by R K Shinde Developers · Bhugaon, Pune 412115Also near PirangutRegistered on MahaRERA as “Pre Eminence”

What’s in the report? →

Possession date of Shinde Pre Eminence (MahaRERA P52100055471): 30 April 2028, moved from 31 December 2025 (24 months later). It has 18 homes, 25% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100055471, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100055471, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What MahaRERA’s sales freeze means for Shinde Pre Eminence

R K Shinde Developers, the builder
can't sign new agreements for sale or sale deeds for Shinde Pre Eminence, and can't use the money in the project's bank account, until MahaRERA lifts the freeze.
If you're thinking of buying in Shinde Pre Eminence
you can't get a registered agreement for a flat here right now. A token or booking amount paid now has no registered agreement behind it, so it isn't protected. Don't pay anything until MahaRERA lifts the freeze.
If you already bought in Shinde Pre Eminence
your agreement for sale, signed before the freeze, and your rights under it still stand. With the project's bank account frozen, construction can slow down: ask R K Shinde Developers in writing what is pending and when it will be fixed.
If you want to resell a flat in Shinde Pre Eminence
MahaRERA's order speaks of the builder's agreements, not resale between buyers. But a transfer usually needs the builder's NOC or a tripartite agreement, which R K Shinde Developers may not be able to sign while the freeze lasts. Check with the builder and a lawyer before you agree a resale.

This kind of freeze is often lifted once the builder files the missing quarterly reports. Ask R K Shinde Developers when they will file them.

General information from MahaRERA’s own order text, not legal advice. For a specific purchase, check with a lawyer.

What do you want to know about Shinde Pre Eminence?

MahaRERA ki red-flag list mein hai. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shinde Pre Eminence has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA29122519074)

    Reason the builder gave MahaRERA: “Due to Finance”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Shinde Pre Eminence’s extension records on MahaRERA (P52100055471), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shinde Pre Eminence

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100055471
Status
Registered and active
Builder
R K Shinde Developers
Location
Bhugaon, Pune · 412115
Project type
Residential / Group Housing
Registered on
2 Apr 2024
Completion date at registration
December 2025
Latest completion date
April 2028
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
18
Sold or booked
25%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shinde Pre Eminence, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PRE EMINENCE25%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • PRE EMINENCE: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shinde Pre Eminence every 1–2 months.

Shinde Pre Eminence: buildings, flats and land, as filed on MahaRERA

  • Buildings: PRE EMINENCE (2 floors, 18 units)
  • Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 825 sq m
  • Land, as filed: 280/(2P)
  • Map: Get directions

The builder’s record and reviews

Vastushilp Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 12 months late). No complaints on MahaRERA.

Read Google reviews of Shinde Pre Eminence →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shinde Pre Eminence: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shinde Pre Eminence

Can I book a flat in Shinde Pre Eminence now?

Not while MahaRERA's sales freeze lasts. MahaRERA has put Shinde Pre Eminence in abeyance (quarterly reports not filed): until it is lifted, R K Shinde Developers may not sign agreements for sale or sale deeds, and the project's bank account is frozen. A token paid now has no registered agreement behind it. Buyers who signed their agreement before the freeze keep their rights, but construction can slow down. This kind of freeze is often lifted once the builder files the missing quarterly reports. Ask R K Shinde Developers when they will file them. GharKundli rechecks MahaRERA's lists daily and shows here when the freeze is lifted.

What is the possession date of Shinde Pre Eminence?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shinde Pre Eminence in Bhugaon, Pune is 30 April 2028 — 24 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shinde Pre Eminence?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shinde Pre Eminence's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shinde Pre Eminence extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Due to Finance". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Shinde Pre Eminence?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shinde Pre Eminence in Bhugaon, Pune is P52100055471.

Is Shinde Pre Eminence registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence is registered as P52100055471 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: quarterly reports not filed. MahaRERA has put this project in abeyance for not filing its quarterly progress reports (report missing for: April 2024). Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.

What is the current construction status of Shinde Pre Eminence? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence's status on MahaRERA is "Registered and active". As filed by the builder, slab work on PRE EMINENCE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shinde Pre Eminence have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shinde Pre Eminence safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence is registered on MahaRERA as P52100055471, its completion date has moved 24 months since registration, no complaints are listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: quarterly reports not filed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shinde Pre Eminence?

Shinde Pre Eminence is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shinde Pre Eminence?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shinde Pre Eminence: gharkundli.com/tools/property-cost-calculator

Has Shinde Pre Eminence received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Shinde Pre Eminence uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shinde Pre Eminence was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shinde Pre Eminence's possession date changes?

The latest dates are on Shinde Pre Eminence's MahaRERA page (P52100055471). GharKundli's Kundli Watch sends a free WhatsApp update on Shinde Pre Eminence every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shinde Pre Eminence have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence has one building filed: PRE EMINENCE with 2 floors and 18 units.

How big is the land of Shinde Pre Eminence?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence stands on 1,000 sq m of land (about 0.2 acres), with 825 sq m of sanctioned built-up area.

What is the track record of Shinde Pre Eminence's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vastushilp Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 12 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shinde Pre Eminence?

Google Maps has reviews of Shinde Pre Eminence written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shinde Pre Eminence?

Shinde Pre Eminence by R K Shinde Developers is in Bhugaon, Pune, pincode 412115 (near Pirangut), Maharashtra, and is registered on MahaRERA as P52100055471, per GharKundli's check of MahaRERA records. Its land is filed as 280/(2P). GharKundli lists all 237 MahaRERA projects in Pirangut (412115).

How many flats are in Shinde Pre Eminence, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence has 18 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.

When was Shinde Pre Eminence registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shinde Pre Eminence was registered on MahaRERA on 2 April 2024. GharKundli did not find a title report on the land on file there.

Does Shinde Pre Eminence have any legal issues or court cases?

No court cases are listed for Shinde Pre Eminence on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shinde Pre Eminence?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is R K Shinde Developers.

All projects with possession due in 2028 in Pune →

Other projects in Pirangut (412115)

All 237 projects in Pirangut (412115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.