SKP SKY PAVILION Phase II
by SKP Corp Private Limited · Undri, Pune 411060Also near Pisoli, YewalewadiRegistered on MahaRERA as “SKY PAVILION Phase II”
What’s in the report? →Possession date of SKP SKY PAVILION Phase II (MahaRERA P52100018243): 30 April 2027, moved from 30 June 2021 (66 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100018243, and currently active. Its completion date has moved from June 2021 to April 2027: 66 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100018243, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about SKP SKY PAVILION Phase II?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of SKP SKY PAVILION Phase II has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT52100009737)
Reason the builder gave MahaRERA:
“COVID - 19 pandemic and other factors such as lockdown, delay in materials supply, and other factors affecting the market condition and construction activities the promoter is unable to complete the project in this time period. Therefore, r…” Read the full reason
“COVID - 19 pandemic and other factors such as lockdown, delay in materials supply, and other factors affecting the market condition and construction activities the promoter is unable to complete the project in this time period. Therefore, request you to kindly provide an extension for 1 year. The Self-certified copy of the permission/approval from the competent authority is attached for your perusal.”31 December 2024
Extended at the builder's request (MahaRERA application EXT52100016669)
Reason the builder gave MahaRERA:
“The construction of the said project is almost completed but unfortunately, we were unable to complete the project by the stipulated timeline because of the slow market condition and slump in the real estate market during the period creatin…” Read the full reason
“The construction of the said project is almost completed but unfortunately, we were unable to complete the project by the stipulated timeline because of the slow market condition and slump in the real estate market during the period creating acute economic crises which ultimately slowed down the sale transactions. We are committed to complete and deliver the project. The allottees has provided the required consent which is attached for your perusal.”31 December 2026
Extended at the builder's request (MahaRERA application EXT52100028122)
Reason the builder gave MahaRERA:
“1. Project is 85 % completed 2. Consent of 91.30 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Other Techn…” Read the full reason
“1. Project is 85 % completed 2. Consent of 91.30 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Other Technical Tab of the Main Application 5. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 3 6. QPR till date are updated 7. Due to unavoidable circumstances project has been delay and it will be completed by 31/12/2026”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SKP SKY PAVILION Phase II’s extension records on MahaRERA (P52100018243), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SKP SKY PAVILION Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SKY Pavilion Phase IP52100013569 · possession 29 Jun 2022
- MahaRERA registration
- P52100018243
- Status
- Registered and active
- Builder
- SKP Corp Private Limited
- Location
- Undri, Pune · 411060
- Project type
- Commercial
- Registered on
- 16 Oct 2018
- Completion date at registration
- June 2021
- Latest completion date
- April 2027
- Delay so far
- 66 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of SKP SKY PAVILION Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SKY PAVILION PHASE II | 100% | 100% | 86% | 86% |
Commencement certificate (CC), as filed on MahaRERA
- SKY PAVILION PHASE II: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SKP SKY PAVILION Phase II every 1–2 months.
SKP SKY PAVILION Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: SKY PAVILION PHASE II (5 floors, 53 units)
- Land: 3,475 sq m (about 0.9 acres) · sanctioned built-up 3,469 sq m
- Land, as filed: Sr No 62/2/2 Part and 60/3 Undri Pune
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
SKP Corp has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 2 past the promised date (typically 47 months late). No complaints on MahaRERA.
Read Google reviews of SKP SKY PAVILION Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SKP SKY PAVILION Phase II: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about SKP SKY PAVILION Phase II
What is the possession date of SKP SKY PAVILION Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SKP SKY PAVILION Phase II in Undri, Pune is 30 April 2027 — 66 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 66 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for SKP SKY PAVILION Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SKP SKY PAVILION Phase II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SKP SKY PAVILION Phase II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "COVID - 19 pandemic and other factors such as lockdown, delay in materials supply, and other factors affecting the market condition and construction activities the promoter is unable to complete the project in this time period. Therefore, request you to kindly provide an extension for 1 year. The Self-certified copy of the permission/approval from the competent authority is attached for your perusal."; to 31 December 2024, giving the reason "The construction of the said project is almost completed but unfortunately, we were unable to complete the project by the stipulated timeline because of the slow market condition and slump in the real estate market during the period creating acute economic crises which ultimately slowed down the sale transactions. We are committed to complete and deliver the project. The allottees has provided the required consent which is attached for your perusal."; to 31 December 2026, giving the reason "1. Project is 85 % completed 2. Consent of 91.30 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Other Technical Tab of the Main Application 5. Explanatory Note for Delay in project Completion Uploaded in Other Tab No. 3 6. QPR till date are updated 7. Due to unavoidable circumstances project has been delay and it will be completed by 31/12/2026". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SKP SKY PAVILION Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SKP SKY PAVILION Phase II in Undri, Pune is P52100018243.
Is SKP SKY PAVILION Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II is registered as P52100018243 and its status is "Registered and active".
What is the current construction status of SKP SKY PAVILION Phase II? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SKY PAVILION PHASE II is 100% done and internal work 86%. GharKundli's full report compares construction progress with the deadline.
Does SKP SKY PAVILION Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SKP SKY PAVILION Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II is registered on MahaRERA as P52100018243, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in SKP SKY PAVILION Phase II?
SKP SKY PAVILION Phase II is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in SKP SKY PAVILION Phase II?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in SKP SKY PAVILION Phase II: gharkundli.com/tools/property-cost-calculator
Has SKP SKY PAVILION Phase II received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has SKP SKY PAVILION Phase II uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for SKP SKY PAVILION Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does SKP SKY PAVILION Phase II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SKY Pavilion Phase I (P52100013569, possession 29 Jun 2022). Check that your agreement names the registration of your own wing.
How can I get updates if SKP SKY PAVILION Phase II's possession date changes?
The latest dates are on SKP SKY PAVILION Phase II's MahaRERA page (P52100018243). GharKundli's Kundli Watch sends a free WhatsApp update on SKP SKY PAVILION Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SKP SKY PAVILION Phase II have?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II has one building filed: SKY PAVILION PHASE II with 5 floors and 53 units.
How big is the land of SKP SKY PAVILION Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II stands on 3,475 sq m of land (about 0.9 acres), with 3,469 sq m of sanctioned built-up area.
What is the track record of SKP SKY PAVILION Phase II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP Corp has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 17 months); 2 still being built, 2 past the promised date (typically 47 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of SKP SKY PAVILION Phase II?
Google Maps has reviews of SKP SKY PAVILION Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of SKP SKY PAVILION Phase II?
SKP SKY PAVILION Phase II by SKP Corp Private Limited is in Undri, Pune, pincode 411060 (near Pisoli, Yewalewadi), Maharashtra, and is registered on MahaRERA as P52100018243, per GharKundli's check of MahaRERA records. Its land is filed as Sr No 62/2/2 Part and 60/3 Undri Pune. GharKundli lists all 236 MahaRERA projects in Undri (411060).
How many flats are in SKP SKY PAVILION Phase II, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II has 0 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was SKP SKY PAVILION Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SKP SKY PAVILION Phase II was registered on MahaRERA on 16 October 2018. GharKundli did not find a title report on the land on file there.
Does SKP SKY PAVILION Phase II have any legal issues or court cases?
No court cases are listed for SKP SKY PAVILION Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of SKP SKY PAVILION Phase II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SKP Corp Private Limited, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SKP SKY PAVILION Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Undri (411060)
- Dynamic Solitaire – Phase II
- Dynamic Solitaire
- Ganga Fernhill phase 02
- Godrej Greens
- Ved Tanish Phase I
- Astonia Classic Phase II - A5 Building
- Tradeparkb
- Sukhwani Verde
Other projects by SKP Corp Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.