SHANKARVINAYAK APARTMENT

by A AND D CONSTRUCTION · Balewadi, PuneAlso near Baner, Mahalunge, N.I.A

Possession: SHANKARVINAYAK APARTMENT is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100016973. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about SHANKARVINAYAK APARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHANKARVINAYAK APARTMENT has moved

  1. 18 December 2020

    Completion date given when the project was registered

  2. 31 July 2021

    Extended at the builder's request (MahaRERA application EXT52100009057)

    Reason the builder gave MahaRERA: “THERE WERE CHANGES IN PNE MUNICIPAL CORPORATION NORMS AND WE HAD PRIVILEGE OF TDR FROM CORPORATION”
  3. 28 December 2022

    Extended at the builder's request (MahaRERA application EXT52100010678)

    Reason the builder gave MahaRERA:
    “We have applied for extension of the said project on 05/08/2021 having application no. EXT52100010678. As per order No. 24/2021 our project is under lapse category and we want to apply for extension for the said project till completion date…” Read the full reason“We have applied for extension of the said project on 05/08/2021 having application no. EXT52100010678. As per order No. 24/2021 our project is under lapse category and we want to apply for extension for the said project till completion date only (i.e. 28/12/2022 ). Accordingly, we have uploaded Form 4 and OC's received in part on rera portal and declaration for extension is also uploaded while applying for extension. Therefore, kindly consider our application and grant us extension till completion date. Also, please find attached the Form 4, Occupancy certificates (received in 2 part), Appl…”

Source: SHANKARVINAYAK APARTMENT’s extension records on MahaRERA (P52100016973), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHANKARVINAYAK APARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100016973
Status
Completed
Builder
A AND D CONSTRUCTION
Location
Balewadi, Pune · 411045
Project type
Residential / Group Housing
Registered on
26 Jun 2018
Completion date at registration
December 2020
Latest completion date
December 2022
Delay so far
24 months
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of SHANKARVINAYAK APARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHANKARVINAYAK APARTMENT100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHANKARVINAYAK APARTMENT every month.

SHANKARVINAYAK APARTMENT: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHANKARVINAYAK APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHANKARVINAYAK APARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHANKARVINAYAK APARTMENT

What is the possession date of SHANKARVINAYAK APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHANKARVINAYAK APARTMENT in Balewadi, Pune is 28 December 2022 — 24 months later than 18 December 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHANKARVINAYAK APARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHANKARVINAYAK APARTMENT's builder has filed on MahaRERA, the official one, is 28 December 2022, already 24 months later than the 18 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHANKARVINAYAK APARTMENT extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT's builder applied to MahaRERA to extend the completion date 2 times: to 31 July 2021, giving the reason "THERE WERE CHANGES IN PNE MUNICIPAL CORPORATION NORMS AND WE HAD PRIVILEGE OF TDR FROM CORPORATION"; to 28 December 2022, giving the reason "We have applied for extension of the said project on 05/08/2021 having application no. EXT52100010678. As per order No. 24/2021 our project is under lapse category and we want to apply for extension for the said project till completion date only (i.e. 28/12/2022 ). Accordingly, we have uploaded Form 4 and OC's received in part on rera portal and declaration for extension is also uploaded while applying for extension. Therefore, kindly consider our application and grant us extension till completion date. Also, please find attached the Form 4, Occupancy certificates (received in 2 part), Appl…".

What is the RERA number of SHANKARVINAYAK APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHANKARVINAYAK APARTMENT in Balewadi, Pune is P52100016973.

Is SHANKARVINAYAK APARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT is registered as P52100016973 and its status is "Completed".

What is the construction status of SHANKARVINAYAK APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT's status on MahaRERA is "Completed". As filed by the builder, slab work on SHANKARVINAYAK APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SHANKARVINAYAK APARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SHANKARVINAYAK APARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT is registered on MahaRERA as P52100016973, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHANKARVINAYAK APARTMENT's possession date changes?

The latest dates are on SHANKARVINAYAK APARTMENT's MahaRERA page (P52100016973). GharKundli's Kundli Watch sends a free WhatsApp update on SHANKARVINAYAK APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHANKARVINAYAK APARTMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT has one building filed: SHANKARVINAYAK APARTMENT with 7 floors.

How big is the land of SHANKARVINAYAK APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT stands on 453 sq m of land (about 0.1 acres), with 481 sq m of sanctioned built-up area.

Where can I read reviews of SHANKARVINAYAK APARTMENT?

Google Maps has reviews of SHANKARVINAYAK APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHANKARVINAYAK APARTMENT?

SHANKARVINAYAK APARTMENT by A AND D CONSTRUCTION is in Balewadi, Pune (pincode 411045), near Baner, Mahalunge, N.I.A, Maharashtra, and is registered on MahaRERA as P52100016973, per GharKundli's check of MahaRERA records.

How many homes are in SHANKARVINAYAK APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT has 14 homes in 1 tower registered on MahaRERA.

When was SHANKARVINAYAK APARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHANKARVINAYAK APARTMENT was registered on MahaRERA on 26 June 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on SHANKARVINAYAK APARTMENT?

No court cases are listed for SHANKARVINAYAK APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHANKARVINAYAK APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is A AND D CONSTRUCTION, which has 1 other project registered on MahaRERA.