slowed-down. Thus Seeking extension of Registration.”
30 September 2023
Extended at the builder's request (MahaRERA application EXT52100015109)
Reason the builder gave MahaRERA: “In terms of application, we hereby seek extension of time for Godrej Greens by 6 months.”
30 September 2026
Extended at the builder's request (MahaRERA application EA05032620098)
Reason the builder gave MahaRERA: “As per Justification Letter attached”
Source: Godrej Greens’s extension records on MahaRERA (P52100000985), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Godrej Greens
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 34 complaints and 19 court cases, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100000985
- Status
- Completed
- Builder
- DREAM WORLD LANDMARKS LLP
- Location
- Undri, Pune · 412207
- Project type
- Residential / Group Housing
- Registered on
- 25 Jul 2017
- Completion date at registration
- September 2022
- Latest completion date
- September 2026
- Delay so far
- 48 months
- Homes
- 952
- Sold or booked
- 88%
- Towers
- 6
- Complaints on MahaRERA
- 34
- Court cases listed
- 19
- Appeals at the tribunal
- 4
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Godrej Greens, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B1 | 100% | 100% | 100% | 100% |
| B2 | 100% | 100% | 100% | 100% |
| B3 | 100% | 100% | 100% | 100% |
| B4 | 100% | 100% | 100% | 100% |
| B5 | 100% | 100% | 100% | 100% |
| B6 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- B1: covers 17 floors
- B2: covers 17 floors
- B3: covers 17 floors
- B4: covers 17 floors
- B5: covers 17 floors
- B6: covers 17 floors
Latest CC order on MahaRERA: dated 31/07/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Godrej Greens every 1–2 months.
Godrej Greens: buildings, flats and land, as filed on MahaRERA
- Buildings: B1 (20 floors, 204 units) · B2 (20 floors, 136 units) · B3 (20 floors, 136 units) · B4 (19 floors, 136 units) · B5 (19 floors, 136 units) · B6 (19 floors, 204 units)
- Car parking: 644 covered
- Land: 42,691 sq m (about 10.5 acres) · sanctioned built-up 80,111 sq m · recreational space 9,801 sq m
- Land, as filed: Survey no. 31 part , 32 part, 33 part, 34 part, 37 part and 40 part
- Map: Get directions
The builder’s record and reviews
Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 23 finished, 18 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 2 lapsed. 571 complaints on MahaRERA across 62 projects.
Read Google reviews of Godrej Greens →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Godrej Greens: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Godrej Greens
What is the possession date of Godrej Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Godrej Greens in Undri, Pune is 30 September 2026 — 48 months later than 30 September 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Godrej Greens?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Godrej Greens's builder has filed on MahaRERA, the official one, is 30 September 2026, already 48 months later than the 30 September 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Godrej Greens extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2023, giving the reason "on account of (I) COVID-19 Pandemic; (ii) shortage in supply of construction material, hardware, and equipment; and (iii) labour shortage - the overall completion of Project slowed-down. Thus Seeking extension of Registration."; to 30 September 2023, giving the reason "In terms of application, we hereby seek extension of time for Godrej Greens by 6 months."; to 30 September 2026, giving the reason "As per Justification Letter attached".
What is the RERA number of Godrej Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Godrej Greens in Undri, Pune is P52100000985.
Is Godrej Greens registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens is registered as P52100000985 and its status is "Completed".
What is the current construction status of Godrej Greens? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does Godrej Greens have complaints on MahaRERA?
34 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
34 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →
Is Godrej Greens safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens is registered on MahaRERA as P52100000985, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and 34 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Godrej Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Godrej Greens?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Godrej Greens: gharkundli.com/tools/property-cost-calculator
Has Godrej Greens received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Godrej Greens completed?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens is marked completed on MahaRERA, and the completion date filed there is 30 September 2026. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Godrej Greens uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Godrej Greens was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Godrej Greens's possession date changes?
The latest dates are on Godrej Greens's MahaRERA page (P52100000985). GharKundli's Kundli Watch sends a free WhatsApp update on Godrej Greens every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Godrej Greens have?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens has 6 buildings filed: B1 with 20 floors and 204 units; B2 with 20 floors and 136 units; B3 with 20 floors and 136 units; B4 with 19 floors and 136 units; B5 with 19 floors and 136 units; B6 with 19 floors and 204 units.
How much parking does Godrej Greens have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 644 covered car parking spaces for Godrej Greens.
How big is the land of Godrej Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens stands on 42,691 sq m of land (about 10.5 acres), with 80,111 sq m of sanctioned built-up area and 9,801 sq m of recreational open space.
What is the track record of Godrej Greens's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Properties (a group of 18 linked companies) has 99 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 23 finished, 18 within the promised date and 5 needed more time (typically 13 months); 71 still being built, 12 past the promised date (typically 9 months late); 2 lapsed. 571 complaints on MahaRERA across 62 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Godrej Greens?
Google Maps has reviews of Godrej Greens written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 34 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Godrej Greens?
Godrej Greens by DREAM WORLD LANDMARKS LLP (Godrej) is in Undri, Pune, pincode 412207, Maharashtra, and is registered on MahaRERA as P52100000985, per GharKundli's check of MahaRERA records. Its land is filed as Survey no. 31 part , 32 part, 33 part, 34 part, 37 part and 40 part. GharKundli lists all 379 MahaRERA projects in Wagholi (412207).
How many flats are in Godrej Greens, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens has 952 homes in 6 towers registered on MahaRERA, and 88% of them are sold or booked.
When was Godrej Greens registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Godrej Greens was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.
Does Godrej Greens have any legal issues or court cases?
19 court cases are listed for Godrej Greens on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Godrej Greens?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DREAM WORLD LANDMARKS LLP, the company Godrej files this project under, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Godrej Greens
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wagholi (412207)
- Dynamic Solitaire – Phase II
- SKY PAVILION Phase II
- Dynamic Solitaire
- Ganga Fernhill phase 02
- Ved Tanish Phase I
- Astonia Classic Phase II - A5 Building
- Tradeparkb
- Sukhwani Verde
Other projects by DREAM WORLD LANDMARKS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.