According to GharKundli's check of MahaRERA records, 146 housing projects are registered in pincode 411060 (Undri, Pune). 91 are still being built, 27 with possession due by the end of 2027. For 93, the completion date on MahaRERA is later than the one first promised. 61 have at least one complaint filed on MahaRERA.
Pincode 411060 also covers: Mohammadwadi, Nibm, Mohamadwadi, Off NIBM, Pisoli, Undri-Ext.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| Al Marjaan Briskband Associates | Active | 30 Oct 2026passed | 30 Dec 2024 | 9 |
| tradeparkb VTP Mohite Associates | Active | 30 Oct 2026passed | 30 Dec 2023 | 1 |
| Ganga Fernhill phase 02 MEENAMANI GANGA BUILDERS LLP | Active | 30 Dec 2026 | 30 Dec 2025 | 6 |
| Astonia Classic Phase II - A5 Building AMIT ENTERPRISES HOUSING LIMITED | Active | 31 Dec 2026 | 31 Dec 2020 | 0 |
| KHUSH VISTA Elated Housing LLP | Active | 31 Dec 2026 | same | 1 |
| Neco Officers Ville I Vasupujya Corporation | Active | 31 Dec 2026 | same | 0 |
| ARNAV SOKANDE PATIL PLAZA SOKANDE PATIL PROM & DEVELOPERS | Active | 1 Mar 2027 | 30 May 2023 | 0 |
| 38 Park Majestique Phase V Majestique Promoters AOP | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| CALLISTO NAYAN BUILDERS | Active | 30 Apr 2027 | 30 Dec 2023 | 10 |
| EL REGALO MAHESH REALTORS | Active | 30 Apr 2027 | 30 Dec 2023 | 2 |
| Engracia B C E F M/s Pacific Orient Genesis Associates | Active | 30 Apr 2027 | 30 Dec 2023 | 37 |
| Lodha Bella Vita Signet Lodha Developers Limited | Active | 30 Apr 2027 | 31 Dec 2026 | 1 |
| Lodha Pune NIBM Project-Tower 10 Lodha Developers Limited | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Neco Officers Ville II Vasupujya Corporation | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Palmspring Towers - A4, A5 and B2 KUMAR KERING DEVELOPERS LLP | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| SAI ARCADE Maanvi Developers | Active | 30 Apr 2027 | 31 Dec 2024 | 0 |
| SKY PAVILION Phase II SKP Corp Private Limited | Active | 30 Apr 2027 | 30 Jun 2021 | 0 |
| T11 named as Raheja Stellar in RV Premiere Cavalcade Properties Private Limited (Raheja) | Active | 30 Apr 2027 | 31 Dec 2026 | 2 |
| GOLDEN COURT Silverleaf landmarks llp | Active | 30 Jun 2027 | 30 Jun 2025 | 0 |
| NYATI EXUBERANCE IV NYATI BUILDERS PRIVATE LIMITED | Active | 31 Jul 2027 | 31 Mar 2026 | 2 |
| SHINDE ASSOCIATES ANIL JAGANNATH SHINDE | Active | 31 Jul 2027 | 25 Nov 2022 | 0 |
| Ved Tanish Phase I Bandal Jarande Ventures | Active | 25 Aug 2027 | 25 Apr 2026 | 0 |
| Ved Tanish Phase II Bandal Jarande Ventures | Active | 30 Aug 2027 | 30 Apr 2027 | 0 |
| NYATI ESTEBAN II NYATI REALTORS LLP | Active | 30 Sep 2027 | same | 3 |
| LANTANA COURT A BUILDING Landmark Ventures | Active | 30 Nov 2027 | 31 Jul 2027 | 0 |
| Samarth Rise Shri Samarth Developers | Active | 15 Dec 2027 | 15 Aug 2026 | 0 |
| Sukhwani Verde Sagar Gurmukh Sukhwani | Active | 30 Dec 2027 | 30 Dec 2026 | 2 |
| ELATE M/s. Guddwill RVN Spaces LLP | Active | 29 Feb 2028 | 31 Oct 2027 | 0 |
| RIVA ASIAN VENTURES | Active | 20 Mar 2028 | 30 Sep 2020 | 1 |
| TENSIDE TENSIDE REALITY | Active | 30 Mar 2028 | 30 Nov 2027 | 0 |
| ATUR VALLEY VISTA WING A M/S ATUR SANGTANI AND ASSOCIATES | Active | 30 Apr 2028 | 31 Dec 2025 | 0 |
| AVIRO SQUARE Krishna Vision | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| DORABJEE HEIGHTS DORABJEE ESTATES PRIVATE LIMITED | Active | 30 Apr 2028 | 31 Dec 2026 | 0 |
| GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N MILLENNIA SCHEMES PRIVATE LIMITED | Active | 30 Apr 2028 | 30 Jun 2025 | 4 |
| HILL GREEN DATTARAJ BUILDCON | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| KP ARCHANA PARADISE PHASE 03 KANIFNATH PROPERTIES | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Lodha Pune NIBM Project- Tower 7,8 and 9 Lodha Developers Limited | Active | 30 Apr 2028 | 31 Dec 2027 | 2 |
| MEMORIES 90 - PHASE IV M/s NAMO DEVELOPERS | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| SOMNATH VASTU SAIRAJ CONSTRUCTIONS | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| The Atrium Arhumashtika Life Spaces | Active | 30 Apr 2028 | 31 Dec 2027 | 1 |
| UBC DHONE BATHIYA ENTERPRISES LLP | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| GANGA VASANT GANRAJ TOWNSHIP LLP | Active | 30 Oct 2028 | 30 Dec 2024 | 0 |
| Karma Rejoice Rejoice homes LLP | Active | 30 Oct 2028 | 30 Dec 2026 | 2 |
| SHREEJA SERENE Yogiraj Krishna Lohokare | Active | 30 Oct 2028 | 30 Jun 2028 | 0 |
| T2 named Constella of Raheja Galaxy in RV Premiere CAVALCADE PROPERTIES PVT LTD (Raheja) | Active | 30 Nov 2028 | 31 Jul 2028 | 0 |
| T3 named Altair of Raheja Galaxy in RV Premiere CAVALCADE PROPERTIES PVT LTD (Raheja) | Active | 30 Nov 2028 | 31 Jul 2028 | 0 |
| Casa Mia A R R CONSTRUCTIONS | Active | 31 Dec 2028 | 30 Jun 2019 | 0 |
| SKY GATE SGD REALTORS | Active | 28 Feb 2029 | 31 Oct 2028 | 0 |
| T1 named Helios of Raheja Galaxy in RV Premiere CAVALCADE PROPERTIES PVT LTD (Raheja) | Active | 30 Mar 2029 | 30 Nov 2028 | 1 |
| Aura Aiwa SKYSCAPES HOMES LLP | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
96 more projects
- CONSTELLA · 30 Apr 2029
- MAYURI ADHINATHPURAM · 30 Apr 2029
- Palmspring Towers - A1, A2 and A3 · 30 Apr 2029
- SAHIL VATIKA · 30 Apr 2029
- The Landmark · 30 Apr 2029
- High-Street of Raheja Galaxy in RVP · 31 Jul 2029
- DREAMS ASMITA · 28 Sep 2029
- BASIL FAB 11 · 30 Nov 2029
- Dynamic Grandeur Premium H · 31 Dec 2029
- Hillcrest Manor · 30 Jan 2030
- Palmspring Towers - A8, A12 and B1 · 27 Mar 2030
- 11 SQUARE · 30 Mar 2030
- GANGA IMPERIA BLDG A · 31 Mar 2030
- AERO EAST - PH IV · 30 Apr 2030
- BHOOMI ARCADIA · 30 Apr 2030
- GANGA IMPERIA COMMERCIAL · 30 Apr 2030
- KP SUPERNOVA · 30 Apr 2030
- MALHAR AARAMBH · 30 Apr 2030
- Prime Vista · 30 Apr 2030
- Prime Vista Row Houses · 30 Apr 2030
- Palmspring Towers - A9, A10 and A11 · 20 Jul 2030
- GANGA GENESIA · 31 Jul 2030
- Stellaris · 31 Jul 2030
- T4A named Celina of Raheja Galaxy in RV Premiere · 31 Jul 2030
- MAHALAXMI ELEGANCE · 1 Sep 2030
- NYATI ESTEBAN III · 30 Nov 2030
- DYNAMIC SOLITAIRE – PHASE II · 31 Dec 2030
- Rezo Phase 1 · 31 Dec 2030
- Raheja Aurum · 30 Mar 2031
- Kalaya Greens Phase I · 9 Apr 2031
- Banka Sapphire · 30 Apr 2031
- KUMAR PALMNEST · 30 Apr 2031
- T4 named Astra of Raheja Galaxy in RV Premiere · 30 Apr 2031
- The Ark Voyage to the Star Tower E Annex · 30 Apr 2031
- Dynamic Grandeur Premium I · 30 Dec 2031
- Dynamic Grandeur Premium J Wing · 31 Dec 2031
- Dynamic Solitaire · 31 Dec 2031
- 5 Senses iLife · 30 Apr 2032
- RBD- ELINA LEGEND · 30 Apr 2032
- THE TITAN TOWERS · 30 Apr 2032
- THE SPECTRUM · 14 Aug 2035
- Mi Casa · completed
- Centria R Building - Casa · completed
- GANGA GLITZ G UNDRI PUNE · completed
- AMITs COLORI Phase-III G Building · completed
- Voyage to the stars - Commercial · completed
- Gagan Ela · completed
- NYATI EXUBERANCE III · completed
- ELINA LITE · completed
- AVIRO · completed
- Lodha Pune NIBM Project · completed
- Lodha Pune NIBM Project-Tower 5 · completed
- Lodha Pune NIBM Project-Tower 6 · completed
- ROYAL KP STELLAR · completed
- SAI VISHWA · 31 Dec 2024
- NYATI EXUBERANCE II · 31 Mar 2025
- ATRIUM SKYWARD WING D · 30 Jun 2025
- NYATI EXUBERANCE I · 30 Sep 2025
- TheCrown · 30 Sep 2025
- CHOWHAN RESIDENCY PHASE II · 31 Dec 2025
- PRAGATI SERENE · 31 Jul 2026
- 38-Park Majestique · —
- AMITs COLORI Phase-II H and I Building · —
- Atrium Skyward · —
- Avani II · —
- BENCHMARK · —
- BROOKEFIELD WILLOWS · —
- COLLINA · —
- Dynamic Oasis · —
- ELINA LIVING · —
- ELINA LIVING PHASE III · —
- Gagan Tisha · —
- GANGA FERNHILL PHASE I · —
- LA ROYALE - A BUILDING · —
- LA ROYALE - B BUILDING · —
- LA ROYALE - C BUILDING · —
- LUSHLIFE OVO · —
- MANTRA ESSENCE PHASE 4 · —
- MANTRA ESSENCE PHASE 5 · —
- MANTRA ESSENCE PHASE 6 · —
- Neco Beaumont · —
- NYATI ESTEBAN I · —
- NYATI ETHOS I - A1-Part · —
- NYATI ETHOS I - B3 · —
- NYATI EVARA I · —
- Platinum Park Phase I · —
- Platinum Park Phase II · —
- RAHEJA STERLING - TOWER 5 · —
- SERRENE · —
- SIGMA AVENTINO · —
- T8 named LUXURIANT Phase 2 of Raheja Reserve being Buildings T7 T8 T9 T10 in RV Premiere · —
- T9 Chronos and T10 Supremus Phase 1 Of Raheja Reserve being Buildings T7 T8 T9 T10 in RV Premiere · —
- The Ark - Voyage to the Stars - Phase II · —
- TULSI SHAKUNTALA KANADE NAGAR · —
- VISTAS CENTREPOINT · —
- Voyage to the Stars - Phase I · —
Other areas in Pune
- Alandi Devachi · 450
- Chinchwadgaon · 370
- Wakad · 367
- Baner · 363
- Ravet · 344
- Kothrud · 276
- Wagholi · 230
- N I B M · 210
- Armament · 193
- Kharadi · 188
- Katraj · 186
- Bhugaon · 170
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.