Possession date of Sanskruti Heights (MahaRERA P99000009831): 14 January 2021, moved from 15 July 2019 (18 months later), and it has already passed. It has 53 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000009831. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P99000009831, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (January 2021) has passed.

What do you want to know about Sanskruti Heights?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sanskruti Heights has moved

  1. 15 July 2019

    Completion date given when the project was registered

  2. 14 July 2020

    Extended at the builder's request (MahaRERA application EXT99000002148)

    Reason the builder gave MahaRERA: “DUE TO CHANGE IN ENVIRONMENMT NORMS.”
  3. 14 January 2021

    Revised completion date on MahaRERA

Source: Sanskruti Heights’s extension records on MahaRERA (P99000009831), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sanskruti Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000009831
Status
Lapsed (registration period ended)
Builder
SHREE SAI ENTERPRISES
Location
Nallasopara, Palghar · 401203
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
July 2019
Latest completion date
January 2021
Delay so far
18 months
Homes
53
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
8

Construction progress of Sanskruti Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SANSKRUTI HEIGHTS WING B100%100%100%97%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sanskruti Heights every 1–2 months.

Sanskruti Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sanskruti Builder AND Developer (a group of 8 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 9 still being built, 3 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Sanskruti Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sanskruti Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sanskruti Heights

What is the possession date of Sanskruti Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sanskruti Heights in Nallasopara, Palghar is 14 January 2021 — 18 months later than 15 July 2019, the date given at registration. That date has already passed.

The date has already moved 18 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sanskruti Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sanskruti Heights's builder has filed on MahaRERA, the official one, is 14 January 2021, already 18 months later than the 15 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sanskruti Heights extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights's builder applied to MahaRERA to extend the completion date once: to 14 July 2020, giving the reason "DUE TO CHANGE IN ENVIRONMENMT NORMS.".

What is the RERA number of Sanskruti Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sanskruti Heights in Nallasopara, Palghar is P99000009831.

Is Sanskruti Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights is registered as P99000009831 and its status is "Lapsed (registration period ended)".

What is the current construction status of Sanskruti Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SANSKRUTI HEIGHTS WING B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Sanskruti Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Sanskruti Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights is registered on MahaRERA as P99000009831, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sanskruti Heights?

Sanskruti Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sanskruti Heights?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sanskruti Heights: gharkundli.com/tools/property-cost-calculator

Has Sanskruti Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 14 January 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Sanskruti Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (14 January 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Sanskruti Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Sanskruti Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sanskruti Heights's possession date changes?

The latest dates are on Sanskruti Heights's MahaRERA page (P99000009831). GharKundli's Kundli Watch sends a free WhatsApp update on Sanskruti Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sanskruti Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights has one building filed: SANSKRUTI HEIGHTS WING B with 8 floors.

How big is the land of Sanskruti Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights stands on 236 sq m of land (about 0.1 acres), with 1,399 sq m of sanctioned built-up area and 280 sq m of recreational open space.

What is the track record of Sanskruti Heights's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Builder AND Developer (a group of 8 linked companies) has 11 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 6 months); 9 still being built, 3 past the promised date (typically 6 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sanskruti Heights?

Google Maps has reviews of Sanskruti Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sanskruti Heights?

Sanskruti Heights by SHREE SAI ENTERPRISES (Sanskruti) is in Nallasopara, Palghar, pincode 401203 (near Nilemore, Bhayandar East, Virar), Maharashtra, and is registered on MahaRERA as P99000009831, per GharKundli's check of MahaRERA records. Its land is filed as 259. GharKundli lists all 221 MahaRERA projects in Nallasopara West (401203).

How many flats are in Sanskruti Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights has 53 homes in 1 tower registered on MahaRERA.

When was Sanskruti Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sanskruti Heights was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Does Sanskruti Heights have any legal issues or court cases?

No court cases are listed for Sanskruti Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Sanskruti Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHREE SAI ENTERPRISES, the company Sanskruti files this project under, which has 8 other projects registered on MahaRERA.

Other projects in Nallasopara West (401203)

All 221 projects in Nallasopara West (401203) →

Other projects by SHREE SAI ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.