by SHREE VYANKATESH PROMOTERS ANDBUILDERS · Pirangut, Pune 412115Registered on MahaRERA as “BLUE BERRY”

What’s in the report? →

Possession date of Vyankatesh Blue Berry (MahaRERA P52100013035): 22 August 2023, and it has already passed. It has 84 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100013035. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100013035, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2023) has passed.

What do you want to know about Vyankatesh Blue Berry?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Vyankatesh Blue Berry

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100013035
Status
Lapsed (registration period ended)
Builder
SHREE VYANKATESH PROMOTERS ANDBUILDERS
Location
Pirangut, Pune · 412115
Project type
Commercial
Registered on
12 Sep 2017
Completion date at registration
August 2023
Latest completion date
August 2023
Homes
84
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Vyankatesh Blue Berry, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A WING0%0%0%0%
B AND C100%20%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vyankatesh Blue Berry every 1–2 months.

Vyankatesh Blue Berry: buildings, flats and land, as filed on MahaRERA

  • Buildings: A WING (6 floors) · B AND C (6 floors)
  • Car parking: 10 covered
  • Land: 2,500 sq m (about 0.6 acres) · sanctioned built-up 2,857 sq m
  • Land, as filed: GAT NO 840 841
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Vyankatesh Blue Berry →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vyankatesh Blue Berry: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vyankatesh Blue Berry

What is the possession date of Vyankatesh Blue Berry?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vyankatesh Blue Berry in Pirangut, Pune is 22 August 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Vyankatesh Blue Berry?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vyankatesh Blue Berry's builder has filed on MahaRERA, the official one, is 22 August 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Vyankatesh Blue Berry?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vyankatesh Blue Berry in Pirangut, Pune is P52100013035.

Is Vyankatesh Blue Berry registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry is registered as P52100013035 and its status is "Lapsed (registration period ended)".

What is the current construction status of Vyankatesh Blue Berry? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 20% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Vyankatesh Blue Berry have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Vyankatesh Blue Berry safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry is registered on MahaRERA as P52100013035, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vyankatesh Blue Berry?

Vyankatesh Blue Berry isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vyankatesh Blue Berry?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vyankatesh Blue Berry: gharkundli.com/tools/property-cost-calculator

Has Vyankatesh Blue Berry received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 22 August 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Vyankatesh Blue Berry?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (22 August 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Vyankatesh Blue Berry uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Vyankatesh Blue Berry was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Vyankatesh Blue Berry's possession date changes?

The latest dates are on Vyankatesh Blue Berry's MahaRERA page (P52100013035). GharKundli's Kundli Watch sends a free WhatsApp update on Vyankatesh Blue Berry every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vyankatesh Blue Berry have?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry has 2 buildings filed: A WING with 6 floors; B AND C with 6 floors.

How much parking does Vyankatesh Blue Berry have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 10 covered car parking spaces for Vyankatesh Blue Berry.

How big is the land of Vyankatesh Blue Berry?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry stands on 2,500 sq m of land (about 0.6 acres), with 2,857 sq m of sanctioned built-up area.

What are the reviews of Vyankatesh Blue Berry?

Google Maps has reviews of Vyankatesh Blue Berry written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vyankatesh Blue Berry?

Vyankatesh Blue Berry by SHREE VYANKATESH PROMOTERS ANDBUILDERS is in Pirangut, Pune, pincode 412115, Maharashtra, and is registered on MahaRERA as P52100013035, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO 840 841. GharKundli lists all 237 MahaRERA projects in Pirangut (412115).

How many flats are in Vyankatesh Blue Berry?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry has 84 homes in 2 towers registered on MahaRERA.

When was Vyankatesh Blue Berry registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vyankatesh Blue Berry was registered on MahaRERA on 12 September 2017. GharKundli did not find a title report on the land on file there.

Does Vyankatesh Blue Berry have any legal issues or court cases?

No court cases are listed for Vyankatesh Blue Berry on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Vyankatesh Blue Berry?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE VYANKATESH PROMOTERS ANDBUILDERS.

Other projects in Pirangut (412115)

All 237 projects in Pirangut (412115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.