Skip to content
GharKundli

Swagat Nandanvan Park

by SWAGAT PROMOTERS AND BUILDERS · Bhugaon, Pune 412115Also near PirangutRegistered on MahaRERA as “NANDANVAN PARK”

What’s in the report? →

Possession date of Swagat Nandanvan Park (MahaRERA P52100000846): 23 March 2028, moved from 28 May 2021 (78 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100000846, and currently active. Its completion date has moved from May 2021 to March 2028: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P52100000846, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Swagat Nandanvan Park?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Swagat Nandanvan Park has moved

  1. 28 May 2021

    Completion date given when the project was registered

  2. 28 May 2022

    Extended at the builder's request (MahaRERA application EXT52100009752)

    Reason the builder gave MahaRERA:
    “We Swagat Developers and Builder had registered out Real Estate project viz. ‘Nandanvan Park’ with you under Project Registration No. P5210000084. The Project Completion Date is 28.05.2021. Though the structural and site development is comp…” Read the full reason“We Swagat Developers and Builder had registered out Real Estate project viz. ‘Nandanvan Park’ with you under Project Registration No. P5210000084. The Project Completion Date is 28.05.2021. Though the structural and site development is completed in full , due to labor and material shortage owing to ‘ Global Pandemic’ and ‘Recent Lockdown’ few actions like OC and Handover is still pending. We require some more time to finish the project and complete paper work for Handover to Association of Allottee In Light of above fact we request you to grant us 1 year extension for project completion and…”
  3. 20 November 2023

    Extended at the builder's request (MahaRERA application EXT52100012929)

    Reason the builder gave MahaRERA:
    “As on 21.11.2022 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune,…” Read the full reason“As on 21.11.2022 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) Delay in receipt of NOC from Ministry of Civil Aviation about building height permission 2) Fire NOC not yet received in respect of completion of the project from Fire Officer There is time required for getting documents compliance to get completion certificate for remaining 6 flats at 6th Floor, you are reques…”
  4. 26 November 2024

    Extended at the builder's request (MahaRERA application EXT52100018030)

    Reason the builder gave MahaRERA:
    “As on 27.11.2023 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune,…” Read the full reason“As on 27.11.2023 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA. There is time required for getting documents compliance to get completion certificate for remaining 6 flats…”
  5. 25 November 2025

    Extended at the builder's request (MahaRERA application EXT52100025629)

    Reason the builder gave MahaRERA:
    “As on 19.12.2024 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune,…” Read the full reason“As on 19.12.2024 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA.”
  6. 23 November 2027

    Extended at the builder's request (MahaRERA application EA10082622068)

    Reason the builder gave MahaRERA:
    “As on 10.08.2026 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune,…” Read the full reason“As on 10.08.2026 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA. The above mentioned technical issue not resolved from PMRDA department till date.”
  7. 23 March 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Swagat Nandanvan Park’s extension records on MahaRERA (P52100000846), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Swagat Nandanvan Park

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100000846
Status
Registered and active
Builder
SWAGAT PROMOTERS AND BUILDERS
Location
Bhugaon, Pune · 412115
Project type
Residential / Group Housing
Registered on
23 Jul 2017
Completion date at registration
May 2021
Latest completion date
March 2028
Delay so far
78 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Swagat Nandanvan Park, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NANDANVAN PARK100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Swagat Nandanvan Park every 1–2 months.

Swagat Nandanvan Park: buildings, flats and land, as filed on MahaRERA

  • Buildings: NANDANVAN PARK (8 floors)
  • Land: 2,000 sq m (about 0.5 acres) · sanctioned built-up 1,982 sq m · recreational space 200 sq m
  • Land, as filed: 262/5/2A
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Swagat Nandanvan Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Swagat Nandanvan Park: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Swagat Nandanvan Park

What is the possession date of Swagat Nandanvan Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Swagat Nandanvan Park in Bhugaon, Pune is 23 March 2028 — 78 months later than 28 May 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 78 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Swagat Nandanvan Park?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Swagat Nandanvan Park's builder has filed on MahaRERA, the official one, is 23 March 2028, already 78 months later than the 28 May 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Swagat Nandanvan Park extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park's builder applied to MahaRERA to extend the completion date 5 times: to 28 May 2022, giving the reason "We Swagat Developers and Builder had registered out Real Estate project viz. ‘Nandanvan Park’ with you under Project Registration No. P5210000084. The Project Completion Date is 28.05.2021. Though the structural and site development is completed in full , due to labor and material shortage owing to ‘ Global Pandemic’ and ‘Recent Lockdown’ few actions like OC and Handover is still pending. We require some more time to finish the project and complete paper work for Handover to Association of Allottee In Light of above fact we request you to grant us 1 year extension for project completion and…"; to 20 November 2023, giving the reason "As on 21.11.2022 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) Delay in receipt of NOC from Ministry of Civil Aviation about building height permission 2) Fire NOC not yet received in respect of completion of the project from Fire Officer There is time required for getting documents compliance to get completion certificate for remaining 6 flats at 6th Floor, you are reques…"; to 26 November 2024, giving the reason "As on 27.11.2023 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA. There is time required for getting documents compliance to get completion certificate for remaining 6 flats…"; to 25 November 2025, giving the reason "As on 19.12.2024 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA."; to 23 November 2027, giving the reason "As on 10.08.2026 we have obtained part completion certificate of the project up to 5th floor for 29 Flats from the PMRDA, Pune. The completion certificate of the remaining flats i.e. 6th floor 6 Flats are not yet received from PMRDA, Pune, which is pending due to following reasons 1) There is technical issue regarding handing over amenity space of the project to the PMRDA. 2) There is technical issue regarding TDR of annex road to the Project due to revision in new ring road by PMRDA. The above mentioned technical issue not resolved from PMRDA department till date.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Swagat Nandanvan Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Swagat Nandanvan Park in Bhugaon, Pune is P52100000846.

Is Swagat Nandanvan Park registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park is registered as P52100000846 and its status is "Registered and active".

What is the current construction status of Swagat Nandanvan Park? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NANDANVAN PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Swagat Nandanvan Park have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Swagat Nandanvan Park safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park is registered on MahaRERA as P52100000846, its completion date has moved 78 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Swagat Nandanvan Park?

Swagat Nandanvan Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Swagat Nandanvan Park?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Swagat Nandanvan Park: gharkundli.com/tools/property-cost-calculator

Has Swagat Nandanvan Park received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park is still under construction, with 23 March 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Swagat Nandanvan Park uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Swagat Nandanvan Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Swagat Nandanvan Park's possession date changes?

The latest dates are on Swagat Nandanvan Park's MahaRERA page (P52100000846). GharKundli's Kundli Watch sends a free WhatsApp update on Swagat Nandanvan Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Swagat Nandanvan Park have?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park has one building filed: NANDANVAN PARK with 8 floors.

How big is the land of Swagat Nandanvan Park?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park stands on 2,000 sq m of land (about 0.5 acres), with 1,982 sq m of sanctioned built-up area and 200 sq m of recreational open space.

What are the reviews of Swagat Nandanvan Park?

Google Maps has reviews of Swagat Nandanvan Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Swagat Nandanvan Park?

Swagat Nandanvan Park by SWAGAT PROMOTERS AND BUILDERS is in Bhugaon, Pune, pincode 412115 (near Pirangut), Maharashtra, and is registered on MahaRERA as P52100000846, per GharKundli's check of MahaRERA records. Its land is filed as 262/5/2A. GharKundli lists all 237 MahaRERA projects in Pirangut (412115).

When was Swagat Nandanvan Park registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Swagat Nandanvan Park was registered on MahaRERA on 23 July 2017. GharKundli did not find a title report on the land on file there.

Does Swagat Nandanvan Park have any legal issues or court cases?

No court cases are listed for Swagat Nandanvan Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Swagat Nandanvan Park?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SWAGAT PROMOTERS AND BUILDERS.

All projects with possession due in 2028 in Pune →

Other projects in Pirangut (412115)

All 237 projects in Pirangut (412115) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.